Fund Name: NIGAM NIDHI 2024-25
SRNOWORK IDWORK ORDER NOWORK NAMEESTIMATE COST & DATETENDER AMOUNT & DATEAGREEMENT DATE & ACTUAL WORK START DATETARGET DATE OF WORK COMPLETIONCONTRACTOR NAME & PHONE NO.ENG. NAME AND PHONE NOFUND NAMESTATUSWork ProgressZoneWardInspection Before StartInspection In-ProgressInspection After CompelitionWORK STATUS REASON
1 🔗 1 28Remaining plumbing work in Uttaranchal Bhawan. 7.70 20/01/2024 7.70 11 Jun 202418 Jul 2024 18 Jul 2024 Arun Const.Co. NAGENDRA SHARMAJunior Engineer NIGAM NIDHI 2024-25Completed
100%
CITY ZONE    
2 🔗 2 58Street construction work with drain and interlocking tiles in the street of Smt. Chanchal Chauhan in Ward-60 Shyampur Main. 21.24 02/03/2024 21.24 01 Aug 202421 Sep 2024 21 Sep 2024 Yes Enter. NAGENDRA SHARMAJunior Engineer NIGAM NIDHI 2024-25Completed
100%
MOHAN NAGAR Shyampark main  
3 🔗 3 27Sliding, door railing, paint on doors and ACP sheet etc. remaining work in Uttaranchal Bhawan. 9.77 20/01/2024 9.77 11 Jun 202418 Jul 2024 18 Jul 2024 Arun Const.Co. NAGENDRA SHARMAJunior Engineer NIGAM NIDHI 2024-25Completed
100%
CITY ZONE    
4 🔗 4 48Construction of 04 additional platforms, tin shed work, interlocking tiles and gate at the cremation ground in Ward-37 Shalimar Garden Main. 24.20 02/03/2024 24.20 08 Jul 202420 Aug 2024 20 Aug 2024 P.S. Consaltance Vinod KumarJunior Engineer NIGAM NIDHI 2024-25In Progress
20.00%
MOHAN NAGAR Shalimar Garden Main  
5 🔗 5 32Construction work of secondary point for C&D waste in the empty plot adjacent to RRTS Metro station in Ward-61 under Vasundhara Zone. 3.64 25/05/2024 3.64 01 Aug 202424 Sep 2024 24 Sep 2024  Sanjay Gangwar 8178016821 Junior Engineer NIGAM NIDHI 2024-25Completed
100%
VASUNDHRAVasundhra-2  
6 🔗 6 32In view of the Kanwad Yatra in the city zone, barricading work is being done from Mahamaya flyover to Hindon Bridge under the Thakurdwara flyover, in the Sai Upvan temple complex and from Shri Dudheshwarnath temple to the clock tower gate and other places. 9.77 03/07/2024 9.77 08 Jul 202429 Jul 2024 20 Jul 2024  NAGENDRA SHARMA 8882460223 Junior Engineer NIGAM NIDHI 2024-25Completed
100%
CITY ZONEDeendayal Puri View View View  
7 🔗 7 26Construction work of drain and culvert in front of GDA market in Ward-47, Shastrinagar F-block. 4.01 29/06/2024 4.01 08 Jul 2024 01 Aug 2024 KESHRAM CONSTRUCTIONS 9910458482GANESHI LAL 8178016823 Junior Engineer NIGAM NIDHI 2024-25Completed
100%
KAVI NAGARShastrinagar Mahendra Encalave  
8 🔗 8 32Work of interlocking tiles from Pushpram Sadan house to Pramod Kumar house in Ward 16, Vardhamanpuram. 7.10 29/06/2024 7.10 08 Jul 202402 Sep 2024 02 Sep 2024  GANESHI LAL 8178016823 Junior Engineer NIGAM NIDHI 2024-25Completed
100%
KAVI NAGARMorta  
9 🔗 9 36Interlocking tiles work in Ward-46, Mainapur from Mudit's shop/Satish's house via Tilak Ram Tyagi's house to Madhuban Bapudham Road. 28.22 25/06/2024 28.22 08 Jul 202423 Sep 2024 23 Sep 2024 KESHRAM CONSTRUCTIONS 9910458482Rajender Singh 8178016904 Junior Engineer NIGAM NIDHI 2024-25Completed
100%
KAVI NAGARGuldhar Duhai  
10 🔗 10 21Repair of damaged road on Pipeline Road and gravelling work on side track. 29.48 03/07/2024 29.48 08 Jul 202420 Jul 2024 22 Jul 2024  Rajender Singh 8178016904 Junior Engineer NIGAM NIDHI 2024-25Completed
100%
KAVI NAGARMorta  
11 🔗 11 otherRepair work of culvert at RDC cut in Ward 84, Rajnagar and drain in front of Asal Sumaglam, Shivam. 4.97 24/05/2024 4.97 08 Jul 2024 09 Aug 2024  Rajender Singh 8178016904 Junior Engineer NIGAM NIDHI 2024-25Completed
100%
KAVI NAGARRajNagar  
12 🔗 12 33Construction work of CC road and drain from E-6 to E-7/7 in Ward-96, Nehrunagar Third E-Block. 8.07 11/06/2024 8.07 08 Jul 202409 Aug 2024 09 Aug 2024 Pramood Kumar Singhal Preeti BansalJunior Engineer NIGAM NIDHI 2024-25Completed
100%
CITY ZONE Nehru Nagar 3  
13 🔗 13 28Improvement work by interlocking tiles in single storey C-101 to C-106, C-91 to C-95 and C-90 to C-86 in Ward-68, Brajvihar. 8.22 11/06/2024 8.22 08 Jul 202421 Sep 2024 21 Sep 2024 V K CONTRACTOR 7982481495Sanjay Gangwar 8178016821 Junior Engineer NIGAM NIDHI 2024-25Completed
100%
VASUNDHRABrijvihar  
14 🔗 14 39Improvement work through drain and C.C. in the damaged street from H.No.-89 to Nanak Chand's house in Rajbagh Colony, Ward-70, Janakpuri. 12.67 22/06/2024 12.67 08 Jul 202407 Aug 2024 07 Aug 2024 A.V. Enter. Vinod KumarJunior Engineer NIGAM NIDHI 2024-25Completed
100%
MOHAN NAGAR Janakpuri  
15 🔗 15 45Construction work of drain and street through C.C. on both sides from C-157 Hanuman Bansal's building to C-265 in C-block, lane no. 08, ward-70, Janakpuri. 13.57 05/07/2024 13.57 08 Jul 202414 Aug 2024 14 Aug 2024 Aasutos Const. Vinod KumarJunior Engineer NIGAM NIDHI 2024-25Completed
100%
MOHAN NAGAR Janakpuri  
16 🔗 16 21Repair work of damaged road from Suryanagar Police Chowki to Liquor Emporium Wine Shop, Ward-97, under Vasundhara Zone on 311 Smart City App by Dense. 7.08 11/06/2024 7.08 08 Jul 202408 Aug 2024 08 Aug 2024  POOJA SINGH 8178016909 Junior Engineer NIGAM NIDHI 2024-25Completed
100%
VASUNDHRARamprasth  
17 🔗 17 26Repair and painting work of damaged dividers in Ward-89,76,77 in Vasundhara Zone on complaint received on 311 Smart City App. 9.12 25/06/2024 9.12 08 Jul 202422 Aug 2024 22 Aug 2024 V.K. Contr. Sanjay GangwarJunior Engineer NIGAM NIDHI 2024-25Completed
100%
VASUNDHRA    
18 🔗 18 otherRoad improvement work by RCC drain and CC from Dr. Bengali Clinic to Arun Medical on complaint on 311 Smart City App under Vasundhara Zone. 6.32 24/05/2024 6.32 08 Jul 2024  Mahalaxmi Infra. Sanjay GangwarJunior Engineer NIGAM NIDHI 2024-25Completed
100%
VASUNDHRA    
19 🔗 19 35Repair work of damaged road from D-206 to D.V. Medical in Ward-97, Ramprastha under Vasundhara Zone on 311 Smart City App by DANS. 5.61 11/06/2024 5.61 05 Sep 202406 Nov 2024 09 Oct 2024 RG BuildTech Engg. Sanjay GangwarJunior Engineer NIGAM NIDHI 2024-25Completed
100%
VASUNDHRA    
20 🔗 20 59Repair work of damaged road by patching in Ward-89, 76, 77 in Vaishali under Vasundhara Zone on complaint received on Smart City App No. 311. 5.56 18/06/2024 5.56 05 Aug 202415 Oct 2024 10 Oct 2024 RG BuildTech Engg. Sanjay GangwarJunior Engineer NIGAM NIDHI 2024-25Completed
100%
VASUNDHRA    
21 🔗 21 60Repair work of damaged road by patching based on complaint received on 311 Smart City App under Vasundhara Zone. 9.97 11/06/2024 9.97 05 Sep 202402 Dec 2024 10 Oct 2024 Kamlesh Engg. Sanjay GangwarJunior Engineer NIGAM NIDHI 2024-25Completed
100%
VASUNDHRA    
22 🔗 22 35Construction work of interlocking tiles on the road in front of Ret Mandi Community Centre, Ward 49, Nandgram Road. 10.00 19/06/2024 10.00 25 Jun 2024 10 Sep 2024 Anuj kumar Contr. Preeti BansalJunior Engineer NIGAM NIDHI 2024-25Completed
100%
CITY ZONE Nandgram Mariyam Nagar  
23 🔗 23 143Work of two seater toilet and one urinal in front of the power house at Ward 09 Lal Chowk. 4.31 19/06/2024 4.31 07 Oct 202430 Dec 2024 30 Dec 2024  Preeti Bansal 8433403327 Junior Engineer NIGAM NIDHI 2024-25Completed
100%
CITY ZONESibbanpura Patel marg  
24 🔗 24 125Road improvement work by Danes from Shaheed Ashfaqulla Khan to Ramzan Hotel on Ward 95 Kaila Bhatta Main Road. 9.84 22/07/2024 9.84 05 Sep 2024 14 Oct 2024 Prateek Enter. Preeti BansalJunior Engineer NIGAM NIDHI 2024-25Completed
100%
CITY ZONE Premnagar Kaila  
25 🔗 25 138In Ward 01 Krishnanagar Bagu, from Pawan Sharma's house to Ravindra Sharma's house, from Mahesh Sharma Girish Raghav's house, from Ramveer to Devdutt Shri Kumar to Narendra Yadav's house, repair of drains and improvement work of damaged road by C.C. road. 9.03 13/06/2024 9.03 26 Nov 2024 24 Dec 2024 PRADHAN CONTRACTOR 9625326078SHIV KUMAR SAROJ 8178016826 Junior Engineer NIGAM NIDHI 2024-25Completed
100%
VIJAY NAGARBagu Kischayan Nagar  
26 🔗 26 57Supply of precast concrete drain cover in Mohannagar zone. 9.95 11/06/2024 9.95 01 Aug 202418 Sep 2024 18 Sep 2024 P.S. Consaltance Vinod KumarJunior Engineer NIGAM NIDHI 2024-25Completed
100%
MOHAN NAGAR    
27 🔗 27 32Road and drain construction work through interlocking tiles in the damaged street from Mohan Provision Shop in Ward-07 Sudamapuri D-Block via Kanti Memorial School to Satveer Pal's house. 13.96 22/06/2024 13.96 01 Aug 202403 Sep 2024 03 Sep 2024 Yes Enter. SHIV KUMAR SAROJJunior Engineer NIGAM NIDHI 2024-25Completed
100%
VIJAY NAGARBihariPura Sudamapuri  
28 🔗 28 129Work of installing wire fencing on the side tracks of the newly constructed road from the Gurudwara to the corner in front of Allahabad Bank in Ward 72, Vaishali Sector 1. 13.49 18/10/2020 13.49 01 Aug 202430 Dec 2024 30 Dec 2024 ZUBER CONSTRUCTION CO 9350508259Sanjay Gangwar 8178016821 Junior Engineer NIGAM NIDHI 2024-25Completed
100%
VASUNDHRAKaushambhi  
29 🔗 29 30Repair of damaged road, drain and interlocking tiles from Sunil to Saurabh, Ashok to Gaur, Rana Sagaram School to Satveer's house in Ward-27, Shanti Nagar. 8.43 06/02/2024 8.43 01 Aug 202409 Aug 2024 09 Aug 2024 Nikhil Asso. SHIV KUMAR SAROJJunior Engineer NIGAM NIDHI 2024-25Completed
100%
VIJAY NAGARDundaheda  
30 🔗 30 33Work of constructing parapet wall of damaged drain in front of Neelam Dharmkanta, Ward-27. 8.72 04/07/2024 8.72 01 Aug 202406 Sep 2024 06 Sep 2024  Nagendra Kumar Sharma 9927045275 Junior Engineer NIGAM NIDHI 2024-25Not Started
0.00%
VIJAY NAGARDundaheda स्थल पर नाला निर्माण कार्य प्रस्तावित है।
31 🔗 31 31Road improvement work by interlocking tiles on the damaged road from H.No. 882 to H.No. 945 in Ward-01, Bhimnagar Street No. 09 under Vijayanagar Zone. 2.30 18/07/2024 2.30 01 Aug 202412 Sep 2024 12 Sep 2024 J.P. Shakti Const. SHIV KUMAR SAROJJunior Engineer NIGAM NIDHI 2024-25Completed
100%
VIJAY NAGARBagu Kischayan Nagar  
32 🔗 32 115Patch repair work of damaged road near Sahibabad Station Road and Jal Nigam Colony Road and Shani Temple near Chhath Ghat in Ward-60, Shyampur Main. 9.99 18/07/2024 9.99 05 Apr 202404 Dec 2024 10 Oct 2024 Kamlesh Engg. Sanjay GangwarJunior Engineer NIGAM NIDHI 2024-25Completed
100%
MOHAN NAGAR Shyampark main  
33 🔗 33 56Construction work of damaged culvert in front of Dr. Taru Singh's clinic in Ward-80, Rajendra Nagar Sector-02 through RCC. 4.31 18/07/2024 4.31 01 Aug 2024 10 Sep 2024 Anuj kumar Contr. Vinod KumarJunior Engineer NIGAM NIDHI 2024-25Completed
100%
MOHAN NAGAR Rajendra Nagar Sec2  
34 🔗 34 36In Ward-31, Subhash Nagar, from Dushyant's house to Subhash Chand's house via Radheshyam's house and Dr. Upadhyay's street and from Suresh Chand Sharma's house to Panna's house and from K.S. Memorial School to Chhote Lal Upadhyay's house, work of C.C.C. and drain. 18.14 12/07/2024 18.14 01 Aug 2024 17 Sep 2024 Zuber Const. NAGENDRA SHARMAJunior Engineer NIGAM NIDHI 2024-25Completed
100%
CITY ZONE Nandgram Sihani  
35 🔗 35 33Road construction work by interlocking tiles in Ward-56, Malti Colony. 28.14 12/07/2024 28.14 01 Aug 2024 17 Sep 2024  Rajender Singh 8178016904 Junior Engineer NIGAM NIDHI 2024-25Completed
100%
KAVI NAGARChiranjeev Vihar  
36 🔗 36 37Work of drain and interlocking tiles in Sardar Wali Gali, from Kailash's house to Yashoda's house in Ward-32, Harvanshnagar Krishnanagar. 2.33 19/07/2024 2.33 01 Aug 2024 19 Sep 2024  NAGENDRA SHARMA 8882460223 Junior Engineer NIGAM NIDHI 2024-25Completed
100%
CITY ZONEKrishna Nagar  
37 🔗 37 60Drain repair work in front of SB-10 in Ward-47, Shastri Nagar. 1.56 25/07/2024 1.56 05 Sep 202422 Jan 2025 09 Oct 2024 A3R Enterprise 9871999403Rajender Singh 8178016904 Junior Engineer NIGAM NIDHI 2024-25Completed
100%
KAVI NAGARShastrinagar Mahendra Encalave  
38 🔗 38 62Construction work of CC road and drain in Ward-95, adjacent to Markaz Mosque. 1.96 21/06/2024 1.96 05 Sep 2024 09 Oct 2024  NAGENDRA SHARMA 8882460223 Junior Engineer NIGAM NIDHI 2024-25Completed
100%
CITY ZONEPremnagar Kaila  
39 🔗 39 34Repair work of toilets on ground floor and first floor near Hon'ble Court. 9.63 23/07/2024 9.63 01 Aug 202421 Sep 2024 21 Sep 2024  Rajender Singh 8178016904 Junior Engineer NIGAM NIDHI 2024-25Completed
100%
KAVI NAGARMorta  
40 🔗 40 35Repair work of toilets on the second and third floors near Hon'ble Court. 5.50 23/07/2024 5.50 01 Aug 2024 23 Sep 2024  Rajender Singh 8178016904 Junior Engineer NIGAM NIDHI 2024-25Completed
100%
KAVI NAGARMorta  
41 🔗 41 otherRepair work of damaged street from Dr. Subhash's house to Shiv Kumar's house and from Chandra Kiran's house to Subhash's house in Ward-07, Sarvodaya Nagar by laying interlocking tiles and drain repair work. 12.00 17/06/2024 12.00 01 Aug 2024  ZUBER CONSTRUCTION CO 9350508259Nagendra Kumar Sharma 9927045275 Junior Engineer NIGAM NIDHI 2024-25Not Started
0.00%
VIJAY NAGARBihariPura Sudamapuri उक्त स्थल पर सम्पत्ति सम्बन्धी विवाद था। जिस पर सम्पत्ति विभाग की आख्या के अधार पर कार्य निरस्त किया गया।
42 🔗 42 38Construction work of interlocking tiles road from H.No. 60 to H.No. 65 in Ward-39, Nehrunagar Third H-Block. 2.38 29/07/2024 2.38 01 Aug 202420 Sep 2024 20 Sep 2024  Preeti Bansal 8433403327 Junior Engineer NIGAM NIDHI 2024-25Completed
100%
CITY ZONENarsirpur  
43 🔗 43 58Repair work through drain and CCC in the damaged street from H.No. D-74 to Maurya ji's house in D-block, Ward-70, Janakpuri. 16.66 29/07/2024 16.66 01 Aug 202423 Sep 2024 23 Sep 2024 R.R. Const. Vinod KumarJunior Engineer NIGAM NIDHI 2024-25Completed
100%
MOHAN NAGAR Janakpuri  
44 🔗 44 54Construction work of damaged drain in front of ITS College from Shani Mandir to Petrol Pump in Ward-38, Arthala by RCC. 29.89 19/07/2024 29.89 01 Aug 202410 Sep 2024 10 Sep 2004 Prateek Enter. Sanjay GangwarJunior Engineer NIGAM NIDHI 2024-25Completed
100%
MOHAN NAGAR Atharla  
45 🔗 45 46Work of drain and interlocking tiles from Devendra Ghodi Wale to Anil Pandit's house in Ward 53, Raispur. 5.62 25/07/2024 5.62 05 Sep 2024 04 Oct 2024 A S CONSTRUCTIONS (AAQFA8231R) 8630570065Rajender Singh 8178016904 Junior Engineer NIGAM NIDHI 2024-25Completed
100%
KAVI NAGARRaishpur  
46 🔗 46 48Work of interlocking tiles from Sampat Singh's house to Yatyavati's house near Shiva temple in Ward 46, Peepal Wali Colony. 4.72 30/07/2024 4.72 05 Sep 202415 Oct 2024 04 Oct 2024 J S S CONSTRUCTION 9999280744Rajender Singh 8178016904 Junior Engineer NIGAM NIDHI 2024-25Completed
100%
KAVI NAGARGuldhar Duhai  
47 🔗 47 41Work of drain and interlocking tiles from Kaklu's house to Sheeshpal's house in Ward 53, Raispur. 3.61 25/07/2024 3.61 05 Sep 202414 Oct 2024 04 Oct 2024 VINOD KUMAR CONTRACTOR 9278081661Rajender Singh 8178016904 Junior Engineer NIGAM NIDHI 2024-25Completed
100%
KAVI NAGARRaishpur  
48 🔗 48 40Construction work of boundary wall and two rooms of Community Centre in Ward 53, Raispur. 29.31 02/08/2024 29.31 05 Sep 2024 04 Oct 2024 A S CONSTRUCTIONS (AAQFA8231R) 8630570065GANESHI LAL 8178016823 Junior Engineer NIGAM NIDHI 2024-25Not Started
0.00%
KAVI NAGARRaishpur  
49 🔗 49 50Work of construction of drain from Punjabi Daba to D.P. Yadav's plot in Ward 24, Shankar Vihar Lal Kuan. 9.98 26/07/2024 9.98 05 Sep 202414 Oct 2024 04 Oct 2024 VANSH CONSTRUCTIONS 9953776458Rajender Singh 8178016904 Junior Engineer NIGAM NIDHI 2024-25Completed
100%
KAVI NAGARMahrouli  
50 🔗 50 45Road improvement work by Danes from K-24 to 37 in K-Block, Ward 67, Sanjay Nagar. 9.38 25/07/2024 9.38 05 Sep 202415 Oct 2024 04 Oct 2024 RG BuildTech Engg. Rajender SinghJunior Engineer NIGAM NIDHI 2024-25Completed
100%
KAVI NAGAR Kamla Nehru Nagar Sanjay Nagar 1  
51 🔗 51 64Repair work of rain water harvesting chambers at various places in Ward 67, Sanjay Nagar P-Block. 8.52 25/07/2024 8.52 05 Sep 202427 Jan 2025 09 Oct 2024 Keshram Const. Rajender SinghJunior Engineer NIGAM NIDHI 2024-25Completed
100%
KAVI NAGAR Kamla Nehru Nagar Sanjay Nagar 1  
52 🔗 52 44Road improvement work by Danes from P-139 to P-150 and P-91 to P-100 in Ward 67, Sanjay Nagar P-Block. 9.83 25/07/2024 9.83 05 Sep 202415 Oct 2024 04 Oct 2024  Rajender Singh 8178016904 Junior Engineer NIGAM NIDHI 2024-25Completed
100%
KAVI NAGARKamla Nehru Nagar Sanjay Nagar 1  
53 🔗 53 98Construction work of C.C. road and drain from primary school to Jeet's house, from Dweepchand Sharma's house to Nandu's house in Ward-31, Sihani. 5.57 07/08/2024 5.57 05 Sep 2024 14 Oct 2024 Prakash Const Preeti BansalJunior Engineer NIGAM NIDHI 2024-25Completed
100%
CITY ZONE Nandgram Sihani  
54 🔗 54 115Construction work of drain and interlocking tiles in Ward-32, Harvansh Nagar from Bhagwat Thekedar to Ramesh's house via Pawan's house and in Rajaram Wali Gali. 7.75 19/07/2024 7.75 05 Sep 202415 Jan 2025 14 Oct 2024 J P Sakti Preeti BansalJunior Engineer NIGAM NIDHI 2024-25Completed
100%
CITY ZONE Krishna Nagar  
55 🔗 55 97Construction work of CC road and drain from Banwari's house to the front of Naveen Tyagi and Ishwar Tyagi's house in Ward-31, Sihani. 1.53 12/08/2024 1.53 05 Sep 202404 Feb 2025 14 Oct 2024 Shree Balaji Enterp. Preeti BansalJunior Engineer NIGAM NIDHI 2024-25Completed
100%
CITY ZONE Nandgram Sihani  
56 🔗 56 101Construction of culvert and ramp near the houses of Vijay Sharma, Kavya Beauty Parlour, H.No. 211, Anil, Balkishan, Thakur Properties, Munshi, building owner Sanjay, Raju, Phoolbabu, Pawan, Vinod, Monu, Sumit and Vinod Kumar in Ward-11, Nandagram New Basti Bombay Colony. 4.12 12/08/2024 4.12 05 Sep 202410 Oct 2024 10 Oct 2024 PRAKASH CONSTRUCTION CO. 9873251928Preeti Bansal 8433403327 Junior Engineer NIGAM NIDHI 2024-25Completed
100%
CITY ZONENandgram, Deendayal puri  
57 🔗 57 47Construction work of CC road and drain from Bachpan Gift Shop to H.No.-09 in Ward-39, Rakesh Marg, R.K. Puram. 7.71 25/07/2024 7.71 05 Sep 202410 Oct 2024 05 Oct 2024 A.S. Const. NAGENDRA SHARMAJunior Engineer NIGAM NIDHI 2024-25Completed
100%
CITY ZONE Narsirpur  
58 🔗 58 43Construction work of CC road and drain from Shri Banke Bihari Hardware Shop to Anil's house in Ward-39, Rakesh Marg, RK Puram. 8.17 25/07/2024 8.17 05 Sep 202410 Oct 2024 05 Oct 2024 A.S. Const. NAGENDRA SHARMAJunior Engineer NIGAM NIDHI 2024-25Completed
100%
CITY ZONE Narsirpur  
59 🔗 59 43Construction work of interlocking tiles road and drain from H.No.-B/323 to Hanuman Temple in Ward-52, New Panchvati. 9.98 18/07/2024 9.98 05 Sep 2024 05 Oct 2024 A.S. Const. Preeti BansalJunior Engineer NIGAM NIDHI 2024-25Completed
100%
CITY ZONE Aryanagar Kotgaon  
60 🔗 60 44Construction work of interlocking tiles road and drain in Ward-52, New Panchvati C-Block from H.No. C/93 to C/98. 9.86 18/07/2024 9.86 05 Sep 2024 05 Oct 2024  Preeti Bansal 8433403327 Junior Engineer NIGAM NIDHI 2024-25Completed
100%
CITY ZONEAryanagar Kotgaon  
61 🔗 61 103Construction work of CC road and drain from in front of the temple to Jain Sahab's house in Ward-22, Radhakunj Enclave. 9.95 25/07/2024 9.95 05 Sep 2024 14 Oct 2024 Modern Const.Co. Preeti BansalJunior Engineer NIGAM NIDHI 2024-25In Progress
70.00%
CITY ZONE Daulat Pura  
62 🔗 62 102Construction work of CC road and drain from Baburam's house to H.No.-29 in Ward-22, Radhakunj Enclave. 9.98 25/07/2024 9.98 05 Sep 2024 14 Oct 2024 MODERN CONSTRUCTION CO Preeti Bansal 8433403327 Junior Engineer NIGAM NIDHI 2024-25Completed
100%
CITY ZONEDaulat Pura  
63 🔗 63 74Patch repair work at various places in Wards 22, 33, 39 and 52 of City Zone. 9.82 19/09/2024 9.82 05 Sep 202415 Oct 2024 25 Jul 2024 Prateek Enter. Preeti BansalJunior Engineer NIGAM NIDHI 2024-25Completed
100%
CITY ZONE    
64 🔗 64 41Ward-49, work of interlocking tiles from pre-constructed drain to Diwan Farm. 9.98 28/08/2024 9.98 05 Sep 2024 04 Oct 2024 Anuj kumar Contr. NAGENDRA SHARMAJunior Engineer NIGAM NIDHI 2024-25Completed
100%
CITY ZONE Nandgram Mariyam Nagar  
65 🔗 65 40Ward - 49, Work of interlocking tiles from C&D waste factory to pre-constructed drain. 9.99 14/08/2024 9.99 05 Sep 2024 04 Oct 2024 Anuj kumar Contr. NAGENDRA SHARMAJunior Engineer NIGAM NIDHI 2024-25Completed
100%
CITY ZONE Nandgram Mariyam Nagar  
66 🔗 66 147Repair work through drain and C.C. in the damaged lane from Kismati Devi's house to Priya Beauty Parlour in Indra Garden, Ward-60, Shyampur Main. 6.08 22/07/2024 6.08 05 Sep 202415 Oct 2024 15 Oct 2024 Manveer Singh Cont. Sanjay GangwarJunior Engineer NIGAM NIDHI 2024-25Completed
100%
MOHAN NAGAR Shyampark main  
Fund Name: MEMBER KOTA
67 🔗 67 otherWork of drain and interlocking tiles in the damaged street from Choudhary Jagveer to Satyaveer Choudhary's company in Rajendra Nagar Ind. Area of ​​Ward-60, Shyampur Main. 9.99 22/07/2024 9.99 05 Sep 2024   Vinod KumarJunior Engineer NIGAM NIDHI 2024-25Completed
100%
MOHAN NAGAR Shyampark main  
68 🔗 558 94Work of laying interlocking tiles on the road from Priya Automobile to house no. 200/2 near Ambersaria Bank in Ward 76, Vaishali. 14.97 10/09/2024 14.97 19 Sep 202415 May 2025 15 Oct 2024  POOJA SINGH 8178016909 Junior Engineer MEMBER KOTACompleted
100%
VASUNDHRAVaishali Sec 1  
69 🔗 559 96Work of laying interlocking tiles on the road from house no. 236 to house no. 306 in ward 76, sector 2B, Vaishali. 14.94 10/09/2024 14.94 19 Sep 2024 15 Oct 2024  POOJA SINGH 8178016909 Junior Engineer MEMBER KOTAIn Progress
10.00%
VASUNDHRAVaishali Sec 1  
Fund Name: Smart City
70 🔗 560 91In Ward 77 Sec 3 Vaishali, the road behind Shiv Temple and from Khushi Sweets 920 to Nikhil Egg Store 874 and from 496 to 517 and 445 to 447, road repair work with old interlocking tiles. 14.92 10/09/2024 14.92 19 Sep 2024 15 Oct 2024  POOJA SINGH 8178016909 Junior Engineer MEMBER KOTACompleted
100%
VASUNDHRAVaishali Sec 2  
Fund Name: CM GRID
71 🔗 1278 10Installation of 350 new cameras under City Surveillance Project 245.00 20/10/2024 243.92 27 Feb 202527 Jun 2025 27 Jun 202526 Sep 2025 All JE 0000000000 Junior Engineer Smart CityIn Progress
0.00%
<--Select-->  View View  
72 🔗 1286 02gDevelopment of Roads from Mohan Nagar Bus stand to Airforce Station via Mohan Nagar Chouraha 2332.00 16/03/2024 1688.00 07 Aug 202408 Oct 2024 08 Oct 2024 R& C Infra Engineers Pvt Ltd 8586051107Vinod Kumar 8650930015 Junior Engineer CM GRIDIn Progress
72.00%
MOHAN NAGARKarheda View View  
Fund Name: CM-VNY
73 🔗 1287 02gDevelopment of Road works from Seshnag Gate to Elevated Road 1227.00 13/03/2024 1228.00 07 Aug 202408 Oct 2024 08 Oct 202407 Jan 2026R& C Infra Engineers Pvt Ltd 8586051107Vinod Kumar 8650930015 Junior Engineer CM GRIDIn Progress
50.00%
MOHAN NAGARGagan Vihar View View  
Fund Name: MEMBER KOTA
74 🔗 1288 1308/GM(N-9)/E-Tender/2025Construction of a Working Women's Hostel. 2440.00 28/02/2025 2440.00 21 Mar 202503 Jun 2025 27 Jun 2025 M/s. Mittal Associates Jitendra JauhariJunior Engineer CM-VNY 
0%
CITY ZONE    
Fund Name: NIGAM NIDHI 2024-25
75 🔗 1294 57Work of interlocking tiles on side track from K-70 to K-43 in K-Block, Ward-96, Nehrunagar-Third. 4.24 05/09/2024 4.24 09 Sep 202414 Oct 2024 09 Oct 2024 R.R Const. Preeti BansalJunior Engineer MEMBER KOTACompleted
100%
CITY ZONE Nehru Nagar 3  
76 🔗 1295 39Work of supply and spreading of sand in Ward-91, Kavi Nagar Ramlila Ground. 4.41 02/09/2024 4.41 19 Sep 202409 Oct 2024 01 Oct 2024  Rajender Singh 8178016904 Junior Engineer NIGAM NIDHI 2024-25Completed
100%
KAVI NAGARKavi nagar  
Fund Name: BOARD FUND
77 🔗 1296 153Repair of damaged road from Khemchand to Ramgopal, Sharda's house to Dr. Rakesh, Kiranpal to Shripal in ward-58, Mawai through C.C. 9.20 03/09/2024 9.20 26 Dec 202430 Jan 2025 30 Jan 2025 Ariti Const.Co. SHIV KUMAR SAROJJunior Engineer NIGAM NIDHI 2024-25Completed
100%
VIJAY NAGARShivpuri  
78 🔗 1434 141/Nazarat 2024-25नगर निगम मुख्यालय में नयी लिफ्ट लगाये जाने के साथ-साथ 02 वर्ष का रख-रखाव का कार्य। 26.11 17/08/2024 23.60 20 Aug 202425 Sep 2024 25 Sep 202418 Feb 2025OTHER SUNIL KUMAR MAURYA 8707646842 Junior Engineer BOARD FUNDCompleted
100%
CITY ZONEChandrapuri  
Fund Name: NIGAM NIDHI 2024-25
79 🔗 1490 175/I/Nazarat/2024-25नगर निगम मुख्यालय में लिफ्ट नं-3 को नई लगाये जाने के साथ-साथ 02 वर्ष का रख-रखाव का कार्य। 26.11 21/09/2024 23.90 15 Oct 202415 Oct 2024 15 Oct 202415 Jan 2025SUNIL GARG & CO. 9310488879SUNIL KUMAR MAURYA 8707646842 Junior Engineer BOARD FUNDCompleted
100%
CITY ZONEChandrapuri  
80 🔗 1558  Laying and connecting of 250 meter PVC drinking water pipe line of 110 mm diameter in 06 H.H.I. G. D. A. 04 story flats in Ward No. 086 Rajendra Nagar Sec.-05 under Mohan Nagar Zone. 3.60 3.61 01 Jul 202404 Oct 2024  SUNIL KUMAR Somendra Pratap Singh(mn) 8178016856 Junior Engineer NIGAM NIDHI 2024-25In Progress
0.00%
MOHAN NAGARGagan Vihar  
81 🔗 1559  Laying of 250 m GI drinking water pipeline of 80 mm diameter from Jai Medicos to Lala Jai ​​Singh Pharma and from Ashish Medicos to Ghaziabad Chemist Association via the back gate of Shambhu Dayal College in Ward No. 59 Nai Basti Dawaai Market under City Zone I. 0.00 3.85 05 Jul 2024  Balaji Construction 9999391117Pooja Rai 8178016854 Junior Engineer NIGAM NIDHI 2024-25In Progress
50.00%
CITY ZONEChandrapuri  
82 🔗 1560  Work of laying 4'' diameter PVC drinking water pipeline from C-3 to shop no. 13 and from A-11 to C-32 in Ward-12 Express Market under City Zone-1 3.46 3.46 28 May 2024  Hanumat Enterprises Pooja Rai 8178016854 Junior Engineer NIGAM NIDHI 2024-25Completed
100%
CITY ZONEKalkagadi, Jatavbada  
Fund Name: MEMBER KOTA 2024-25(II)
83 🔗 68 64Construction work of drain on both sides and street through C.C. in Dileen Tripathi street in front of Shiv temple, Ward-70, Janakpuri C-Block. 9.82 26/07/2024 9.82 05 Sep 2024 07 Oct 2024  Vinod Kumar 8650930015 Junior Engineer NIGAM NIDHI 2024-25In Progress
30.00%
MOHAN NAGARJanakpuri  
84 🔗 803  Construction work of RCC drain and CC road in the streets of Manoj, Yogesh Ghumsingh Jagmal in Ward 21 Bhowapur village. 7.39 05/03/2025 7.39 21 Mar 2025   Sanjay Gangwar 8178016821 Junior Engineer MEMBER KOTA 2024-25(II)Completed
100%
VASUNDHRABhoowa Pura  
85 🔗 804  Road and drain construction work through interlocking tiles on the damaged road from Suresh's house to Thakur Deshraj's house and from Vinod's house to Ankit's shop in Ward 58, Sector 09 Shivpuri. 7.45 30/01/2025 7.45 21 Mar 2025  A H CONSTRUCTIONS 9873347860SHIV KUMAR SAROJ 8178016826 Junior Engineer MEMBER KOTA 2024-25(II)Completed
100%
VIJAY NAGARShivpuri  
86 🔗 806  Construction work of CC road and RCC drain from Divya Kirana Store to house no. H/703 and from Tarachand's house to Satendra Singh's house in Ward-03, H Block. 7.72 30/01/2025 7.72 21 Mar 2025  A H CONSTRUCTIONS 9873347860SHIV KUMAR SAROJ 8178016826 Junior Engineer MEMBER KOTA 2024-25(II)Completed
100%
VIJAY NAGARPurana Vijay Nagar  
87 🔗 807  Construction work of drain and interlocking tiles in the damaged street from Vijay Kumar's house to Durvijay's house in Ward No. 05, Gagan Vihar. 7.74 30/01/2025 7.74 21 Mar 2025  Ujjwal Cons. 9625363623Vinod Kumar 8650930015 Junior Engineer MEMBER KOTA 2024-25(II)Completed
100%
MOHAN NAGARGagan Vihar  
88 🔗 808  Construction work of C.C. road and drain in Old Mosque Street and from Surendra's house to Wasim's house in Ward-50, Noor Nagar. 7.83 30/01/2025 7.83 21 Mar 2025  Sachin Builders NAGENDRA SHARMAJunior Engineer MEMBER KOTA 2024-25(II) 
0%
CITY ZONE Saddiknagar, Noornagar  
Fund Name: NIGAM NIDHI 2024-25
89 🔗 809 5Construction work of CC road from house no. A 98 to house no. A 88 in A-block in Ward-97 Ramprastha. 7.98 05/03/2025 7.98 21 Mar 202526 May 2025 26 May 2025  POOJA SINGH 8178016909 Junior Engineer MEMBER KOTA 2024-25(II)Completed
100%
VASUNDHRARamprasth  
Fund Name: MEMBER KOTA 2024-25(II)
90 🔗 69 65Work of drain and street through CCC and culvert through RCC from the corner of Maharana Pratap Park to H.No. 88-1-1 to building no. 50 in Ward-70, Rajbagh. 9.97 26/07/2024 9.97 05 Sep 202412 Nov 2024 07 Oct 2024 Prateek Enter. Vinod KumarJunior Engineer NIGAM NIDHI 2024-25Completed
100%
MOHAN NAGAR Janakpuri  
91 🔗 810  Construction work of drain and C.C. road in the damaged lane from Fayaz's house to Imran's house in ward 90 Shahidnagar III. 8.13 30/01/2025 8.13 21 Mar 2025   Sanjay Gangwar 8178016821 Junior Engineer MEMBER KOTA 2024-25(II)Completed
100%
MOHAN NAGARShahid Nagar 2  
92 🔗 811  Construction work of CC road and RCC drain from Puran Vijayeta's house to Rahul's house in Ward-04, Thana Road D Block. 8.18 30/01/2025 8.18 21 Mar 2025  OTHER SHIV KUMAR SAROJ 8178016826 Junior Engineer MEMBER KOTA 2024-25(II)Completed
100%
VIJAY NAGARSec-12 Mata Colony  
93 🔗 812  Construction work of RCC drain and CC road from Jaiprakash to Roopchand, Vinita to Shripal's house in Ward 07 Shiv Vihar. 8.19 30/01/2025 8.19 21 Mar 2025  OTHER SHIV KUMAR SAROJ 8178016826 Junior Engineer MEMBER KOTA 2024-25(II)Completed
100%
VIJAY NAGARBihariPura Sudamapuri  
94 🔗 813 2Road improvement work by interlocking tiles from near Tikona Park to 448G and from H.No. 311/2 to Public Service Centre in Ward 57, Nyay Khand 2. 8.21 05/03/2025 8.21 21 Mar 202524 May 2025 24 May 2025 SG ENTERPRISES Sanjay Gangwar 8178016821 Junior Engineer MEMBER KOTA 2024-25(II)Completed
100%
VASUNDHRAMakan pur  
95 🔗 814  Construction work of RCC drain and CC road from Manoj to Dharampal's house in Ward 07 Shiv Vihar. 8.22 30/01/2025 8.22 21 Mar 2025  OTHER SHIV KUMAR SAROJ 8178016826 Junior Engineer MEMBER KOTA 2024-25(II)Completed
100%
VIJAY NAGARBihariPura Sudamapuri  
96 🔗 815  Work of construction of drain from the cut of Hydel Colony to KA-39 in Ward 91, Kavi Nagar. 8.24 30/01/2025 8.24 21 Mar 2025  V.S. Buildcon.Co. POOJA SINGHJunior Engineer MEMBER KOTA 2024-25(II) 
0%
VASUNDHRA Kavi nagar  
Fund Name: NIGAM NIDHI 2024-25
97 🔗 816  Ward-08, Maliwada Thakur wali gali, from Jayaprakash to Satendra's house, work of drain and interlocking tiles and drain construction work in Pappu wali gali, Chandrashekhar wali gali, lane opposite Chandrashekhar, Nice Look wali gali, Sundar wali gali, Baba Chaat wali gali, lane no.02, temple wali gali, Dheemar wali gali, well wali gali and other lanes. 8.24 30/01/2025 8.24 21 Mar 202513 Aug 2025 13 Aug 2025  SUNIL KUMAR MAURYA 8707646842 Junior Engineer MEMBER KOTA 2024-25(II)Completed
100%
CITY ZONENehru Nagar 2  
Fund Name: MEMBER KOTA
98 🔗 70 60Construction work of drain and C.C. street and R.C.C. culvert on both sides from Manish Sharma's house to Ramraj Orphanage in Ward-70, Janakpuri, Ramnagar. 9.93 24/07/2024 9.93 05 Sep 2024 07 Oct 2024 Prateek Enter. Vinod KumarJunior Engineer NIGAM NIDHI 2024-25Completed
100%
MOHAN NAGAR Janakpuri  
99 🔗 522 117Repair work of damaged road from Jain temple to the road between Sec 10 and 12 in ward 61 Sec 10 by Danes. 10.95 10/09/2024 10.95 07 Oct 202416 Dec 2024 16 Dec 2024 R G BUILDTECH ENGINEERS LTD 9810616350Sanjay Gangwar 8178016821 Junior Engineer MEMBER KOTACompleted
100%
VASUNDHRAVasundhra-2  
100 🔗 523 104Work of interlocking tiles from C-71 to C-49 via C-59 and from C-95 to C-85 in Ward 62, RK Puram. 27.22 10/09/2024 27.22 19 Sep 202415 Oct 2024 14 Oct 2024  Rajender Singh 8178016904 Junior Engineer MEMBER KOTACompleted
100%
KAVI NAGARGovindpuram Harsav  
101 🔗 524 101Work of construction of RCC drain from C-257 to C-246 in Ward 62, Govindpuram C-Block, Lane No. 07. 16.77 10/09/2024 16.77 19 Sep 202412 Dec 2024 14 Oct 2024  Rajender Singh 8178016904 Junior Engineer MEMBER KOTACompleted
100%
KAVI NAGARGovindpuram Harsav  
102 🔗 525 140Work of drain and CC road in ward 62, Madiya village from Vijendra Singh's house via Amit Rathi's house to Sunil's house. 12.18 10/09/2024 12.18 19 Sep 202412 Dec 2024 15 Oct 2024  Rajender Singh 8178016904 Junior Engineer MEMBER KOTACompleted
100%
KAVI NAGARGovindpuram Harsav  
103 🔗 526 139Construction work by interlocking tiles in the drain and damaged street from the house of Haji Jabruddin to the house of Haji Mohd. Shahjad and from the house of Choudhary Ibrahim to the house of Salman, under ward 63. 20.06 12/09/2024 20.06 19 Sep 202415 Oct 2024 14 Oct 2024 Mohit Choudhary Vinod KumarJunior Engineer MEMBER KOTACompleted
100%
MOHAN NAGAR Pasonda  
104 🔗 527 140Construction work by interlocking tiles in the drain and damaged street from the house of Isaad to the houses of Farooq, Mansoor and Banno under ward 63. 12.34 10/09/2024 12.34 19 Sep 202412 Dec 2024 14 Oct 2024 Ujjwal Const. Vinod KumarJunior Engineer MEMBER KOTACompleted
100%
MOHAN NAGAR Pasonda  
Fund Name: NIGAM NIDHI 2024-25
105 🔗 528 137Construction work of drain and CC road in the damaged street up to the house of Nanak Chand Moharram under ward 63/66. 17.60 12/09/2024 17.60 19 Sep 2024 14 Oct 2024  Vinod Kumar 8650930015 Junior Engineer MEMBER KOTACompleted
100%
MOHAN NAGARPasonda  
Fund Name: MEMBER KOTA
106 🔗 71 189Work of drain and interlocking tiles in the unpaved lane from Sarfaraz's house to Aslam's house in lane no. 12 of Rajiv Colony in Ward-20, Bhaupura. 4.77 15/12/2023 4.77 05 Sep 202410 Feb 2025 10 Feb 2025  Vinod Kumar 8650930015 Junior Engineer NIGAM NIDHI 2024-25Completed
100%
MOHAN NAGARBhaupura  
107 🔗 529 174Construction work of drain and damaged street with interlocking tiles from Yasin's house to Salimuddin's house in Ward 64 Garima Garden. 14.67 12/09/2024 14.67 19 Sep 2024 15 Oct 2024  Vinod Kumar 8650930015 Junior Engineer MEMBER KOTACompleted
100%
MOHAN NAGARGarima Garden  
108 🔗 530 136Construction work of drain and damaged street with interlocking tiles from Dr. Rhees's house to Sarif's house in Ward 64 Garima Garden. 17.27 12/09/2024 17.27 19 Sep 202415 Feb 2025 14 Oct 2024 Anuj kumar Contr. Vinod KumarJunior Engineer MEMBER KOTACompleted
100%
MOHAN NAGAR Garima Garden  
109 🔗 531 107Road improvement work by DANS from KH-124 to KH-107 and KH-92 to KH-70 in Ward 65, Kavi Nagar H-Block. 21.13 10/09/2024 21.13 19 Sep 2024 14 Oct 2024  Rajender Singh 8178016904 Junior Engineer MEMBER KOTACompleted
100%
KAVI NAGARVivekanand Nagar Jeevan Vihar  
110 🔗 532 111Road improvement work by DANS in Ward 65, Kavi Nagar H-Block from KH-145 to KH-135, KH-263 to KH-247, KH-183 to KH-171, KH-220 to KH-198, KH-170 to KH-156. 26.38 10/09/2024 26.38 19 Sep 2024 14 Oct 2024  Rajender Singh 8178016904 Junior Engineer MEMBER KOTACompleted
100%
KAVI NAGARVivekanand Nagar Jeevan Vihar  
111 🔗 533 141Road improvement work by DANS from KH-41 to Railway Ring Road in Ward 65, Kavi Nagar H-Block. 14.24 10/09/2024 14.24 19 Sep 2024 15 Oct 2024  Rajender Singh 8178016904 Junior Engineer MEMBER KOTACompleted
100%
KAVI NAGARVivekanand Nagar Jeevan Vihar  
112 🔗 534 175Improvement work of damaged street from Chaudhary Medical Store to Chaudhary Mustakim's house under Ward No. 66 by providing drain and interlocking. 13.27 12/09/2024 13.27 19 Sep 202412 Nov 2024 15 Oct 2024 Mohit Choudhary Vinod KumarJunior Engineer MEMBER KOTACompleted
100%
MOHAN NAGAR Mausam Vihar  
Fund Name: NIGAM NIDHI 2024-25
113 🔗 535 164Improvement work of the damaged lane from Rahisu's house to Niaz Bhai's house and from Feuji's house to Dr. Nura and from Rajkumar's house to Nasir's house under ward 66 by providing drain and interlocking tiles. 20.40 12/09/2024 20.40 19 Sep 202412 Dec 2024 15 Oct 2024 Ujjwal Const. Vinod KumarJunior Engineer MEMBER KOTACompleted
100%
MOHAN NAGAR Mausam Vihar  
Fund Name: MEMBER KOTA
114 🔗 72 70Repair work through drain and C.C. in the damaged street from the temple to Ramveer's house in Jal Nigam Colony, Ward-60, Shyampur Main. 8.42 26/07/2024 8.42 05 Sep 202428 Nov 2024 07 Oct 2024 Akruti Const. Sanjay GangwarJunior Engineer NIGAM NIDHI 2024-25Completed
100%
MOHAN NAGAR Shyampark main  
115 🔗 536 138Improvement work of damaged street from Deen Maulana's house to Zahid's house under ward 66 by providing drain and interlocking tiles. 16.47 12/09/2024 16.47 19 Sep 2024 14 Oct 2024 Anuj kumar Contr. Vinod KumarJunior Engineer MEMBER KOTACompleted
100%
MOHAN NAGAR Mausam Vihar  
116 🔗 537 119Construction work of RCC drain from J-373 to J-421 and J-514 to J-600 in Ward 67, Sanjay Nagar J-Block. 14.96 10/09/2024 14.96 19 Sep 202415 Oct 2024 15 Oct 2024  Rajender Singh 8178016904 Junior Engineer MEMBER KOTACompleted
100%
KAVI NAGARKamla Nehru Nagar Sanjay Nagar 1  
117 🔗 538 107Improvement work by interlocking tiles in the damaged lanes from single story C-113 to C-130 and C-81 to C-85 in Ward-68 Brajvihar. 11.19 10/09/2024 11.19 19 Sep 202430 Dec 2024 15 Oct 2024 V K CONTRACTOR 7982481495Sanjay Gangwar 8178016821 Junior Engineer MEMBER KOTACompleted
100%
VASUNDHRABrijvihar  
118 🔗 539 172Ward-69, Lohianagar A-block from A-68 to railway line and B-block from B-72 to B-168 in service lane. Work of drain and C.C. and road improvement work by Dans from B-73 to B-86, B-112 to B-105 via B-101. 17.13 10/09/2024 17.13 07 Oct 2024 05 Mar 2025  Preeti Bansal 8433403327 Junior Engineer MEMBER KOTACompleted
100%
CITY ZONELohiya Nagar Lal Qtr  
119 🔗 540 132Work of drain and C.C. in service lane from C-78 to C-154 in Ward-69, Lohianagar C-Block and work of drain and interlocking tiles from Golden Bakery to Saini Compound and in front of Deepak Tyagi in C-Block. 16.36 10/09/2024 16.36 19 Sep 202407 Jan 2025 14 Oct 2024 Modern Const.Co. Preeti BansalJunior Engineer MEMBER KOTACompleted
100%
CITY ZONE Lohiya Nagar Lal Qtr  
120 🔗 541 06-12-2024Work of drain and C.C. road in Ward-69, Lohianagar Lal Quarter from H.No.-53/1 to 53/8 and H.No.-3/1 to 1/1 and H.No.-2/8 to 6/1 and H.No.-8/1 to 8/8. 11.36 10/09/2024 11.36 07 Oct 202423 Mar 1900 09 Dec 2024 A.V. Enter. Preeti BansalJunior Engineer MEMBER KOTACompleted
100%
CITY ZONE Lohiya Nagar Lal Qtr  
Fund Name: NIGAM NIDHI 2024-25
121 🔗 542 159Construction work of drain and C.C. street in ward 70 Janakpuri C. Block from building number C.146 Mangal Sain ji's house to Rajendra Baisaya's house and from B.44 to Gorakh Nath temple. 29.76 12/09/2024 29.76 19 Sep 2024 15 Oct 2024  Vinod Kumar 8650930015 Junior Engineer MEMBER KOTACompleted
100%
MOHAN NAGARJanakpuri  
Fund Name: MEMBER KOTA
122 🔗 73 68Work of interlocking tiles in the damaged street from Sanjay's house to Narendra's house in Durga Colony, Ward-60, Shyampur Main. 6.29 26/07/2024 6.29 05 Sep 2024 07 Oct 2024 JSS Const. Vinod KumarJunior Engineer NIGAM NIDHI 2024-25Completed
100%
MOHAN NAGAR Shyampark main  
123 🔗 543 160Ward 70, Janakpuri A Block, lane no. 4, from A-94 to Raj Bahadur's house to Jagriti Public School and from Councilor's office Manjeet Rana's house to Vishwakarma's house, construction work of drain and C.C. lane. 29.76 12/09/2024 29.76 19 Sep 2024 15 Oct 2024 Prateek Enter. Vinod KumarJunior Engineer MEMBER KOTACompleted
100%
MOHAN NAGAR Janakpuri  
124 🔗 544 115Road improvement work by Danes in Ward 71, Sanjay Nagar E-Block from E-106 to E-116, E-131 to E-116, E-132 to E-150, E-190 to E-95. 14.27 10/09/2024 14.27 19 Sep 2024 15 Oct 2024  Rajender Singh 8178016904 Junior Engineer MEMBER KOTACompleted
100%
KAVI NAGARSanjay Nagar 2  
125 🔗 545 117Road improvement work by DANS from E-569 to Forest Department office in Ward 71, Sanjay Nagar. 12.12 10/09/2024 12.12 19 Sep 2024 15 Oct 2024  Rajender Singh 8178016904 Junior Engineer MEMBER KOTACompleted
100%
KAVI NAGARSanjay Nagar 2  
126 🔗 546 127Repair of damaged road from house no. B-57 to house no. B-49 in Radha Krishna Society, Ward-72, Kaushambi through Dense and work of interlocking tiles on side patri. 14.68 10/09/2024 14.68 21 Oct 202416 Dec 2024 16 Dec 2024 ARUN CONSTRUCTION CO 9312626727Sanjay Gangwar 8178016821 Junior Engineer MEMBER KOTACompleted
100%
VASUNDHRAKaushambhi  
127 🔗 547 118Repair of damaged road from house no. A-01 to house no. A-24 in Park Street and from the corner of the park to the gate by Dense and work of interlocking tiles on side patri in Ward-72 Kaushambi. 12.00 10/09/2024 12.00 21 Oct 2024 16 Dec 2024 ARUN CONSTRUCTION CO 9312626727Sanjay Gangwar 8178016821 Junior Engineer MEMBER KOTACompleted
100%
VASUNDHRAKaushambhi  
128 🔗 548 125Repair of damaged road from house no. B-77 to house no. C-05 in ward-72 Kaushambi by Dense and work of interlocking tiles on side patri. 13.22 10/09/2024 13.22 07 Oct 2024 16 Dec 2024 R G BUILDTECH ENGINEERS LTD 9810616350Sanjay Gangwar 8178016821 Junior Engineer MEMBER KOTACompleted
100%
VASUNDHRAKaushambhi  
Fund Name: NIGAM NIDHI 2024-25
129 🔗 549 143Ward-72 Vaishali Sector-01: Repair work of damaged road from Thursday to transformer by Dense. 13.74 10/09/2024 13.74 07 Oct 2024 20 Feb 2025 PRATEEK ENTERPRISES 9311881082Sanjay Gangwar 8178016821 Junior Engineer MEMBER KOTACompleted
100%
VASUNDHRAKaushambhi  
Fund Name: MEMBER KOTA
130 🔗 74 62Repair work through drain and C.C. in the damaged street from Sanjay Sharma's house to Israr's house in Rajiv Colony, Shyampur Main, Ward-60. 5.06 26/07/2024 5.06 05 Sep 2024 07 Oct 2024 Akruti Const. Vinod KumarJunior Engineer NIGAM NIDHI 2024-25Completed
100%
MOHAN NAGAR Shyampark main  
131 🔗 550 155Construction work of drain and damaged street through C.C. from S.K. Sharma's house to C-43 in Ward 73, Shalimar Garden Ex-1. 26.53 12/09/2024 26.53 19 Sep 202412 Nov 2024 15 Oct 2024 Univershal Vanchar Vinod KumarJunior Engineer MEMBER KOTACompleted
100%
MOHAN NAGAR Shalimar Garden X  
132 🔗 551 145Construction work of drain and damaged street through CC from Nathulal's house to SK Sharma in Ward 73, Shalimar Garden Ex-1. 23.47 12/09/2024 23.47 19 Sep 202412 Nov 2024 15 Oct 2024 Ujjwal Const. Vinod KumarJunior Engineer MEMBER KOTACompleted
100%
MOHAN NAGAR Shalimar Garden X  
133 🔗 552 132In Ward-74 Sec-15 Vasundhara, repair work of damaged wall from house no. 15/1100 to house no. 15/1146 and construction work of interlocking tiles from house no. 15/1131 to house no. 15/1127. 10.94 10/09/2024 10.94 07 Oct 202430 Dec 2024 30 Dec 2024 V S BUILDCON CO 8630570065Sanjay Gangwar 8178016821 Junior Engineer MEMBER KOTACompleted
100%
VASUNDHRAVasundhra 3  
134 🔗 553 84Repair work of damaged road from house no. C-18 to C-31 in ward-74 by Dense. 13.67 10/09/2024 13.67 19 Sep 202422 Nov 2024 15 Oct 2024 PRATEEK ENTERPRISES 9311881082Sanjay Gangwar 8178016821 Junior Engineer MEMBER KOTACompleted
100%
VASUNDHRAVasundhra 3  
135 🔗 554 65Construction work of damaged interlocking tiles in Ward-74 to 13, from house no. 13/394 to house no. 403 and house no. 389 to 388 and house no. 13/335 to 13/356 and house no. 13/332. 10.81 10/09/2024 10.81 19 Sep 202406 Nov 2024 14 Oct 2024  Sanjay Gangwar 8178016821 Junior Engineer MEMBER KOTACompleted
100%
VASUNDHRAVasundhra 3  
136 🔗 555 85Repair of damaged road from 6/210 to 6/225 in Ward-74 Sec-06 Vaishali by Dense and work of interlocking tiles on site plate. 14.55 10/09/2024 14.55 19 Sep 202422 Nov 2024 15 Oct 2024 PRATEEK ENTERPRISES 9311881082Sanjay Gangwar 8178016821 Junior Engineer MEMBER KOTACompleted
100%
VASUNDHRAVasundhra 3  
Fund Name: NIGAM NIDHI 2024-25
137 🔗 556 157Construction work of damaged street through C.C. from D-173 to D 132, D 200 to D 137, D 196 to D 180, D 330 to 84, D 115 to D 21, D 113 to D 24 and D 176 to D 57, near power house in D Block, Ward 75, Lajpat Nagar. 20.18 12/09/2024 20.18 19 Sep 202418 Jan 2025 15 Oct 2024 S.R.S. Buildcon Vinod KumarJunior Engineer MEMBER KOTACompleted
100%
MOHAN NAGAR Lajpat Nagar 1  
138 🔗 75 61Construction work of drain and CC road in the street from Arif's house to Premvati's house in Ward-34, Shaheednagar First. 4.46 26/07/2024 4.46 05 Sep 202420 Jan 2025 07 Oct 2024 H.R. Builders Sanjay GangwarJunior Engineer NIGAM NIDHI 2024-25Completed
100%
MOHAN NAGAR Shaheed Nagar First  
139 🔗 311 42Ward-25, Repair and painting work of Ramlila Ground. 4.32 18/09/2024 4.32 19 Sep 202408 Oct 2024 01 Oct 2024 Keshram Const. Preeti BansalJunior Engineer NIGAM NIDHI 2024-25Completed
100%
VIJAY NAGARAmbedkar Nagar  
140 🔗 312 35Repair and painting work of Ramlila Ground near Tanki Complex in Ward-55, C-Block. 2.10 18/09/2024 2.10 19 Sep 202403 Oct 2024 01 Oct 2024 Jai Shanidev Const Preeti BansalJunior Engineer NIGAM NIDHI 2024-25Completed
100%
VIJAY NAGARVijay Nagar sec11 block-A  
141 🔗 313 36Repair and painting work of Ramlila Ground in Ward-51, Pratap Vihar E-Block. 1.38 18/09/2024 1.38 19 Sep 202403 Oct 2024 01 Oct 2024 Jai Shanidev Const Preeti BansalJunior Engineer NIGAM NIDHI 2024-25Completed
100%
VIJAY NAGARPratap Vihar Sec-11  
142 🔗 314 37Repair and painting work of Ramlila Ground near Tanki Complex, Ward-51. 2.45 18/09/2024 2.45 19 Sep 202403 Oct 2024 01 Oct 2024 Jai Shanidev Const Preeti BansalJunior Engineer NIGAM NIDHI 2024-25Completed
100%
VIJAY NAGARPratap Vihar Sec-11  
143 🔗 315 51Repair and painting work of Ward-71 Sanjay Nagar Ramlila Ground. 5.74 11/09/2024 5.74 19 Sep 202409 Oct 2024 08 Oct 2024  Rajender Singh 8178016904 Junior Engineer NIGAM NIDHI 2024-25Completed
100%
KAVI NAGARSanjay Nagar 2  
144 🔗 316 38Repair and painting work of Ramlila Ground and Arya Samaj Temple park in Ward-84 Rajnagar Sector-10. 6.82 11/09/2024 6.82 19 Sep 202405 Oct 2024 01 Oct 2024  Rajender Singh 8178016904 Junior Engineer NIGAM NIDHI 2024-25Completed
100%
KAVI NAGARRajNagar  
145 🔗 317 33Work of repair and painting etc. of Chhath Ghat located at various places under Vasundhara Zone. 9.52 17/09/2024 9.52 19 Sep 202411 Nov 2024 05 Oct 2024 A H CONSTRUCTIONS 9873347860Sanjay Gangwar 8178016821 Junior Engineer NIGAM NIDHI 2024-25Completed
100%
VASUNDHRABhoowa Pura  
146 🔗 318 43Under Vijayanagar Zone, Ward-07, Sudamapuri C-Block Balaji Temple, A/600 Tikona Park, in front of Sarvodaya Inter College (Mata Ahilyabai Holkar Park), Ward-15, K Block Temple Park, L-Block Ram Janaki Park, Ward-27 Shanti Nagar Near Water Tank, Ward-35, Shiv Temple and Radha Krishna Temple Complex and Ward-58 A-Block A-491 Park, repair and painting work of Chhath Ghats built earlier. 2.34 18/09/2024 2.34 19 Sep 202408 Oct 2024 01 Oct 2024 Manveer Singh Cont. SHIV KUMAR SAROJJunior Engineer NIGAM NIDHI 2024-25Completed
100%
VIJAY NAGAR   
147 🔗 76 63Construction work of drain and CC road in the street from Haji Akbar's house to Budhba's house in Ward-34, Shaheednagar I. 4.92 26/07/2024 4.92 05 Sep 202412 Nov 2024 07 Oct 2024 H.R. Builders Sanjay GangwarJunior Engineer NIGAM NIDHI 2024-25Completed
100%
MOHAN NAGAR Shaheed Nagar First  
148 🔗 77 67Work of drain and interlocking tiles in the kutcha lane from Amrish's house to Nanak's house in lane no. 10 of Rajiv Colony, Bhaupura, ward-20. 5.64 15/12/2023 5.64 05 Sep 202412 Nov 2024 07 Oct 2024 Mohit Choudhary Vinod KumarJunior Engineer NIGAM NIDHI 2024-25Completed
100%
MOHAN NAGAR Bhaupura  
149 🔗 78 141Ward - 10, Pappu Kalani, Street No. 06, from Yashpal Pehalwan's house to Mahendra Singh Parcha's house, drain and C.C. work. 9.67 25/06/2024 9.67 05 Sep 202414 Oct 2024 14 Oct 2024 A.S. Const. Vinod KumarJunior Engineer NIGAM NIDHI 2024-25Completed
100%
MOHAN NAGAR DLF Colony  
150 🔗 79 158Ward - 10, Pappu Kalani, Street No. 06, from Jagpal's house to Yashpal's house, drain and CC work. 9.85 28/06/2024 9.85 05 Sep 202415 Oct 2024 15 Oct 2024 A.S. Const. Vinod KumarJunior Engineer NIGAM NIDHI 2024-25Completed
100%
MOHAN NAGAR DLF Colony  
151 🔗 80 163Ward - 10, Pappu Kalani, Street No. 06, from Subodh Das's house to Jagpal's house, drain and CC work. 9.32 01/07/2024 9.32 05 Sep 202415 Oct 2024 15 Oct 2024 A.S. Const. Vinod KumarJunior Engineer NIGAM NIDHI 2024-25Completed
100%
MOHAN NAGAR DLF Colony  
152 🔗 81 66Work of boundary wall of vacant land of Municipal Corporation near Chikamberpur GT Road Shahidnagar Metro Station and Shani Temple, Ward-34, Shahidnagar First. 14.90 02/08/2024 14.90 05 Sep 202415 Oct 2024 07 Oct 2024 Mohit Choudhary Sanjay GangwarJunior Engineer NIGAM NIDHI 2024-25Completed
100%
MOHAN NAGAR Shaheed Nagar First  
153 🔗 82 70Patch repair work in Ward-22, Industrial Area Amrit Steel Compound. 9.75 25/07/2024 9.75 05 Sep 202415 Oct 2024 10 Oct 2024 Prateek Enter. Preeti BansalJunior Engineer NIGAM NIDHI 2024-25Completed
100%
CITY ZONE Daulat Pura  
154 🔗 83 44Work of drain and interlocking tiles from Nutan's house via Horam's house to Diamond Steel shop in Ward-02, Siddharth Vihar. 17.35 13/06/2024 17.35 05 Sep 202428 Nov 2024 01 Oct 2024 Satnam Const. SHIV KUMAR SAROJJunior Engineer NIGAM NIDHI 2024-25Completed
100%
VIJAY NAGARRahul Vihar Siddharth Vihar  
155 🔗 84 38Ward-55, in front of Kuti Ashram, from Radha Sweets to the corner of the park (H.No. 288) and from B-338 to Satnam Halwai, repair work of interlocking tiles. 10.00 05/09/2024 10.00 05 Sep 202408 Oct 2024 01 Oct 2024 Pragati Enterprises SHIV KUMAR SAROJJunior Engineer NIGAM NIDHI 2024-25Completed
100%
VIJAY NAGARVijay Nagar sec11 block-A  
156 🔗 85 39Construction work of interlocking tiles from Balaji Stationery to Garhwali Park and on the tank side (side track) in front of Kuti Ashram in Ward-55, D-Block. 6.73 05/09/2024 6.73 05 Sep 202407 Oct 2024 01 Oct 2024 Pragati Enterprises SHIV KUMAR SAROJJunior Engineer NIGAM NIDHI 2024-25Completed
100%
VIJAY NAGARVijay Nagar sec11 block-A  
157 🔗 86 41Drain construction work in H.No. 205 to 260, H.No. 450 to 435, H.No. 451 to 466 and H.No. 546 to 335 in Ward-55, D-Block. 9.22 05/09/2024 9.22 05 Sep 2024 01 Oct 2024 Keshram Const. SHIV KUMAR SAROJJunior Engineer NIGAM NIDHI 2024-25Completed
100%
VIJAY NAGARVijay Nagar sec11 block-A  
158 🔗 87 40Drain construction work in H.No. 188 to 196, H.No. 200 to 197, H.No. 522 to 511 and H.No. 499 to 377 in Ward-55, D-Block. 9.38 05/09/2024 9.38 05 Sep 202408 Oct 2024 01 Oct 2024 Keshram Const. SHIV KUMAR SAROJJunior Engineer NIGAM NIDHI 2024-25Completed
100%
VIJAY NAGARVijay Nagar sec11 block-A  
159 🔗 88 125Road improvement work through drain and CC from Surjeet's house to Sundar's house in Ward-03, Vijaynagar Sector-09. 7.85 26/07/2024 7.85 05 Sep 202427 Jan 2025 24 Dec 2024 Jaiveer Singh Contr. Preeti BansalJunior Engineer NIGAM NIDHI 2024-25Completed
100%
VIJAY NAGARPurana Vijay Nagar  
160 🔗 89 123Road improvement work through drain and C.C. from K-1306 to main road (Sanatani Gali No. 02) in Ward-03, Vijayanagar Sector-09. 9.51 26/07/2024 9.51 16 Sep 2024 24 Dec 2024 JAIVEER SINGH CONTRACTOR 9971480216SHIV KUMAR SAROJ 8178016826 Junior Engineer NIGAM NIDHI 2024-25Completed
100%
VIJAY NAGARPurana Vijay Nagar  
161 🔗 90 133Construction work of CC road and drain from Bunty's shop to Bhavani Auto Mobile via Sharma's house in lane no. 3 in Ward-25, Ambedkar Nagar. 8.19 26/07/2024 8.19 26 Nov 2024 24 Dec 2024 Pardhan Const. SHIV KUMAR SAROJJunior Engineer NIGAM NIDHI 2024-25Completed
100%
VIJAY NAGARAmbedkar Nagar  
162 🔗 91 77Road improvement work by providing drain and interlocking tiles on the damaged road from Pratap's house to Darogaji's house in Ward-27, San Vihar. 9.54 13/06/2024 9.54 05 Sep 202426 Nov 2024 14 Oct 2024 Chandra Mohan Singh Raguwanshi SHIV KUMAR SAROJJunior Engineer NIGAM NIDHI 2024-25Completed
100%
VIJAY NAGARDundaheda  
163 🔗 92 76Work of tiles and drain construction in Ward-27, San Vihar Street No.-08. 9.84 24/07/2024 9.84 05 Sep 202410 Dec 2024 14 Oct 2024 Pragati Enterprises SHIV KUMAR SAROJJunior Engineer NIGAM NIDHI 2024-25Completed
100%
VIJAY NAGARDundaheda  
164 🔗 93 45Road improvement work by laying interlocking tiles on the damaged road from Sadi Mahal to Mahesh's house in Ward-02, Rahul Vihar under Ward-53, Vijay Nagar Zone. 14.43 31/10/2024 14.43 05 Sep 202414 Oct 2024 01 Oct 2024 Satnam Const. SHIV KUMAR SAROJJunior Engineer NIGAM NIDHI 2024-25Completed
100%
KAVI NAGAR Raishpur  
165 🔗 94 69Work of drain and interlocking tiles in the damaged street from Banwari's house to Goyal Book's house in street no. 04 in Ward-60, Shyampur Main. 5.13 26/07/2024 5.13 05 Sep 2024 07 Oct 2024  Sanjay Gangwar 8178016821 Junior Engineer NIGAM NIDHI 2024-25Completed
100%
MOHAN NAGARShyampark main  
166 🔗 95 49Work of interlocking tiles in Ward-53, Raispur Ambedkar School. 9.01 24/07/2024 9.01 05 Sep 202414 Oct 2024 04 Oct 2024 A.K.G Construction 9654220230SHIV KUMAR SAROJ 8178016826 Junior Engineer NIGAM NIDHI 2024-25Completed
100%
KAVI NAGARRaishpur  
167 🔗 97 46Work of interlocking tiles on the road leading to garbage factory behind C&D Waste Plant, Ward - 17. 18.59 04/09/2024 18.59 05 Sep 202414 Oct 2024 05 Oct 2024 Pramood Kumar Singhal Preeti BansalJunior Engineer NIGAM NIDHI 2024-25Completed
100%
CITY ZONE Sewa Nagar, Hindan Vihar  
168 🔗 98 45Work of interlocking tiles from Ward - 17, Garbage Factory to C&D Waste Plant behind street. 18.76 04/09/2024 18.76 05 Sep 202417 Jan 2025 05 Oct 2024 Satnam Const. Preeti BansalJunior Engineer NIGAM NIDHI 2024-25Completed
100%
CITY ZONE Sewa Nagar, Hindan Vihar  
169 🔗 99 42Work of construction of culvert in front of Milan Sweets in Ward-67, Sanjay Nagar. 4.92 26/07/2024 4.92 05 Sep 202402 Dec 2024 04 Oct 2024  Rajender Singh 8178016904 Junior Engineer NIGAM NIDHI 2024-25Completed
100%
KAVI NAGARKamla Nehru Nagar Sanjay Nagar 1  
170 🔗 100 43Road improvement work by Danes from P-175 to P-183 and P-163 to P-135 in Ward-67, Sanjaynagar P-Block. 9.91 24/07/2024 9.91 05 Sep 2024 04 Oct 2024  Rajender Singh 8178016904 Junior Engineer NIGAM NIDHI 2024-25Completed
100%
KAVI NAGARKamla Nehru Nagar Sanjay Nagar 1  
Fund Name: MEMBER KOTA
171 🔗 101 68Construction work of pink toilet under the park at the Municipal Corporation Headquarters. 18.10 10/09/2024 18.10 05 Sep 2024 09 Oct 2024 Chandra Mohan Singh Raguwanshi NAGENDRA SHARMAJunior Engineer NIGAM NIDHI 2024-25Completed
100%
CITY ZONE    
172 🔗 102 99Ward-01, Bhim Nagar Street No. 08, from Dev Karan to Sanjeev, Omvir to Rajpal, damaged road, repair of drains and C.C. road improvement work. 6.52 03/09/2024 6.52 07 Oct 202413 Dec 2024 10 Dec 2024  SHIV KUMAR SAROJ 8178016826 Junior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARBagu Kischayan Nagar  
173 🔗 103 97Repair of drain and improvement of damaged road from Murari Lal to Dev Karan in Ward-01, Bhim Nagar Street No. 08 by C.C. road. 8.57 04/09/2024 8.57 07 Oct 202413 Dec 2024 10 Dec 2024 Pradhan Contr. SHIV KUMAR SAROJJunior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARBagu Kischayan Nagar  
174 🔗 104 57Road improvement work by interlocking tiles from Jaipal to Jaiveer Pal in Ward-01, Bhimnagar Bali No.-08. 5.44 04/09/2024 5.44 09 Sep 2024 10 Oct 2024 J P Sakti SHIV KUMAR SAROJJunior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARBagu Kischayan Nagar  
175 🔗 105 58Road improvement work by interlocking tiles from Ompal to Khub Singh in Ward-01, Bhimnagar Gali No.-08. 3.50 04/09/2024 3.50 09 Sep 2024 10 Oct 2024 J P Sakti SHIV KUMAR SAROJJunior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARBagu Kischayan Nagar  
176 🔗 106 128Repair work of drain and improvement of damaged road through C.C. road from Manoj to Devendra Bhagat in Ward-01, Christian Nagar Bagu E Block, Street No.01. 5.88 04/09/2024 5.88 16 Dec 202403 Jan 2025 24 Dec 2024 Nirban Infra SHIV KUMAR SAROJJunior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARBagu Kischayan Nagar  
177 🔗 107 69Repair of drains and C.C. road repair work on damaged road from Satnam and Chaudhary Chatar Singh, Ravindra Chauhan to Tarun Kumar in Ward-01, Krishna Nagar Bagu. 6.56 04/09/2024 6.56 09 Sep 2024 10 Oct 2024 Nirban Infra SHIV KUMAR SAROJJunior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARBagu Kischayan Nagar  
178 🔗 108 56Construction work of RCC drain from Rana Dairy to K/11 on Ward-03, Thana Road. 6.32 03/09/2024 6.32 09 Sep 2024 10 Oct 2024 J.P. Shakti Const. SHIV KUMAR SAROJJunior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARPurana Vijay Nagar  
179 🔗 109 55Construction of drain from Rakesh's house to Laxmi Dairy via Chhajju Singh in Ward-03, Purana Vijayanagar 6.86 03/09/2024 6.86 09 Sep 2024 10 Oct 2024 J.P. Shakti Const. SHIV KUMAR SAROJJunior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARPurana Vijay Nagar  
180 🔗 110 110Work of drain construction till Pradeep’s house Jatin Footwear in Ward-03, Purana Vijayanagar. 6.45 03/09/2024 6.45 07 Oct 2024 10 Dec 2024 J.P. Shakti Const. SHIV KUMAR SAROJJunior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARPurana Vijay Nagar  
181 🔗 111 113Construction of C.C. road and drain in Ward-03, Purana Vijayanagar from Ram Bahadur to Chandrapal and from Satendra's house via Murali's house to Agnihotri's house. 4.53 03/09/2024 4.53 07 Oct 2024 10 Dec 2024 J.P. Shakti Const. SHIV KUMAR SAROJJunior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARPurana Vijay Nagar  
182 🔗 112 112Drain and CC road improvement work from Inspector's house to Dulichand's house in Ward-03, Old Vijayanagar. 9.83 27/08/2024 9.83 07 Oct 2024 10 Dec 2024 J.P. Shakti Const. SHIV KUMAR SAROJJunior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARPurana Vijay Nagar  
183 🔗 113 105Construction of C.C. road and drain from Kavi Medical Store to Mahendra Masterji and from Balbir to Jitendra's shop in Ward-04, Mata Colony. 9.95 03/09/2024 9.95 07 Oct 2024 10 Dec 2024  SHIV KUMAR SAROJ 8178016826 Junior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARSec-12 Mata Colony  
184 🔗 114 48Construction work of interlocking tiles road and drain from Munna Khan's house (Madar Meri Wali Gali) to Raju Kori's house and from Nirjan Kapde Walo to Rathore Chaat Wale in Ward-04, Mata Colony. 9.97 09/09/2024 9.97 09 Sep 202414 Oct 2024 08 Oct 2024 Pragati Enterprises SHIV KUMAR SAROJJunior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARSec-12 Mata Colony  
185 🔗 115 103Work of construction of interlocking tiles road and drain from the house of Harveer Singh to the house of Askin in Ward-04, Rozi Colony. 2.44 27/08/2024 2.44 07 Oct 2024 10 Dec 2024  SHIV KUMAR SAROJ 8178016826 Junior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARSec-12 Mata Colony  
186 🔗 117 102Construction of CC road and drain from house no. 282 to Lochan Singh's house in ward-04 Mata Colony 8.07 27/08/2024 8.07 07 Oct 2024 10 Dec 2024  SHIV KUMAR SAROJ 8178016826 Junior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARSec-12 Mata Colony  
187 🔗 118 106Construction work of CC road and drain from Mastaram's house to Subhash's house in Ward-04 Mata Colony. 7.96 27/08/2024 7.96 07 Oct 2024 10 Dec 2024  SHIV KUMAR SAROJ 8178016826 Junior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARSec-12 Mata Colony  
188 🔗 121 78Construction work of drain from Yogendra's house to Prakash's house in ward no. 05 Gagan Vihar and laying of interlocking tiles in the damaged street. 8.95 05/09/2024 8.95 09 Sep 202404 Dec 2024 08 Oct 2024 Abad Const Vinod KumarJunior Engineer MEMBER KOTACompleted
100%
MOHAN NAGAR Gagan Vihar  
189 🔗 122 82Construction work of drain from Urmila's house to Akash's house in ward no. 05 Gagan Vihar and laying of interlocking tiles in the damaged street. 8.27 05/09/2024 8.27 09 Sep 2024 08 Oct 2024  Vinod Kumar 8650930015 Junior Engineer MEMBER KOTACompleted
100%
MOHAN NAGARGagan Vihar  
190 🔗 123 78Work of construction of drain and interlocking tiles from Ajay to Ramesh in Ward-07 Sudamapuri D-Block. 9.57 04/09/2024 9.57 27 Sep 202423 Jan 2025 14 Oct 2024 Abad Const SHIV KUMAR SAROJJunior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARBihariPura Sudamapuri  
191 🔗 124 104Work of construction of drain and interlocking tiles from Vicky to Ved Prakash, Kanishka Beauty Parlour to Chandrapal in Ward-07 Adarsh ​​Colony. 8.16 03/09/2024 8.16 07 Oct 2024 10 Dec 2024  SHIV KUMAR SAROJ 8178016826 Junior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARBihariPura Sudamapuri  
192 🔗 125 59Road improvement work by interlocking tiles on the damaged road from Dr. L.L. Sharma to Mithlesh, Nandi Lal to Prithvi in ​​Ward-07 Ardash Colony. 7.59 03/09/2024 7.59 27 Sep 202402 Jan 2025 14 Oct 2024 Abad Const SHIV KUMAR SAROJJunior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARBihariPura Sudamapuri  
193 🔗 126 60Road improvement work by interlocking tiles on the damaged road from Prithvi to Tewatia, Ashu to Kiran, Nandi Lal to Sonu in Ward-07 Adarsh ​​Colony. 9.78 02/09/2024 9.78 27 Sep 202402 Jan 2025 14 Oct 2024 Abad Const SHIV KUMAR SAROJJunior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARBihariPura Sudamapuri  
194 🔗 127 95Road improvement work by interlocking tiles on the damaged road from B.S.Tomar to Shiv Vihar square, behind Shri Ram temple in Ward-07, Shiv Vihar and work of laying RCC culvert in front of Prashant General Store, Vishnu. 8.77 03/09/2024 8.77 07 Oct 202411 Dec 2024 10 Dec 2024 A.P Const. SHIV KUMAR SAROJJunior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARBihariPura Sudamapuri  
195 🔗 128 141Construction work of CC road and drain in the service line behind house no. 51 from SL Agarwal to Subhash Kansal in Ward-08, Laxmi Vihar Colony. 8.20 05/09/2024 8.20 09 Sep 202430 Dec 2024 30 Dec 2024  NAGENDRA SHARMA 8882460223 Junior Engineer MEMBER KOTACompleted
100%
CITY ZONENehru Nagar 2  
196 🔗 129 55Construction work of CC road and drain in Ward-08, Laxmi Vihar, near the triangular park, in front of Pramod Kumar and in front of Agarwal. 7.37 05/09/2024 7.37 09 Sep 202414 Oct 2024 09 Oct 2024  NAGENDRA SHARMA 8882460223 Junior Engineer MEMBER KOTACompleted
100%
CITY ZONENehru Nagar 2  
197 🔗 130 147Work of CC and drain parapet from Baljeet's house to Barfi's house in Ward-09, Shibbanpura. 4.60 05/09/2024 4.60 26 Nov 202407 Jan 2025 07 Jan 2025  SUNIL KUMAR MAURYA 8707646842 Junior Engineer MEMBER KOTACompleted
100%
CITY ZONESibbanpura Patel marg  
198 🔗 131 129Work of drain construction and interlocking tiles from H.No. 222 Shri Omveer to Meerut Road liquor shop in Ward-09, Purana Aryanagar. 6.65 11/07/2024 6.65 09 Sep 2024 14 Oct 2024  NAGENDRA SHARMA 8882460223 Junior Engineer MEMBER KOTACompleted
100%
CITY ZONEDeendayal Puri  
199 🔗 132 88Work of making ramp in front of Aggarwal Sweets and near Ekta Park under Ward 10. 2.22 05/09/2024 2.22 09 Sep 202412 Nov 2024 08 Oct 2024 Ujjwal Const. Vinod KumarJunior Engineer MEMBER KOTACompleted
100%
MOHAN NAGAR DLF Colony  
200 🔗 133 67Work of drain and interlocking tiles from Kanti Sharma to Adesh Tyagi and from Inam's house to Gaje Sharma's house in Ward-11, Nandgram Sangam Vihar. 9.25 05/09/2024 9.25 09 Sep 2024 09 Oct 2024 A.H Const. NAGENDRA SHARMAJunior Engineer MEMBER KOTACompleted
100%
CITY ZONE Nandgram, Deendayal puri  
201 🔗 134 112Work of drain and interlocking tiles in front of Himanshu Tyagi's house in Ward-11, Krishnakunj and from Rohela to behind Takshila School. 7.96 05/09/2024 7.96 09 Sep 202430 Nov 2024 14 Oct 2024 Nirban Infra Preeti BansalJunior Engineer MEMBER KOTACompleted
100%
CITY ZONE Nandgram, Deendayal puri  
202 🔗 135 140Road improvement work by Dense on the road from Kunal Tyagi to Shiv Shankar in Ward - 12, Jatwada Computer Market and work of interlocking tiles on the side track and work of interlocking tiles in front of Siddharth School. 8.05 05/09/2024 8.05 26 Nov 202430 Dec 2024 30 Dec 2024  Preeti Bansal 8433403327 Junior Engineer MEMBER KOTACompleted
100%
CITY ZONEKalkagadi, Jatavbada  
203 🔗 136 124Ward-12, Hardev Sarai: Construction of drain and C.C. road from H.No.-95 and Jain sahab's house via Pankaj Tyagi to Virendra's shop. 8.87 05/09/2024 8.87 28 Sep 202428 Nov 2024 14 Oct 2024 Shyama Const. NAGENDRA SHARMAJunior Engineer MEMBER KOTACompleted
100%
CITY ZONE Kalkagadi, Jatavbada  
204 🔗 137 119Construction of C.C. road and drain in ward-12, Kasyawan from Musharraf's house via Aslam to Imran, via Jameel to Bhuura to Adil and from Nazim to Kasam. 8.82 05/09/2024 8.82 09 Sep 202428 Nov 2024 14 Oct 2024 A P Const NAGENDRA SHARMAJunior Engineer MEMBER KOTACompleted
100%
CITY ZONE Kalkagadi, Jatavbada  
205 🔗 138 140Construction work of drain and CC road from the house of Shri Om Prakash Giri to the house of Shri Shankar Jha in Ward-14, Sector-12 Sarvodaya Nagar. 6.33 03/09/2024 6.33 26 Nov 202430 Dec 2024 24 Dec 2024 A.S. Const. SHIV KUMAR SAROJJunior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARNew Vijay Nagar  
206 🔗 139 94Ward-14 Sarvodayanagar Street No. 08: Construction work of drain and CC road from Shri Baburam Sanger's house to I India Mart. 9.96 10/09/2024 9.96 07 Oct 202430 Dec 2024 10 Dec 2024 Manveer Singh Cont. SHIV KUMAR SAROJJunior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARNew Vijay Nagar  
207 🔗 140 113Ward-17, Sevanagar Street No. 06: From Om Prakash Prachoon to Fauji's house and from Kamal Singh via RS Electricals to Ravi's house, drain and C.C. work. 7.85 05/09/2024 7.85 09 Sep 2024 14 Oct 2024  SUNIL KUMAR MAURYA 8707646842 Junior Engineer MEMBER KOTACompleted
100%
CITY ZONESewa Nagar, Hindan Vihar  
208 🔗 141 58Ward-17, Sevanagar Vishwakarma Marg: Work of drain and interlocking tiles from Neeraj to Kishore's house via Brij Kishore's house and till Vishwakarma main road. 9.85 05/09/2024 9.85 09 Sep 202415 Oct 2024 09 Oct 2024 Pramood Kumar Singhal Preeti BansalJunior Engineer MEMBER KOTACompleted
100%
CITY ZONE Sewa Nagar, Hindan Vihar  
209 🔗 142 111Work of drain and C.C. from Lokesh Tyagi to Real Beauty Parlour in Ward-17, Seva Nagar and in Dr. Bengali lane and Ajit Tiwari lane. 8.41 02/09/2024 8.41 09 Sep 202414 Oct 2024 14 Oct 2024 shri balaji contractor & supplier 9871858838NAGENDRA SHARMA 8882460223 Junior Engineer MEMBER KOTACompleted
100%
CITY ZONESewa Nagar, Hindan Vihar  
210 🔗 143 62Work of drain and interlocking tiles from Nagendra Chaudhary's house to Lokesh Pandit's house in Ward 18, Rajapur. 7.47 03/09/2024 7.47 09 Sep 2024 09 Oct 2024 J S S CONSTRUCTION 9999280744Rajender Singh 8178016904 Junior Engineer MEMBER KOTACompleted
100%
KAVI NAGARRajapur ShastriNagar  
211 🔗 144 67Work of drain and interlocking tiles in Pramod Wali Gali and Deepak Moodi Wali Gali in Ward 18, Rajapur. 3.85 03/09/2024 3.85 09 Sep 202415 Feb 2025 09 Oct 2024 RAGHUVANSHI BUILDTECH 7503116611Rajender Singh 8178016904 Junior Engineer MEMBER KOTACompleted
100%
KAVI NAGARRajapur ShastriNagar  
212 🔗 145 61Work of drain and interlocking tiles from Yad Ram's house to D P's house and in Sudhir's street in ward 18, Rajapur. 2.74 03/09/2024 2.74 09 Sep 202422 Jan 2025 09 Oct 2024 A3R Enterprise 9871999403Rajender Singh 8178016904 Junior Engineer MEMBER KOTACompleted
100%
KAVI NAGARRajapur ShastriNagar  
213 🔗 146 58Work of drain and interlocking tiles from Gulshan's house to A-168 in Ward 18, Bagwali Colony. 4.55 03/09/2024 4.55 09 Sep 202422 Jan 2025 09 Oct 2024  Rajender Singh 8178016904 Junior Engineer MEMBER KOTACompleted
100%
KAVI NAGARRajapur ShastriNagar  
214 🔗 147 69Work of interlocking tiles from Reliance Industries to Dalip via Anas Fabrication in Ward-19, Patel Nagar Bounjha and construction work of drain and C.C. road from Bhagwan Daan to Banke Lal. 9.32 05/09/2024 9.32 09 Sep 2024 09 Oct 2024  NAGENDRA SHARMA 8882460223 Junior Engineer MEMBER KOTACompleted
100%
CITY ZONEPatel Nagar, Mukandnagar  
215 🔗 148 61Ward-19, Jagdish Nagar Tyre Market, R.K. Construction of interlocking tiles from Rubber to Meena's house. 9.76 05/09/2024 9.76 09 Sep 2024 09 Oct 2024 Mahima Const. NAGENDRA SHARMAJunior Engineer MEMBER KOTACompleted
100%
CITY ZONE Patel Nagar, Mukandnagar  
216 🔗 149 74Construction work of drain and interlocking tiles in the damaged street from Jai Singh's house to Balram Kasana's house in Ward 20 Bhaipura. 5.69 05/09/2024 5.69 09 Sep 2024 08 Oct 2024 Global Engg. & Infra. Vinod KumarJunior Engineer MEMBER KOTACompleted
100%
MOHAN NAGAR Bhaupura  
217 🔗 150 80Construction work with interlocking tiles in the damaged street from Rajendra's house to Krishna Pal's house in Ward 20 Bhaupura. 2.32 05/09/2024 2.32 09 Sep 2024 08 Oct 2024  Vinod Kumar 8650930015 Junior Engineer MEMBER KOTACompleted
100%
MOHAN NAGARBhaupura  
218 🔗 151 137Construction work of interlocking tiles on site plate in KV Block in Ward-21 Bhowapur. 9.24 05/09/2024 9.24 07 Oct 202424 Jan 2024 24 Jan 2024  Sanjay Gangwar 8178016821 Junior Engineer MEMBER KOTACompleted
100%
VASUNDHRABhoowa Pura  
219 🔗 152 97Improvement work through drain and CC road in the damaged street from Dinesh Pandit's house to Rinku Pandit's house in Ward-21 Bhowapur. 6.19 05/09/2024 6.19 27 Sep 202406 Nov 2024 15 Oct 2024 Maa Padhmawati Const. Sanjay GangwarJunior Engineer MEMBER KOTACompleted
100%
VASUNDHRA Bhoowa Pura  
220 🔗 153 90Improvement work through drain and CC road in the damaged street from Bablu's house to Pappu's house and from Satte's house to Vijay Singh's house in Ward-21 Bhowapur. 4.57 05/09/2024 4.57 09 Sep 202428 Nov 2024 15 Oct 2024 Mahalaxmi Infra. Sanjay GangwarJunior Engineer MEMBER KOTACompleted
100%
VASUNDHRA Bhoowa Pura  
221 🔗 154 108Improvement work through drain and CC road in the damaged street from Sumit's house to Omi's house and from Satte's house to Satish's house and from Devendra to Shivam Deda in Ward-21 Bhowapur. 8.14 05/09/2024 8.14 09 Sep 202405 Nov 2024 15 Oct 2024 Maa Padhmawati Const. Sanjay GangwarJunior Engineer MEMBER KOTACompleted
100%
VASUNDHRA Bhoowa Pura  
222 🔗 155 82Work of installation and repair of iron railing etc. on the divider located on Shukra Bazar Road in Ward-21 Bhowapur. 7.70 05/09/2024 7.70 09 Sep 2024 15 Oct 2024  Sanjay Gangwar 8178016821 Junior Engineer MEMBER KOTACompleted
100%
VASUNDHRABhoowa Pura  
223 🔗 156 144Construction work of CC road and drain from Yadav Niwas to Ekta Siddh (House No. 55/A) in Ward-22 Radhankuj Enclave. 2.99 09/09/2024 2.99 07 Oct 202402 Jan 2025 02 Jan 2025  NAGENDRA SHARMA 8882460223 Junior Engineer MEMBER KOTACompleted
100%
CITY ZONEDaulat Pura  
224 🔗 157 155Construction work of C.C. road and drain in Bakery lane on Ward-22, Bhatia Road and in Dheeraj Singh Choudhary (Anurag Choudhary) lane. 7.18 09/09/2024 7.18 26 Nov 202420 Jan 2025 20 Jan 2025  NAGENDRA SHARMA 8882460223 Junior Engineer MEMBER KOTACompleted
100%
CITY ZONEDaulat Pura  
225 🔗 158 128Construction work of C.C. road and drain from Nanne's house to Bala's house in Ward-22, Daulatpura Purana Telmill Wali Gali. 2.97 05/09/2024 2.97 09 Sep 202408 Apr 2025 08 Apr 2025  NAGENDRA SHARMA 8882460223 Junior Engineer MEMBER KOTACompleted
100%
CITY ZONEDaulat Pura  
226 🔗 159 109Work of construction of interlocking tiles road and drain from Mehru's house to Akbar's house in Ward-23, Kaila Kheda. 8.39 27/08/2024 8.39 07 Oct 202413 Dec 2024 10 Dec 2024 J.P. Shakti Const. Preeti BansalJunior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARKailash Nagar  
227 🔗 160 118Construction work of interlinking tiles road and drain construction in Salman Kinnar Wali Gali from Noorhasan to temple, Titu to Balkishan and various lanes in Ward-23, Kaila Kheda. 8.43 27/08/2024 8.43 07 Oct 2024 10 Dec 2024 J.P. Shakti Const. Preeti BansalJunior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARKailash Nagar  
228 🔗 161 115Work of construction of CC road and drain from Anil Sagar to Shanti Kunj in Ward-23, Kailashnagar Street No.7. 3.16 03/09/2024 3.16 07 Oct 202427 Dec 2024 10 Dec 2024 J.P. Shakti Const. Preeti BansalJunior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARKailash Nagar  
229 🔗 162 117Construction work of CC road and drain in Ward-23, Kailashnagar, from Bhola Prajapati to Rajesh Prajapati, from Gyani via Sunil to Rajesh's house and from Sanjay Kirana Store to Hina. 6.44 06/09/2024 6.44 07 Oct 202427 Dec 2024 10 Dec 2024 J.P. Shakti Const. Preeti BansalJunior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARKailash Nagar  
230 🔗 163 133Work of drain and interlocking tiles from Aziz's house to Sheeshpal's house in Ward 24, Bayana village. 3.79 03/09/2024 3.79 27 Sep 202412 Dec 2024 15 Oct 2024 VANSH CONSTRUCTIONS 9953776458Rajender Singh 8178016904 Junior Engineer MEMBER KOTACompleted
100%
KAVI NAGARMahrouli  
231 🔗 164 131Work of drain and interlocking tiles from Kalu's house to Rajveer's house in Ward 24, Nayphal village. 1.44 03/09/2024 1.44 27 Sep 2024 15 Oct 2024 VANSH CONSTRUCTIONS 9953776458Rajender Singh 8178016904 Junior Engineer MEMBER KOTACompleted
100%
KAVI NAGARMahrouli  
232 🔗 165 150Repair work of drain and interlocking tiles in Ward 24, Mehrauli Village, from Bittu's house via Satveer's shop to Rogan Pal's house. 3.67 03/09/2024 3.67 07 Oct 202412 Dec 2024 12 Dec 2024  Rajender Singh 8178016904 Junior Engineer MEMBER KOTACompleted
100%
KAVI NAGARMahrouli  
233 🔗 166 141Work of drain and interlocking tiles from Beni's Dairy to Rajpal's house in Ward 24, Mehrauli Village. 5.80 03/09/2024 5.80 07 Oct 202421 Feb 2025 07 Oct 2024 MODERN CONSTRUCTION CO Rajender Singh 8178016904 Junior Engineer MEMBER KOTACompleted
100%
KAVI NAGARMahrouli  
234 🔗 167 137Work of drain and interlocking tiles from Sarfaraz's house to Ilyash's house in Ward 24, Bayana. 7.01 03/09/2024 7.01 09 Sep 2024 15 Oct 2024 Chandra Mohan Singh Raguvanshi 9350003528Rajender Singh 8178016904 Junior Engineer MEMBER KOTACompleted
100%
KAVI NAGARMahrouli  
235 🔗 168 160Construction work of C.C. road and drain in Ward No. 11, Ambedkar Nagar, from Munni Devi's house to Hari's house in Street No. 16, from Shobha Devi's house to Vinod Kumar's house via Arvind's house in Street No. 15. 9.96 03/09/2024 9.96 10 Feb 202512 Mar 2025 28 Feb 2025 Keshram Const. SHIV KUMAR SAROJJunior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARAmbedkar Nagar  
236 🔗 169 79Work of interlocking tiles on the side track of the road from in front of house no. D/78 in Ward-25, on three sides of F-Block park and from in front of house no. B/122 to house no. B/54 in B-Block. 3.87 03/09/2024 3.87 09 Sep 202426 Nov 2024 14 Oct 2024 Trinetra Infra SHIV KUMAR SAROJJunior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARAmbedkar Nagar  
237 🔗 170 47Ward - 25, from Vinod Kumar Advocate to Satyacharan (Ashram Wali Gali), Vashisht Shishu Mandir Gali and the lane behind Shankar's shop, work of drain and interlocking tiles and work of interlocking tiles on both sides of the side track of the road in front of Rosewell School. 9.99 09/09/2024 9.99 09 Sep 202414 Oct 2024 08 Oct 2024 Nikhil Asso. SHIV KUMAR SAROJJunior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARAmbedkar Nagar  
238 🔗 171 82Work of interlocking tiles on the side track outside Ramlila Ground, Ward-25. 6.45 03/09/2024 6.45 09 Sep 202410 Dec 2024 14 Oct 2024 Pragati Enterprises SHIV KUMAR SAROJJunior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARAmbedkar Nagar  
239 🔗 172 134Construction work of C.C. road and drain in lane no. 05 from Jeet Bag House to Lali's house in ward-25, Ambedkar Nagar, lane no. 13 from Manoj Dhol Wala to Ramesh Chand. 4.51 02/09/2024 4.51 26 Nov 2024 24 Dec 2024 Pardhan Const. SHIV KUMAR SAROJJunior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARAmbedkar Nagar  
240 🔗 173 46Work of drain and interlocking tiles in Ward-25, Ambedkar Nagar from Syoraj Singh to Vinod and in Gupta Wali Gali and work of interlocking tiles on the side track of the road from Roopchand Halwai to Narendra Mohit. 9.50 09/09/2024 9.50 09 Sep 2024 08 Oct 2024 DSV ENTERPRISES 8630570065SHIV KUMAR SAROJ 8178016826 Junior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARAmbedkar Nagar  
241 🔗 174 81Road and drain improvement work by C.C. on the damaged road from Nach Bharat Tent House to Ghaziabad Convent School and subsidiary lane in Ward No. 26, Bhud-Bharat Nagar. 4.00 03/09/2024 4.00 27 Sep 202415 Oct 2024 14 Oct 2024 Sidh Const SHIV KUMAR SAROJJunior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARMadhopur Sundri  
242 🔗 175 83In ward no. 26, Madhopura, from Shivcharan to Bichhu Gurjar, Chamunda temple to Jagdish Jain, Chamunda temple to Shani temple, damaged road is repaired with C.C. Road and drain repair work. 6.82 03/09/2024 6.82 09 Sep 202415 Oct 2024 14 Oct 2024 Sidh Const SHIV KUMAR SAROJJunior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARMadhopur Sundri  
243 🔗 176 99Road improvement work by interlocking tiles on the damaged road from Somdatt Sharma ji to Satyapal, Satyapal to Ishwar in Ward-27, Shanti Nagar. 8.33 03/09/2024 8.33 07 Oct 202404 Mar 2025 04 Mar 2025 MODERN CONSTRUCTION CO SHIV KUMAR SAROJ 8178016826 Junior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARDundaheda  
244 🔗 177 89Repair work of damaged road in front of Dundahaida pond, Ward No. 27. 3.29 03/09/2024 3.29 07 Oct 2024 10 Dec 2024  SHIV KUMAR SAROJ 8178016826 Junior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARDundaheda  
245 🔗 178 187Construction work of drain and interlocking tiles in the damaged street from J.P. Tyagi's house to Rizwan's house in Neelmani Colony, Ward 28, Rajiv Colony. 5.99 05/09/2024 5.99 07 Oct 202405 Sep 2024 12 Dec 2024  Vinod Kumar 8650930015 Junior Engineer MEMBER KOTACompleted
100%
MOHAN NAGARRajeev Colony  
246 🔗 179 19Boundary wall work of Chamad Mata temple site in Kharsa No. 164 in Ward 30, Sadarpur. 9.82 03/09/2024 9.82 21 Oct 202424 Feb 2025 21 Oct 2024  Rajender Singh 8178016904 Junior Engineer MEMBER KOTACompleted
100%
KAVI NAGARSadarpur, Govind puram  
247 🔗 180 106Work of drain and interlocking tiles from Rajveer's house to Subodh's house and from Kalua's house to Jugendra Singh's house in Ward 30, Sadarpur. 8.39 03/09/2024 8.39 09 Sep 202423 Nov 2024 14 Oct 2024  Rajender Singh 8178016904 Junior Engineer MEMBER KOTACompleted
100%
KAVI NAGARSadarpur, Govind puram  
248 🔗 181 160Work of drain and interlocking tiles from Sunil Verma's house to Mahesh's house and from Subhash Pehlwan's house to Manjoor's shop in Ward 30, Sadarpur. 3.30 03/09/2024 3.30 26 Nov 202423 Jan 2025 23 Jan 2025  Rajender Singh 8178016904 Junior Engineer MEMBER KOTACompleted
100%
KAVI NAGARSadarpur, Govind puram  
249 🔗 182 124Work of drain and interlocking tiles from Harendra's house to Jaipal's house and in Subhash wali gali in ward 30, Sadarpur village. 2.02 03/09/2024 2.02 27 Sep 202412 Dec 2024 15 Oct 2024 VANSH CONSTRUCTIONS 9953776458Rajender Singh 8178016904 Junior Engineer MEMBER KOTACompleted
100%
KAVI NAGARSadarpur, Govind puram  
250 🔗 183 114Work of construction of interlocking tiles and drain from the house of Rajbir Sain to the house of Chaudhary Rishipal, adjacent to District Cooperative Bank in Ward-31, Sihani. 4.51 05/09/2024 4.51 09 Sep 202418 Mar 2025 27 Sep 2024  NAGENDRA SHARMA 8882460223 Junior Engineer MEMBER KOTACompleted
100%
CITY ZONENandgram Sihani  
251 🔗 184 114Construction work of drain and interlocking tiles from Ratanlal Sharma to Avnish Kumar Tyagi and from Srinivas to Lilu's house in Ward-31, Sihani. 6.02 02/09/2024 6.02 09 Sep 202412 Dec 2024 14 Oct 2024 J P Sakti Preeti BansalJunior Engineer MEMBER KOTACompleted
100%
CITY ZONE Nandgram Sihani  
252 🔗 185 60Construction work of drain and interlocking tiles from Rajkumar to Rajan's house in Ward-32, Krishnanagar. 6.07 05/09/2024 6.07 09 Sep 202426 Nov 2024 09 Oct 2024 A.H Const. Preeti BansalJunior Engineer MEMBER KOTACompleted
100%
CITY ZONE Krishna Nagar  
253 🔗 186 53Construction work of C.C. road and drain in Ward-33, Hata Chairman, near Subhash Ghodi Wale, in front of Danny, in front of Jani and in front of the apartment. 9.79 11/07/2024 9.79 09 Sep 2024 09 Oct 2024  Preeti Bansal 8433403327 Junior Engineer MEMBER KOTACompleted
100%
CITY ZONESaray Najar Ali  
254 🔗 187 49Construction work of CC road and drain in the street in front of Mullaji in Ward-33, Sarai Nazar Ali. 9.93 07/09/2024 9.93 09 Sep 2024 09 Oct 2024 Mahakaleshwar Engg. Preeti BansalJunior Engineer MEMBER KOTAIn Progress
20.00%
CITY ZONE Saray Najar Ali  
255 🔗 188 159Work of drain construction in the small street behind the post office in Ward-33, Sarai Nazar Ali. 4.50 07/09/2024 4.50 07 Oct 202430 Jan 2025 30 Jan 2025  Preeti Bansal 8433403327 Junior Engineer MEMBER KOTACompleted
100%
CITY ZONESaray Najar Ali  
256 🔗 189 otherWork of laying interlocking tiles in the courtyard of the primary school of Ward 34 Shahidnagar First. 5.88 05/09/2024 5.88 09 Sep 2024 08 Oct 2024 Akruti Const. Vinod KumarJunior Engineer MEMBER KOTACompleted
100%
MOHAN NAGAR Shaheed Nagar First  
257 🔗 190 79Repair work by drain and C.C. in the damaged lane from Khalil's house to Nausaad's house (Chanda wali lane) in ward 34 Shaheednagar Pratham. 2.48 05/09/2024 2.48 09 Sep 2024 08 Oct 2024 Akruti Const. Vinod KumarJunior Engineer MEMBER KOTACompleted
100%
MOHAN NAGAR Shaheed Nagar First  
258 🔗 191 137Construction work of damaged lane/road through CCC and drain in Ward-35 Buddhist Vihar Akbarpur Bahrampur from Subhash's house to Gopal's house, from Gyanendra's house to Sanjay Master's house, from Devendra Chaudhary's house to Saurabh's house. 9.63 04/09/2024 9.63 26 Nov 202402 Jan 2025 24 Dec 2024 Pardhan Const. SHIV KUMAR SAROJJunior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARAkhbarpur Behrampur  
259 🔗 192 90Construction work of damaged lane/road through CC and drain from Shyam Lal's house to Satendra's house in Ward-35 Buddhist Vihar Akbarpur Bahrampur. 7.31 04/09/2024 7.31 07 Oct 202419 Dec 2024 10 Dec 2024 Balaji Const.Co. SHIV KUMAR SAROJJunior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARAkhbarpur Behrampur  
260 🔗 193 53Work of laying interlocking tiles in front of Vasundhara Sector 16 market in Ward 36 Sector 16 Vasundhara. 2.95 05/09/2024 2.95 09 Sep 2024 09 Oct 2024  Sanjay Gangwar 8178016821 Junior Engineer MEMBER KOTACompleted
100%
VASUNDHRAPrahalad Gari  
261 🔗 194 105Repair work of damaged road from behind Awas Vikas office to main road in Ward 36 Sec 16A Vasundhara by Danes. 5.65 05/09/2024 5.65 09 Sep 202415 Oct 2024 15 Oct 2024  Sanjay Gangwar 8178016821 Junior Engineer MEMBER KOTACompleted
100%
VASUNDHRAPrahalad Gari  
262 🔗 195 112Repair work of damaged road from H.No. 16A/2001 to near S Plaza in Ward 36, S. 16A Vasundhara, near Awas Vikas Guest House, by DANS. 9.88 05/09/2024 9.88 09 Sep 202415 Oct 2024 15 Oct 2024  Sanjay Gangwar 8178016821 Junior Engineer MEMBER KOTACompleted
100%
VASUNDHRAPrahalad Gari  
263 🔗 196 101Work of construction of drain and laying of interlocking tiles from Subodh Sharma's house to Nitin Sharma's house via Shivkumar's house in Ward 36, Prahladgarhi village. 6.07 05/09/2024 6.07 09 Sep 202405 Nov 2024 15 Oct 2024  Sanjay Gangwar 8178016821 Junior Engineer MEMBER KOTACompleted
100%
VASUNDHRAPrahalad Gari  
264 🔗 197 37Work of construction of drain and laying of interlocking tiles from BH No. 16/08 to Jaiveer Singh's house in Ward 36, Prahladgarhi village. 6.14 05/09/2024 6.14 09 Sep 202411 Nov 2024 09 Oct 2024 Tej Const Sanjay GangwarJunior Engineer MEMBER KOTACompleted
100%
VASUNDHRA Prahalad Gari  
265 🔗 198 52Construction of drain and road improvement work through interlocking tiles and C.C. in ward 36, Prahaladgadhi village, from Somdatta to Basanta's house, in the street containing Krishnapal, Fatte, Vipin and Anup Singh. 9.05 05/09/2024 9.05 09 Sep 202405 Nov 2024 09 Oct 2024 Tej Const Sanjay GangwarJunior Engineer MEMBER KOTACompleted
100%
VASUNDHRA Prahalad Gari  
266 🔗 199 90Construction work of drain and CC from B-187 to B-55 in Ward 37, Shalimar Garden. 8.67 05/09/2024 8.67 09 Sep 2024 08 Oct 2024  Vinod Kumar 8650930015 Junior Engineer MEMBER KOTACompleted
100%
MOHAN NAGARShalimar Garden Main  
267 🔗 200 75Construction work by Sugar Pie Skool Interlocking Tiles from Plot No 499, Ward 37, Shalimar Garden. 6.61 05/09/2024 6.61 09 Sep 202412 Dec 2024 08 Oct 2024 Ujjwal Const. Vinod KumarJunior Engineer MEMBER KOTACompleted
100%
MOHAN NAGAR Shalimar Garden Main  
268 🔗 201 87Construction work by interlocking tiles from B-214 to B-230 in Ward 37, Shalimar Garden. 8.35 05/09/2024 8.35 09 Sep 202414 Oct 2024 08 Oct 2024  Vinod Kumar 8650930015 Junior Engineer MEMBER KOTACompleted
100%
MOHAN NAGARShalimar Garden Main  
269 🔗 202 92Work of drain and interlocking tiles in the damaged lane from Kapil Goyal's house to K.R.T. Public School in Ramnagar, Ward 38, Arthala. 9.53 05/09/2024 9.53 09 Sep 2024 08 Oct 2024 J S S CONSTRUCTION 9999280744GANESHI LAL 8178016823 Junior Engineer MEMBER KOTACompleted
100%
MOHAN NAGARAtharla  
270 🔗 203 165Road improvement work by DANS from Vinod Shukla to Rakesh Marg via A/51, K/104 in Ward-39, Nehrunagar Third A & K. 9.94 07/09/2024 9.94 07 Oct 2024 20 Feb 2025 Prateek Enter. Preeti BansalJunior Engineer MEMBER KOTACompleted
100%
CITY ZONE Narsirpur  
271 🔗 204 50Work of construction of interlinking tiles and drains in Somvati, Bablu Pal Wali Gali and Sunaro Wali Gali in Ward-39, Nasirpur. 9.47 07/09/2024 9.47 09 Sep 2024 09 Oct 2024 A.S. Const. Preeti BansalJunior Engineer MEMBER KOTACompleted
100%
CITY ZONE Narsirpur  
272 🔗 205 51Work of construction of interlinking tiles and drain in Ward-39, Rakesh Marg Street No. 02 and G-50, G91, G-100 in G Block, near the park and in the street behind the Patwari. 9.52 07/09/2024 9.52 09 Sep 202410 Oct 2024 09 Oct 2024 A.S. Const. Preeti BansalJunior Engineer MEMBER KOTACompleted
100%
CITY ZONE Narsirpur  
273 🔗 206 54Work of construction of interlinking tiles and drain in service line behind Ward-39, Nasirpur Nehru Nagar Third A/18 and buffalo dairies. 8.43 05/09/2024 8.43 09 Sep 202410 Oct 2024 09 Oct 2024 A.S. Const. Preeti BansalJunior Engineer MEMBER KOTACompleted
100%
CITY ZONE Narsirpur  
274 🔗 207 99Construction work of K.C. drain and C.C. road from B 540 to Ramash's house via Kaushik Medical Store in Ward-40 Sahibabad village. 7.72 05/09/2024 7.72 09 Sep 2024 15 Oct 2024  Sanjay Gangwar 8178016821 Junior Engineer MEMBER KOTACompleted
100%
VASUNDHRASahibabad  
275 🔗 208 110Construction work of drain and interlocking tiles from A to Z Mobile to Mahasingh (Charan Singh wali gali) in ward-40 Sahibabad village. 5.31 11/07/2024 5.31 09 Sep 2024 15 Oct 2024  Sanjay Gangwar 8178016821 Junior Engineer MEMBER KOTACompleted
100%
VASUNDHRASahibabad  
276 🔗 209 95Construction work of drain and CC road from Lucky flour mill to Sunny Shakshaina and Suresh Chauhan's house to Chhuttan's house and from Rinku Tomar's house to Rana's house and from Omprakash's house to Ramchandra in lane no. 1 in ward-40, Jhandapur. 5.46 05/09/2024 5.46 09 Sep 202406 Mar 2025 15 Oct 2024  Sanjay Gangwar 8178016821 Junior Engineer MEMBER KOTACompleted
100%
VASUNDHRASahibabad  
277 🔗 210 106Construction work of RCC drain and CC road from Samar Sharma to Saxena Super Store and from Rahul Sharma Dairy to Pratap's house in Ward-40 Jhandapur. 8.14 05/09/2024 8.14 09 Sep 202418 Mar 2025 15 Oct 2024  Sanjay Gangwar 8178016821 Junior Engineer MEMBER KOTACompleted
100%
VASUNDHRASahibabad  
278 🔗 211 75Construction work of culverts in Balmki Mohalla, Dhara Wali Gali, Railway Line Main Road, Dhobi Wali Gali, near Shiv Mandir, near Primary School and other places in Ward-40, Sahibabad Village. 3.85 05/09/2024 3.85 09 Sep 2024 15 Oct 2024  Sanjay Gangwar 8178016821 Junior Engineer MEMBER KOTACompleted
100%
VASUNDHRASahibabad  
279 🔗 212 86Construction work of C.C. road and drain from Nandini General Store to house no. 592 and from Rajendra Sharma's house to Shri Balaji Electrical in ward-41 Jhandapur. 6.92 05/09/2024 6.92 09 Sep 202425 Nov 2024 15 Oct 2024  Sanjay Gangwar 8178016821 Junior Engineer MEMBER KOTACompleted
100%
VASUNDHRAMaharajpur  
280 🔗 213 109Construction work of RCC drain from Kashinath Building to SK Packing via Red Rose in Ward-43 Kadkad. 5.53 05/09/2024 5.53 09 Sep 202424 Feb 2025 15 Oct 2024  Sanjay Gangwar 8178016821 Junior Engineer MEMBER KOTACompleted
100%
VASUNDHRAKadkad Modal  
281 🔗 214 148Construction of RCC drain and road through CC from Mahendra's house to house no. 491 Geeta Devi in ​​Ward-43 Kadkad Model, from HDFC (ATM) to house no. 1095 (Cookie Wali Gali). 5.24 05/09/2024 5.24 21 Oct 202424 Feb 2025 24 Feb 2025  Sanjay Gangwar 8178016821 Junior Engineer MEMBER KOTACompleted
100%
VASUNDHRAKadkad Modal  
282 🔗 215 85Repair work of drain and C.C. in the damaged lane from M.L. Public School to Anil Pandit's house and from Pramod to Suresh Chauhan's house in Ward 44 Sanjay Colony. 5.37 05/09/2024 5.37 09 Sep 202409 Dec 2024 08 Oct 2024 Chandra Mohan Singh Raguwanshi Sanjay GangwarJunior Engineer MEMBER KOTACompleted
100%
MOHAN NAGAR Sanjay Colony  
283 🔗 216 81Construction work by interlocking tiles in the drain and damaged street from Raju's house to Suraj's house in ward 45, Karhaida. 8.29 05/09/2024 8.29 09 Sep 202412 Nov 2024 08 Oct 2024 JSS Const. Vinod KumarJunior Engineer MEMBER KOTACompleted
100%
MOHAN NAGAR Karheda  
284 🔗 217 57Work of drain and interlocking tiles from Krishanpal Singh's house to Chandrapal Singh's house and the street leading to Harendra Shahlot's house and from Jogendra's house to Ramlal's house in Ward 46, Guldhar II. 8.58 03/09/2024 8.58 09 Sep 2024 09 Oct 2024  Rajender Singh 8178016904 Junior Engineer MEMBER KOTACompleted
100%
KAVI NAGARGuldhar Duhai  
285 🔗 218 128Road improvement work by Danes from house no. 201 to 219 in ward 46, Mansi Vihar. 6.77 03/09/2024 6.77 09 Sep 202415 Oct 2024 15 Oct 2024 R G BUILDTECH ENGINEERS LTD 9810616350Rajender Singh 8178016904 Junior Engineer MEMBER KOTACompleted
100%
KAVI NAGARGuldhar Duhai  
286 🔗 219  Work of drain and interlocking tiles from Manoj's house to house no. 169 in Ward 46, New Friends Colony. 9.88 11/07/2024 9.88 09 Sep 2024  J S S CONSTRUCTION 9999280744Rajender Singh 8178016904 Junior Engineer MEMBER KOTACompleted
100%
KAVI NAGARGuldhar Duhai  
287 🔗 220  Road improvement work by Danes from SC-262 to S-257 and SC-263 to SC-268 and SC-315 to SC-302 in Ward 47, Shastri Nagar C-Block. 9.05 11/07/2024 9.05 09 Sep 2024   Rajender Singh 8178016904 Junior Engineer MEMBER KOTACompleted
100%
KAVI NAGARShastrinagar Mahendra Encalave  
288 🔗 221 127Road improvement work by DANS from SC-230A to SC-205 in Ward 47, Shastri Nagar C-Block. 7.22 23/09/2024 7.22 09 Sep 2024 15 Oct 2024 R G BUILDTECH ENGINEERS LTD 9810616350Rajender Singh 8178016904 Junior Engineer MEMBER KOTACompleted
100%
KAVI NAGARShastrinagar Mahendra Encalave  
289 🔗 222 147Work of drain and interlocking tiles from Z-22 to Z-20 in Ward 47, Mahendra Enclave. 6.69 03/09/2024 6.69 07 Oct 202412 Dec 2024 12 Dec 2024 A K AND ASSOCIATES 7982731070Rajender Singh 8178016904 Junior Engineer MEMBER KOTACompleted
100%
KAVI NAGARShastrinagar Mahendra Encalave  
290 🔗 223 75Construction work of C.C. lane from in front of Bunty's shop to Chaudhary Rashid's house in Ward-48, Mirzapur. 6.08 04/09/2024 6.08 09 Sep 202403 Dec 2024 14 Oct 2024 B S Const SHIV KUMAR SAROJJunior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARMirjapur  
291 🔗 224 50Ward-48, Mirzapur Sector-12, from Intezaar to Choudhary Nanne Kha's house, the damaged road is repaired with C.C. Road. Work of repairing the road with C.C. 9.67 05/09/2024 9.67 09 Sep 202414 Oct 2024 08 Oct 2024 A P Const SHIV KUMAR SAROJJunior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARMirjapur  
292 🔗 225 74Ward-48, Mirzapur Sector-12 Nurani Masjid to Mustafa, Aslam Chaudhary to Intezaar, Bablu to Aslam Chaudhary, Wasim Wali Gali, damaged road, road improvement work by C.C. 7.93 03/09/2024 7.93 09 Sep 202403 Dec 2024 14 Oct 2024 B S Const SHIV KUMAR SAROJJunior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARMirjapur  
293 🔗 226 49Ward-48, Mirzapur Sector-12 From Nisar's house to Nurani Masjid Jan Seva Kendra to Wasim, Wasim, to Aslam, damaged road repair work by C.C. 9.86 05/09/2024 9.86 09 Sep 2024 08 Oct 2024 A P Const SHIV KUMAR SAROJJunior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARMirjapur  
294 🔗 227 73Ward-48, Mirzapur Sector-12 Dr. Naeem Siddiqui from Shifa Clinic, Sher Shah from Imran, Kamal Pal from Bharatpal, work of road repair work through C.C. for the damaged road. 8.41 03/09/2024 8.41 09 Sep 202426 Nov 2024 14 Oct 2024 B.S. Const. SHIV KUMAR SAROJJunior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARMirjapur  
295 🔗 228 80Road repair work through C.C. on the damaged road from Faryad's house to Dr. Naeem Clinic and subsidiary lanes in Ward-48, Sector-12, Mirzapur. 8.88 03/09/2024 8.88 09 Sep 202415 Oct 2024 14 Oct 2024 A P Const SHIV KUMAR SAROJJunior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARMirjapur  
296 🔗 229 94Ward-50, Sadiq Nagar, from Manoj Tyagi to Om Tyagi and work of drain and C.C. road. 4.10 05/09/2024 4.10 09 Sep 202413 Dec 2024 14 Oct 2024 Prakash Const Preeti BansalJunior Engineer MEMBER KOTACompleted
100%
CITY ZONE Saddiknagar, Noornagar  
297 🔗 230 52Work of drain and C.C. road from Arun Kumar's house to Ramanand Sharma via Manish Kumar in Ward-50, Sadiq Nagar. 6.70 05/09/2024 6.70 09 Sep 2024 09 Oct 2024 Mahakaleshwar Engg. NAGENDRA SHARMAJunior Engineer MEMBER KOTAIn Progress
0.00%
CITY ZONE Saddiknagar, Noornagar  
298 🔗 231 56In Ward-50, Saddik Nagar, from Sharma Medical Store to Shri Krishna Sharma via Rajan's house and from Rajkumar Tyagi to Ravindra Sharma's house, work of drain and C.C. road. 9.42 05/09/2024 9.42 09 Sep 2024 09 Oct 2024 Mahakaleshwar Engg. NAGENDRA SHARMAJunior Engineer MEMBER KOTAIn Progress
0.00%
CITY ZONE Saddiknagar, Noornagar  
299 🔗 232 122Work of construction of interlocking tiles road and drain from Mange's house to grocery shop in Ward-52, Kot village. 9.91 11/07/2024 9.91 09 Sep 2024 14 Oct 2024  NAGENDRA SHARMA 8882460223 Junior Engineer MEMBER KOTACompleted
100%
CITY ZONEAryanagar Kotgaon  
300 🔗 233 117Construction work of C.C., interlocking tiles road and drain construction from Kanta Wali Gali and Chahat Wali Gali at Kuye Wala Chowk in Ward-52, Kot Village. 7.22 05/09/2024 7.22 09 Sep 2024 14 Oct 2024  NAGENDRA SHARMA 8882460223 Junior Engineer MEMBER KOTACompleted
100%
CITY ZONEAryanagar Kotgaon  
301 🔗 234 64Work of interlocking tiles road construction and drain repair work from Ward-52, Panchvati B/145 to Tikone Park. 9.98 05/09/2024 9.98 09 Sep 2024 09 Oct 2024 Mahakaleshwar Engg. NAGENDRA SHARMAJunior Engineer MEMBER KOTAIn Progress
0.00%
CITY ZONE Aryanagar Kotgaon  
302 🔗 235 167Work of interlocking tiles road construction and drain repair work in front of house no. B/39, B/164, B/158 and B/172 in Ward-52, Panchvati B Block. 9.99 09/09/2024 9.99 05 Dec 202424 Feb 2025 24 Feb 2025 M.S. Buildwal NAGENDRA SHARMAJunior Engineer MEMBER KOTACompleted
100%
CITY ZONE Aryanagar Kotgaon  
303 🔗 236 169Construction work of C.C. road and drain in lane no. 04, Arya Samaj lane, Ward-52, Purana Aryanagar Kot Village. 7.56 09/09/2024 7.56 26 Dec 202425 Feb 2025 25 Feb 2025 Shree Radhya Const. NAGENDRA SHARMAJunior Engineer MEMBER KOTACompleted
100%
CITY ZONE Aryanagar Kotgaon  
304 🔗 237 59Work of drain and interlocking tiles in Ward 53, Raispur, from Amarnath's house to China's house, from Vinod's house to Devendra's house, from Prakash's house to Vinod's house, in Jitendra and Lilu's street. 9.87 03/09/2024 9.87 09 Sep 202410 Oct 2024 09 Oct 2024  Rajender Singh 8178016904 Junior Engineer MEMBER KOTACompleted
100%
KAVI NAGARRaishpur  
305 🔗 238 69Work of drain and interlocking tiles in Ward 53, Raispur, from Amit's house to Yashpal's house, Lala wali gali, Pradeep wali gali, Raj Singh wali gali. 9.50 03/09/2024 9.50 09 Sep 2024 09 Oct 2024  Rajender Singh 8178016904 Junior Engineer MEMBER KOTAIn Progress
75.00%
KAVI NAGARRaishpur  
306 🔗 239 158Work of drain construction from Veeru's house to Ram Vatika in Ward 53, Raispur. 4.23 03/09/2024 4.23 07 Oct 202424 Jan 2025 22 Jan 2025  Rajender Singh 8178016904 Junior Engineer MEMBER KOTACompleted
100%
KAVI NAGARRaishpur  
307 🔗 240 159Work of interlocking tiles and shed in Harijan Chaupal in Ward 53, Raispur and work of interlocking tiles in front of the house of former councilor Narendra Chaudhary. 4.93 03/09/2024 4.93 07 Oct 202422 Jan 2025 22 Jan 2025  Rajender Singh 8178016904 Junior Engineer MEMBER KOTACompleted
100%
KAVI NAGARRaishpur  
308 🔗 241 otherWork of construction of Johar side wall and interlocking tiles from M-459 to M-452 in Ward 53, Sanjay Nagar M-Block. 7.24 03/09/2024 7.24 21 Oct 2024 12 Dec 2024  Rajender Singh 8178016904 Junior Engineer MEMBER KOTACompleted
100%
KAVI NAGARRaishpur  
309 🔗 242 65Footpath work in Ward 53, Sanjay Nagar M-Block from M-324 to M-328, M-354 to M-361, M-92 to M-76. 7.12 03/09/2024 7.12 09 Sep 202410 Oct 2024 09 Oct 2024  Rajender Singh 8178016904 Junior Engineer MEMBER KOTACompleted
100%
KAVI NAGARRaishpur  
310 🔗 243 136Construction work of CC road parallel to our park from in front of Kishan Sharma's house in Sadbhavna Society in Ward-54. 4.17 22/08/2024 4.17 21 Oct 202422 Jan 2025 22 Jan 2025  Sanjay Gangwar 8178016821 Junior Engineer MEMBER KOTACompleted
100%
VASUNDHRAVashundhra-1  
311 🔗 244 119Improvement work by interlocking tiles in Prayas Housing Society in Ward-54 Vasundhara Sector-03 from 3/273 to 3/283 and in front of Laxmi Narayan Temple. 8.89 05/09/2024 8.89 09 Sep 202416 Dec 2024 16 Dec 2024  Sanjay Gangwar 8178016821 Junior Engineer MEMBER KOTACompleted
100%
VASUNDHRAVashundhra-1  
312 🔗 245 70Construction work of interlinking tiles road in house no. 259 to 270, 258 to 247 and 236 to 246 (Tikona Park) in Ward-55, D Block. 9.99 03/09/2024 9.99 09 Sep 202415 Oct 2024 14 Oct 2024 V.S. Buildcon.Co. SHIV KUMAR SAROJJunior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARVijay Nagar sec11 block-A  
313 🔗 246 71Construction work of interlinking tiles road from house no. 236 to 402 and 403 to 393 in Ward-55, D Block. 9.74 03/09/2024 9.74 09 Sep 2024 14 Oct 2024 V.S. Buildcon.Co. SHIV KUMAR SAROJJunior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARVijay Nagar sec11 block-A  
314 🔗 247 72Construction work of interlinking tiles road in house no. 298 to 304 and 419 to 434 in Ward-55, D Block. 9.97 03/09/2024 9.97 09 Sep 202415 Oct 2024 14 Oct 2024 V.S. Buildcon.Co. SHIV KUMAR SAROJJunior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARVijay Nagar sec11 block-A  
315 🔗 248 138Road improvement work by DANS from 05/129 to 05/159 in Ward 56, Chiranjiv Vikar Sector-05. 9.93 03/09/2024 9.93 09 Sep 2024 15 Oct 2024  Rajender Singh 8178016904 Junior Engineer MEMBER KOTACompleted
100%
KAVI NAGARChiranjeev Vihar  
316 🔗 249 57In ward-57 Makanpur, from Manoj Tyagi via Moolchand to Ravi Tawar, from Islamuddin to Sachin Tyagi, from Moolchand to Sunita's house and from Lakesh Sharma to Kanti, road improvement work through drain and C.C. 9.96 05/09/2024 9.96 09 Sep 2024 09 Oct 2024  Sanjay Gangwar 8178016821 Junior Engineer MEMBER KOTACompleted
100%
VASUNDHRAMakan pur  
317 🔗 250 143Road repair work through C.C. on the damaged road from Sundar to Radheshyam, Madanlal to Sanjay Sharma's house in Ward-58, Mawai. 7.86 03/09/2024 7.86 26 Nov 202430 Dec 2024 24 Dec 2024 A.P Const. SHIV KUMAR SAROJJunior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARShivpuri  
318 🔗 251 135Road repair work through C.C. on the damaged road from Parshuram to Satendra, Kishan to Rajkumar, Deendayal to Manoj in ward 58, Mawai. 8.08 03/09/2024 8.08 26 Nov 202402 Jan 2025 24 Dec 2024 Pardhan Const. SHIV KUMAR SAROJJunior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARShivpuri  
319 🔗 252 122Road repair work through C.C. on the damaged road from Ashok Duggal to D.W.S. Academy, Devdutt Sharma in Ward 58, Mawai Street No. 11. 9.62 03/09/2024 9.62 09 Sep 202426 Dec 2024 24 Dec 2024 A.H Const. SHIV KUMAR SAROJJunior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARShivpuri  
320 🔗 253 95Improvement work by laying drain and interlocking tiles in damaged lane from GT Road to house no. 109/7 (Sawarwal lane) and Harpal Singh lane and Verma House in Ward 60 Shyampur Main. 7.30 05/09/2024 7.30 09 Sep 2024 08 Oct 2024  Vinod Kumar 8650930015 Junior Engineer MEMBER KOTACompleted
100%
MOHAN NAGARShyampark main  
321 🔗 254 91Work of drain and interlocking tiles in the damaged street in Jai Bharat Enclave of Ward 60, Shyampur Main, in lane no. 06 from Church to B-41 and in lane no. 07 from Shanti Bhawan to Shakuntala Devi's house. 6.93 05/09/2024 6.93 09 Sep 202415 Oct 2024 08 Oct 2024 H.R. Builders Sanjay GangwarJunior Engineer MEMBER KOTACompleted
100%
MOHAN NAGAR Shyampark main  
322 🔗 255 84Work of drain and interlocking tiles in the damaged street in lane no. 04 from Surendra Sharma's house to the temple in Jai Bharat Enclave of Ward 60, Shyampur Main and from B 19 to B 26 in lane no. 05. 9.37 05/09/2024 9.37 09 Sep 2024 08 Oct 2024 Nikhil Asso. Vinod KumarJunior Engineer MEMBER KOTACompleted
100%
MOHAN NAGAR Shyampark main  
323 🔗 256 83Repair work of drain and C.C. in the damaged lane from Budhram Sharma's house to Virendra's house in Rajiv Colony, Shyampur Main, from Virendra to Ramkumar's house. 9.56 14/08/2024 9.56 09 Sep 2024 08 Oct 2024  Vinod Kumar 8650930015 Junior Engineer MEMBER KOTACompleted
100%
MOHAN NAGARShyampark main  
324 🔗 257 77Construction of RCC drain in lane no. 04 of ward 60 Shyampur Main from Jaipal's house to Goyal Book wala's house and from Rai's house to temple and from Mikku's house to Aryan Academy. 9.91 14/08/2024 9.91 09 Sep 202421 Nov 2024 08 Oct 2024 J.P. Shakti Const. Sanjay GangwarJunior Engineer MEMBER KOTACompleted
100%
MOHAN NAGAR Shyampark main  
325 🔗 258 96Repair work of drain and C.C. in damaged lanes of Raghupat Pandey wali, Nand Sharma wali and K.S. Rawat in Indra Garden of ward 60 Shyampur Main. 6.02 14/08/2024 6.02 09 Sep 202407 Nov 2024 08 Oct 2024 H.R. Builders Sanjay GangwarJunior Engineer MEMBER KOTACompleted
100%
MOHAN NAGAR Shyampark main  
326 🔗 259 111Repair work of the damaged road near Shivaji Park and Central Park in Ward No. 61-10 by Dense. 9.07 06/09/2024 9.07 09 Sep 202415 Oct 2024 15 Oct 2024 R G BUILDTECH ENGINEERS LTD 9810616350Sanjay Gangwar 8178016821 Junior Engineer MEMBER KOTACompleted
100%
VASUNDHRAVasundhra-2  
327 🔗 260 63Repair work of damaged road from Central Park to Mahavir Marg in Ward 61 Sec 10 by Dense. 5.32 05/09/2024 5.32 09 Sep 202415 Oct 2024 14 Oct 2024 R G BUILDTECH ENGINEERS LTD 9810616350Sanjay Gangwar 8178016821 Junior Engineer MEMBER KOTACompleted
100%
VASUNDHRAVasundhra-2  
328 🔗 261 186Construction work of drain and damaged street through C.C. from Shahid's house to Anish's house in Ward No. 64, Garima Garden. 9.40 05/09/2024 9.40 07 Oct 202412 Dec 2024 12 Dec 2024  Vinod Kumar 8650930015 Junior Engineer MEMBER KOTACompleted
100%
MOHAN NAGARGarima Garden  
329 🔗 262 152Construction work by interlocking tiles in the drain and damaged street from Mustakim's house to Imtiaz's house in Ward 64 Garima Garden. 8.66 05/09/2024 8.66 09 Sep 2024 15 Oct 2024 Marden Engg. Asso. Vinod KumarJunior Engineer MEMBER KOTACompleted
100%
MOHAN NAGAR Garima Garden  
330 🔗 263 54Work of interlocking tiles and drain repair from R-07/194 to R-07/174 in Ward 67, Rajnagar. 9.86 02/09/2024 9.86 09 Sep 2024 09 Oct 2024  Rajender Singh 8178016904 Junior Engineer MEMBER KOTAIn Progress
25.00%
KAVI NAGARKamla Nehru Nagar Sanjay Nagar 1  
331 🔗 264 71Work of Public Facility Centre with NITRA wall in front of CMO office in Ward 67, Sanjay Nagar. 9.54 11/07/2024 9.54 09 Sep 2024 09 Oct 2024  Rajender Singh 8178016904 Junior Engineer MEMBER KOTACompleted
100%
KAVI NAGARKamla Nehru Nagar Sanjay Nagar 1  
332 🔗 265 52Work of installing S.S. boards at various places in Ward 67, Sanjay Nagar. 9.52 02/09/2024 9.52 09 Sep 2024 08 Oct 2024  Rajender Singh 8178016904 Junior Engineer MEMBER KOTACompleted
100%
KAVI NAGARKamla Nehru Nagar Sanjay Nagar 1  
333 🔗 266 82Work of installing directional boards at various places in Ward 67, Sanjay Nagar. 9.89 03/09/2024 9.89 09 Sep 2024 09 Oct 2024  Rajender Singh 8178016904 Junior Engineer MEMBER KOTACompleted
100%
KAVI NAGARKamla Nehru Nagar Sanjay Nagar 1  
334 🔗 267 134Improvement work by interlocking tiles in damaged streets from B-317 to B-353 in Ward-68 Brajvihar. 8.62 01/09/2024 8.62 09 Sep 202420 Jan 2025 20 Jan 2025 V K CONTRACTOR 7982481495Sanjay Gangwar 8178016821 Junior Engineer MEMBER KOTACompleted
100%
VASUNDHRABrijvihar  
335 🔗 268 139Improvement work by interlocking tiles in the damaged streets from B-260 to B-352 and B-286 to B-322 in Ward-68 Brajvihar. 9.70 01/09/2024 9.70 07 Oct 202424 Jan 2025 24 Jan 2025 V K CONTRACTOR 7982481495Sanjay Gangwar 8178016821 Junior Engineer MEMBER KOTACompleted
100%
VASUNDHRABrijvihar  
336 🔗 269 75Repair of drains from D-17/1 to D-121 in D Block in Ward-68 Brajvihar and improvement work by interlocking tiles in damaged streets. 8.21 05/09/2024 8.21 09 Sep 202430 Dec 2024 15 Oct 2024 Chandra Mohan Singh Raguvanshi 9350003528Sanjay Gangwar 8178016821 Junior Engineer MEMBER KOTACompleted
100%
VASUNDHRABrijvihar  
337 🔗 270 54Repair of drain from D-152 to D-217 and D-124 in Ward-68 Brajvihar and improvement work by interlocking tiles in damaged streets. 7.18 05/09/2024 7.18 09 Sep 202410 Oct 2024 09 Oct 2024 J P GOEL 7838640695Sanjay Gangwar 8178016821 Junior Engineer MEMBER KOTACompleted
100%
VASUNDHRABrijvihar  
338 🔗 271 38Improvement work by interlocking tiles in Ward-68 Brajvihar from C-153 to C-158 and from C-162 to C-169 and from C-166 to the corner of the park. 9.75 05/09/2024 9.75 09 Sep 202410 Oct 2024 09 Oct 2024 J P GOEL 7838640695Sanjay Gangwar 8178016821 Junior Engineer MEMBER KOTACompleted
100%
VASUNDHRABrijvihar  
339 🔗 272 131Work of construction of interlocking tiles and drain on the side track in front of Yadavji Sweets in Ward-69, Lohianagar C-Block and from C-281 to C-287. 3.90 05/09/2024 3.90 09 Sep 2024 14 Oct 2024 Prakash Const NAGENDRA SHARMAJunior Engineer MEMBER KOTAIn Progress
80.00%
CITY ZONE Lohiya Nagar Lal Qtr  
340 🔗 273 171Road improvement work by DANS in Ward - 69, Lohia Nagar Lal Quarter from H.No. 76/1 to 76/7 via H.No. 73/1 and from H.No. 69/8 to 72/1 and from H.No. 87/1 to 93/1. 9.12 05/09/2024 9.12 07 Oct 2024 05 Mar 2025  NAGENDRA SHARMA 8882460223 Junior Engineer MEMBER KOTACompleted
100%
CITY ZONELohiya Nagar Lal Qtr  
341 🔗 274 81Work of interlocking tiles from E-57 to E-356 in Ward 71, Sanjaynagar E-Block. 4.74 03/09/2024 4.74 09 Sep 202414 Oct 2024 09 Oct 2024  Rajender Singh 8178016904 Junior Engineer MEMBER KOTACompleted
100%
KAVI NAGARSanjay Nagar 2  
342 🔗 275 80Work of interlocking tiles, Ward 71, Sanjaynagar E-468 to E-459. 5.68 03/09/2024 5.68 09 Sep 202410 Oct 2024 09 Oct 2024  Rajender Singh 8178016904 Junior Engineer MEMBER KOTACompleted
100%
KAVI NAGARSanjay Nagar 2  
343 🔗 276 171Construction work of public facility center in front of J-139 in Ward 71, Sanjaynagar J-Block. 5.18 03/09/2024 5.18 09 Nov 202415 Feb 2025 26 Dec 2024  Rajender Singh 8178016904 Junior Engineer MEMBER KOTACompleted
100%
KAVI NAGARSanjay Nagar 2  
344 🔗 277 125Road improvement work by Danes in Ward 71, Sanjay Nagar J-Block from J-190 to J-133, J-229 to J-277 and J-322 to J-313. 8.37 11/07/2024 8.37 09 Sep 2024 15 Oct 2024  Rajender Singh 8178016904 Junior Engineer MEMBER KOTACompleted
100%
KAVI NAGARSanjay Nagar 2  
345 🔗 278 36Construction work of damaged footpath from Veg Cinema to ICICI Bank in Ward-72 Kaushambi. 6.92 05/09/2024 6.92 09 Sep 2024 09 Oct 2024  Sanjay Gangwar 8178016821 Junior Engineer MEMBER KOTACompleted
100%
VASUNDHRAKaushambhi  
346 🔗 279 56Construction work of CC road from flat no. 126 to 125 in Ward-74 Sec-19 Satyam Enclave. 3.67 09/09/2024 3.67 09 Sep 2024 09 Sep 2024  Sanjay Gangwar 8178016821 Junior Engineer MEMBER KOTACompleted
100%
VASUNDHRAVasundhra 3  
347 🔗 280 113Work of laying mato sheet and construction of toilet at Public Service Centre in Ward 76, Vaishali Sector 2B. 3.88 09/09/2024 3.88 21 Oct 2024 30 Nov 2024  POOJA SINGH 8178016909 Junior Engineer MEMBER KOTACompleted
100%
VASUNDHRAVaishali Sec 1  
348 🔗 281 43Work of laying interlocking tiles on the road from house no. 1/530 to house no. 618 A Balaji Apartment in Ward 76, Sector 1, Vaishali. 7.56 05/09/2024 7.56 09 Sep 202406 Nov 2024 06 Nov 2024 NIKHIL ASSOCIATES 9891453311POOJA SINGH 8178016909 Junior Engineer MEMBER KOTACompleted
100%
VASUNDHRAVaishali Sec 1  
349 🔗 282 40Work of laying interlocking tiles on the road from Drona Classes via 2B 41 to H.No. 23 in Ward 76, S. 2B, Vaishali. 5.45 05/09/2024 5.45 09 Sep 2024 09 Oct 2024 H.R. Builders POOJA SINGHJunior Engineer MEMBER KOTACompleted
100%
VASUNDHRA Vaishali Sec 1  
350 🔗 283 130Work of construction of remaining wall of big drain in Ward 76, Vaishali Sector 2. 9.91 05/09/2024 9.91 21 Oct 202412 Dec 2024 12 Dec 2024 A.H Const. POOJA SINGHJunior Engineer MEMBER KOTACompleted
100%
VASUNDHRA Vaishali Sec 1  
351 🔗 284 58Work of laying interlocking tiles on the road between Buddha Vatika and Ram Vatika in Ward 76, Sec 2B, Vaishali. 3.20 05/09/2024 3.20 09 Sep 2024 09 Oct 2024  POOJA SINGH 8178016909 Junior Engineer MEMBER KOTACompleted
100%
VASUNDHRAVaishali Sec 1  
352 🔗 285 156Repair work of damaged road parallel to Gor Ganga II in Ward 77, Vaishali Sector 4 by Dense. 4.74 01/09/2024 4.74 07 Oct 2024 06 Mar 2025  POOJA SINGH 8178016909 Junior Engineer MEMBER KOTACompleted
100%
VASUNDHRAVaishali Sec 2  
353 🔗 286 89Construction work of drain and damaged street through C.C. in Gol Gappe street in ward 82, Jawahar Park. 9.88 05/09/2024 9.88 09 Sep 202415 Oct 2024 08 Oct 2024 Ujjwal Const. Vinod KumarJunior Engineer MEMBER KOTACompleted
100%
MOHAN NAGAR Jawahar Park  
354 🔗 287 86Construction work of drain from D9 to D1 in ward 83, Shyampur Ex. and construction work of interlocking tiles in the damaged street. 8.16 05/09/2024 8.16 09 Sep 202412 Nov 2024 08 Oct 2024 Pramood Kumar Singhal Vinod KumarJunior Engineer MEMBER KOTACompleted
100%
MOHAN NAGAR Shyam Park X  
355 🔗 288 171Construction work of drain from D 29 to D 35A in Ward 83 Shyampur Ex. and construction work of interlocking tiles in the damaged street. 3.45 05/09/2024 3.45 09 Sep 202412 Nov 2024 15 Oct 2024 Mohit Choudhary Vinod KumarJunior Engineer MEMBER KOTACompleted
100%
MOHAN NAGAR Shyam Park X  
356 🔗 289 1344Road improvement work by DANS from 06/199 to 06/186, 06/172 to 06/185, 06/35 to 06/47 in Ward 84, Rajnagar Sector-06. 9.85 03/09/2024 9.85 09 Sep 202415 Oct 2024 15 Oct 2024  Rajender Singh 8178016904 Junior Engineer MEMBER KOTACompleted
100%
KAVI NAGARRajNagar  
357 🔗 290 76Construction work by interlocking tiles in various streets of L Block in Ward 85, Lajpat Nagar. 8.71 05/09/2024 8.71 09 Sep 202412 Dec 2024 08 Oct 2024 Ujjwal Const. Vinod KumarJunior Engineer MEMBER KOTACompleted
100%
MOHAN NAGAR Lajpat Nagar 2  
358 🔗 291 150Road improvement work by HIG-04 in Ward 86 Rajendra Nagar Road 05. 8.18 05/09/2024 8.18 09 Sep 202415 Oct 2024 15 Oct 2024 R.G. Builtach Engg. Ltd. Vinod KumarJunior Engineer MEMBER KOTACompleted
100%
MOHAN NAGAR Rajendra Nagar Sec5  
359 🔗 292 39Work of interlocking tiles on side track in composite school in Ward - 87, Justice Section 03, Indirapuram Makanpur. 4.96 05/09/2024 4.96 09 Sep 202406 Nov 2024 09 Oct 2024 R.R. Const. POOJA SINGHJunior Engineer MEMBER KOTACompleted
100%
VASUNDHRA Gyankhand Indrapuram  
360 🔗 293 71Construction work of drain and C.C. road in the damaged lane from Haji Nizam's house to Alamm Food in Ward No. 90 Shahid Nagar III. 7.43 05/09/2024 7.43 09 Sep 202412 Nov 2024 07 Oct 2024 Star Enter. Sanjay GangwarJunior Engineer MEMBER KOTACompleted
100%
MOHAN NAGAR Shahid Nagar 2  
361 🔗 294 73Construction work of drain and C.C. road in the damaged lane from Sharif's house to Aash Mohammad's house in lane no. 01 of ward 90 Shahid Nagar III. 8.25 05/09/2024 8.25 09 Sep 202412 Nov 2024 07 Oct 2024 Star Enter. Sanjay GangwarJunior Engineer MEMBER KOTACompleted
100%
MOHAN NAGAR Shahid Nagar 2  
362 🔗 295 72Construction work of drain and C.C. road in the damaged lane from Aash Mohammad's house to Haji Jamma's house in lane no. 01 of ward 90 Shaheednagar III. 7.42 07/10/2024 7.42 09 Sep 202412 Nov 2024 07 Oct 2024 Star Enter. Sanjay GangwarJunior Engineer MEMBER KOTACompleted
100%
MOHAN NAGAR Shahid Nagar 2  
363 🔗 296 56C.C. work in service lane behind K.C./E-55 to K.C./E-25A in C-Block, Ward 91, Kavi Nagar. 9.92 04/09/2024 9.92 09 Sep 202412 Dec 2024 09 Oct 2024  Rajender Singh 8178016904 Junior Engineer MEMBER KOTACompleted
100%
KAVI NAGARKavi nagar  
364 🔗 297 66Work of interlocking tiles in front of KC-128 and KC/CC-20 in Ward 91, Kavi Nagar C-Block. 1.12 04/09/2024 1.12 09 Sep 2024 09 Oct 2024  Rajender Singh 8178016904 Junior Engineer MEMBER KOTACompleted
100%
KAVI NAGARKavi nagar  
365 🔗 298 53Work of interlocking tiles in front of KF-63 and KF-64 in Ward 91, Kavinagar F-Block. 2.82 04/09/2024 2.82 09 Sep 2024 09 Oct 2024  Rajender Singh 8178016904 Junior Engineer MEMBER KOTACompleted
100%
KAVI NAGARKavi nagar  
366 🔗 299 55CC work in service lane from KJ-42 to KJ-60 in Ward 91, Kavi Nagar J-Block. 9.01 04/09/2024 9.01 09 Sep 202423 Nov 2024 09 Oct 2024  Rajender Singh 8178016904 Junior Engineer MEMBER KOTACompleted
100%
KAVI NAGARKavi nagar  
367 🔗 300 70Work of interlocking tiles from KL-01 to KL-40 in Ward 91, Kavinagar L-Block. 5.56 04/09/2024 5.56 09 Sep 202423 Nov 2024 09 Oct 2024  Rajender Singh 8178016904 Junior Engineer MEMBER KOTACompleted
100%
KAVI NAGARKavi nagar  
368 🔗 301  Work of drain and C.C. road from Haji Shamsuddin to Maharaj's house in Ward-92, Kaila Islamnagar. 8.73 11/07/2024 8.73 09 Sep 2024   NAGENDRA SHARMAJunior Engineer MEMBER KOTA 
0%
CITY ZONE Kaila Islam Nagar  
369 🔗 302 59Work of repair of wall, chamber, net, RCC and Hume pipe and C.C. in front of Shri Rashid, Anwar, Aziz and Nazir shop in Ward-92, Kaila Islamnagar. 2.83 05/09/2024 2.83 09 Sep 2024 09 Oct 2024 K.K const. NAGENDRA SHARMAJunior Engineer MEMBER KOTACompleted
100%
CITY ZONE Kaila Islam Nagar  
370 🔗 303 65Repair work of drain/sewer, culvert and C.C. in front of Shri Nadeem, Nasir Building, Bashir, Indian Medical, Zarif, Jarrah, Hakeem, Ramzani, Meenu, Main Road and Farooq's house in Ward-93, Kaila Bhatta. 2.87 02/09/2024 2.87 09 Sep 2024 09 Oct 2024 A.H Const. NAGENDRA SHARMAJunior Engineer MEMBER KOTACompleted
100%
CITY ZONE Kaila Bhatta  
371 🔗 304 123Work of drain and C.C. from Tayyab Qureshi to Shakeel's house and from Haji Bundu to Lahik in Ward-93, Kaila Bhatta. 6.29 05/09/2024 6.29 09 Sep 2024 14 Oct 2024 J P Sakti NAGENDRA SHARMAJunior Engineer MEMBER KOTACompleted
100%
CITY ZONE Kaila Bhatta  
372 🔗 305 34Road improvement work by interlocking on damaged site plate from B-08 to B-11 in Alaknanda Apartment in Ward 94 Suryanagar Rampuri. 4.30 05/09/2024 4.30 09 Sep 202415 Jan 2025 09 Oct 2024  POOJA SINGH 8178016909 Junior Engineer MEMBER KOTACompleted
100%
VASUNDHRASurya Nagar  
373 🔗 306 130Ward-92, Kaila Bhatta, lane no. 01 from Haji Khalil Qureshi to Haji Yasin and lane no. 02 from Indra Sardar to Shama and Yusuf and Salim's house and from Imran to Kalu's house. Construction of C.C. road and drain. 7.95 07/09/2024 7.95 09 Sep 2024 14 Oct 2024 Mahima Const. NAGENDRA SHARMAJunior Engineer MEMBER KOTACompleted
100%
CITY ZONE Kaila Islam Nagar  
374 🔗 307 66RCC road construction work from Sabir's house to Jumayeraullah Khan's house in Ward-95, Kaila Bhatta Habib Colony. 8.35 07/09/2024 8.35 09 Sep 2024 09 Oct 2024 A.P Const. NAGENDRA SHARMAJunior Engineer MEMBER KOTACompleted
100%
CITY ZONE Premnagar Kaila  
375 🔗 308 63Ward-95, RCC road construction work from Kaila Bhatta Habib Colony Gate to Haji Babu's house. 8.99 07/09/2024 8.99 09 Sep 2024 09 Oct 2024 A.P Const. NAGENDRA SHARMAJunior Engineer MEMBER KOTACompleted
100%
CITY ZONE Premnagar Kaila  
376 🔗 309 158Road improvement work by Danes from C-01 to C-10 and C-13 to C-41 in Ward-96, Nehrunagar-Second and interlocking tiles work from A-72 to A-74 in Ashoknagar. 9.54 05/09/2024 9.54 26 Nov 202428 Jan 2025 28 Jan 2025 P.P. Reyalcon Pvt.Ltd. Preeti BansalJunior Engineer MEMBER KOTACompleted
100%
CITY ZONE Nehru Nagar 3  
Fund Name: NIGAM NIDHI 2024-25
377 🔗 310  Ward-96, Nehrunagar - Road improvement work by Danes from 3rd E-144 to H.No.-05 and from 3rd-E-30 to 3rd-E-179 and work of interlocking tiles in service lane from 3rd-E-60 to 3rd-E-54. 9.09 11/07/2024 9.09 09 Sep 2024   NAGENDRA SHARMAJunior Engineer MEMBER KOTA 
0%
CITY ZONE Nehru Nagar 3  
378 🔗 319 93Repair and painting work of Chhath Ghat situated on Hindon River in Ward-44, Sanjay Colony and Chhath Ghat near Sahibabad Station Shani Temple and barricading work in the river. 9.26 18/09/2024 9.26 19 Sep 202415 Oct 2024 08 Oct 2024 Global Engg. & Infra. Sanjay GangwarJunior Engineer NIGAM NIDHI 2024-25Completed
100%
MOHAN NAGAR Sanjay Colony  
379 🔗 320 47Repair and painting work of Chhath Ghat under Kavi Nagar Zone. 9.06 18/09/2024 9.06 19 Sep 202410 Oct 2024 04 Oct 2024  Rajender Singh 8178016904 Junior Engineer NIGAM NIDHI 2024-25Completed
100%
KAVI NAGARMorta  
380 🔗 321 94Repair and painting work of Chhath Ghat under Mohan Nagar Zone. 7.55 18/09/2024 7.55 19 Sep 202415 Oct 2024 08 Oct 2024 Global Engg. & Infra. Vinod KumarJunior Engineer NIGAM NIDHI 2024-25Completed
100%
MOHAN NAGAR    
381 🔗 322 96Repair and painting work of Chhath Ghat in Ward-03/25/51/55 under Vijaynagar Zone. 2.33 18/09/2024 2.33 07 Oct 202413 Dec 2024 10 Dec 2024 Pradhan Contr. SHIV KUMAR SAROJJunior Engineer NIGAM NIDHI 2024-25Completed
100%
VIJAY NAGAR   
382 🔗 323 51Patch repair work at various places in Ward-51 and 55 under Vijaynagar Zone. (Access road to Ramlila Ground) 5.82 26/09/2024 5.82 19 Sep 202414 Oct 2024 09 Oct 2024 Modern Engg. Asso. SHIV KUMAR SAROJJunior Engineer NIGAM NIDHI 2024-25Completed
100%
VIJAY NAGAR   
383 🔗 324 163Patch repair work at various places in Ward-91, Kavi Nagar. 4.54 05/09/2024 4.54 09 Nov 202405 Feb 2025 05 Feb 2025  Rajender Singh 8178016904 Junior Engineer NIGAM NIDHI 2024-25Completed
100%
KAVI NAGARKavi nagar  
384 🔗 325 76Patch repair work at various places in Ward-71, Sanjaynagar. 9.81 05/09/2024 9.81 27 Sep 202415 Oct 2024 09 Oct 2024  Rajender Singh 8178016904 Junior Engineer NIGAM NIDHI 2024-25Completed
100%
KAVI NAGARSanjay Nagar 2  
385 🔗 326 83Patch repair work on Raispur Road in Ward-67, Sanjaynagar. 9.24 05/09/2024 9.24 19 Sep 202415 Oct 2024 09 Oct 2024  Rajender Singh 8178016904 Junior Engineer NIGAM NIDHI 2024-25Completed
100%
KAVI NAGARKamla Nehru Nagar Sanjay Nagar 1  
386 🔗 327 75Patch repair work on CNG Pump Road, Ward-62, Govindpuram. 7.62 05/09/2024 7.62 19 Sep 202415 Oct 2024 09 Oct 2024  Rajender Singh 8178016904 Junior Engineer NIGAM NIDHI 2024-25Completed
100%
KAVI NAGARGovindpuram Harsav  
387 🔗 328 84Patch repair work on Road No. 03, Ward-62, Govindpuram. 9.85 05/09/2024 9.85 27 Sep 202415 Oct 2024 09 Oct 2024  Rajender Singh 8178016904 Junior Engineer NIGAM NIDHI 2024-25Completed
100%
KAVI NAGARGovindpuram Harsav  
388 🔗 329 72Patch repair work on Road No. 02, Ward-62, Govindpuram. 9.98 05/09/2024 9.98 27 Sep 202415 Oct 2024 09 Oct 2024  Rajender Singh 8178016904 Junior Engineer NIGAM NIDHI 2024-25Completed
100%
KAVI NAGARGovindpuram Harsav  
389 🔗 330 73Patch repair work at various places in Ward-56, Chiranjiv Vihar. 4.15 05/09/2024 4.15 27 Sep 202402 Dec 2024 09 Oct 2024  Rajender Singh 8178016904 Junior Engineer NIGAM NIDHI 2024-25Completed
100%
KAVI NAGARChiranjeev Vihar  
390 🔗 331 78Patch repair work at various places in Ward-47, Shastri Nagar. 8.23 05/09/2024 8.23 19 Sep 202405 Oct 2024 09 Oct 2024 R G BUILDTECH ENGINEERS LTD 9810616350Rajender Singh 8178016904 Junior Engineer NIGAM NIDHI 2024-25Completed
100%
KAVI NAGARShastrinagar Mahendra Encalave  
391 🔗 332 73Patch repair work at various places in Ward-18, Rajapur and Shastrinagar. 9.47 05/09/2024 9.47 19 Sep 202402 Dec 2024 09 Oct 2024 Akansha Construction Rajender Singh 8178016904 Junior Engineer NIGAM NIDHI 2024-25Completed
100%
KAVI NAGARRajapur ShastriNagar  
392 🔗 333 79Patch repair work at various places on Ramlila route in Ward-84, Rajnagar. 9.32 19/09/2024 9.32 19 Sep 202415 Oct 2024 09 Oct 2024  Rajender Singh 8178016904 Junior Engineer NIGAM NIDHI 2024-25Completed
100%
KAVI NAGARRajNagar  
393 🔗 334 77Patch repair work at various places in Ward-56, Chinrajeev Vihar and Avantika Pratham. 9.42 05/09/2024 9.42 19 Sep 202402 Dec 2024 09 Oct 2024  Rajender Singh 8178016904 Junior Engineer NIGAM NIDHI 2024-25Completed
100%
KAVI NAGARChiranjeev Vihar  
394 🔗 335 46Patch repair work on main road and Mother Dairy in Ward-54 Sector 11 and 13. 8.35 11/09/2024 8.35 19 Sep 202415 Oct 2024 09 Oct 2024  Sanjay Gangwar 8178016821 Junior Engineer NIGAM NIDHI 2024-25Completed
100%
VASUNDHRAVashundhra-1  
395 🔗 336 50Patch repair work on main road and Shop Prex Mall of Ward-89, 77 Vaishali Sector 3,2,4,5. 9.69 11/09/2024 9.69 19 Sep 202406 Nov 2024 27 Sep 2024 RG Buildtech Engg. Ltd. Sanjay GangwarJunior Engineer NIGAM NIDHI 2024-25Completed
100%
VASUNDHRA    
396 🔗 337 41Patch repair work in wards 54 and 74 from Sector 1 cut Vasundhara via Kanawani culvert via Sector-19 Vasundhara to K.R.Mangalam cut of Sector-6 Vaishali on Gurudwara road. 9.78 11/09/2024 9.78 19 Sep 202415 Oct 2024 09 Oct 2024 RG Buildtech Engg. Ltd. Sanjay GangwarJunior Engineer NIGAM NIDHI 2024-25Completed
100%
VASUNDHRA    
397 🔗 338 45Patch repair work on service road Radisson Gajab Street and Shukra Bazar Road in Ward-21. 9.36 11/09/2024 9.36 19 Sep 202415 Oct 2024 09 Oct 2024 RG Buildtech Engg. Ltd. Sanjay GangwarJunior Engineer NIGAM NIDHI 2024-25Completed
100%
VASUNDHRA Bhoowa Pura  
398 🔗 339 44Patch repair work of damaged potholes on the main road of Sahibabad Industrial Area Site-4 under Vasundhara Zone by Danes. 9.98 11/09/2024 9.98 19 Sep 202415 Oct 2024 09 Oct 2024 RG Buildtech Engg. Ltd. Sanjay GangwarJunior Engineer NIGAM NIDHI 2024-25Completed
100%
VASUNDHRA    
399 🔗 340 51Patch repair work on the internal roads of Vaishali Sector-2 B/2 C, Vaishali 3 Rachna Naveen Hospital Marg, Jain Mandir Marg and Vaishali Sector-1 in Ward-76, 77. 9.97 11/09/2024 9.97 19 Sep 202415 Oct 2024 09 Oct 2024 RG Buildtech Engg. Ltd. Sanjay GangwarJunior Engineer NIGAM NIDHI 2024-25Completed
100%
VASUNDHRA    
400 🔗 341 49Patch repair work on Ward-68 Braj Vihar main road and Radha Kunj Colony and Braj Vihar A and D Block roads. 9.73 11/09/2024 9.73 19 Sep 202415 Oct 2024 09 Oct 2024 R G BUILDTECH ENGINEERS LTD 9810616350Sanjay Gangwar 8178016821 Junior Engineer NIGAM NIDHI 2024-25Completed
100%
VASUNDHRABrijvihar  
Fund Name: MEMBER KOTA 2024-25(II)
401 🔗 342 42Patch repair work on service road of Ward-36 Vasundhara Sector 12 and 14. 9.38 11/09/2024 9.38 19 Sep 202415 Oct 2024 09 Oct 2024 RG Buildtech Engg. Ltd. Sanjay GangwarJunior Engineer NIGAM NIDHI 2024-25Completed
100%
VASUNDHRA    
402 🔗 796  Construction work of CC road and drain from Fateh Bahadur Yadav to Vijay Sharma's house near Children Public School, Ward-03. 7.14 30/01/2025 7.14 21 Mar 2025  OTHER SHIV KUMAR SAROJ 8178016826 Junior Engineer MEMBER KOTA 2024-25(II)Completed
100%
VIJAY NAGARPurana Vijay Nagar  
403 🔗 797  Construction work of drain from A-1 to A-16 and Akhilesh's house in ward 83 Shyampur Ex. and construction work of interlocking tiles in the damaged street. 7.15 30/01/2025 7.15 21 Mar 2025   Vinod Kumar 8650930015 Junior Engineer MEMBER KOTA 2024-25(II)Completed
100%
MOHAN NAGARShyam Park X  
404 🔗 798  Construction work of CC road and RCC drain from Sundar Singh's house to Ashish's house via Rohtas's house in Ward-03, H Block. 7.16 30/01/2025 7.16 21 Mar 2025  OTHER SHIV KUMAR SAROJ 8178016826 Junior Engineer MEMBER KOTA 2024-25(II)Completed
100%
VIJAY NAGARPurana Vijay Nagar  
405 🔗 799  Work of interlocking tiles inside Gautam Buddha Park in Ward-12, Kalkagarhi and on the side pavement of the road in front of Suchita Complex. 7.24 30/01/2025 7.24 21 Mar 2025  M.D. Enter. NAGENDRA SHARMAJunior Engineer MEMBER KOTA 2024-25(II) 
0%
CITY ZONE Kalkagadi, Jatavbada  
406 🔗 800 2Road improvement work through interlocking tiles from E-184 to E-201 and E-124 to E-103 in Ward 55 E-Block. 7.31 06/03/2025 7.31 21 Mar 202516 Jun 2025 16 Jun 2025 OTHER SHIV KUMAR SAROJ 8178016826 Junior Engineer MEMBER KOTA 2024-25(II)Completed
100%
VIJAY NAGARVijay Nagar sec11 block-A  
Fund Name: NIGAM NIDHI 2024-25
407 🔗 801  Construction work of drain and C.C. road in the street from Gurudwara to Haseen's house in ward 34 Shaheednagar Pratham. 7.34 30/01/2025 7.34 21 Mar 2025   Sanjay Gangwar 8178016821 Junior Engineer MEMBER KOTA 2024-25(II)Completed
100%
MOHAN NAGARShaheed Nagar First  
408 🔗 343 48Patch repair work on the roads of Double Zonal Office Road, Sector 10B main road and Sector-10, 12, 14 Vasundhara between Ward-61, 36. 9.68 11/09/2024 9.68 19 Sep 202410 Oct 2024 09 Oct 2024 Arun Const.Co. Sanjay GangwarJunior Engineer NIGAM NIDHI 2024-25Completed
100%
VASUNDHRA    
409 🔗 344 47Patch repair work on Dr. Burman Marg in Ward-72 Kaushambi. 9.95 11/09/2024 9.95 19 Sep 202410 Oct 2024 09 Oct 2024 ARUN CONSTRUCTION CO 9312626727Sanjay Gangwar 8178016821 Junior Engineer NIGAM NIDHI 2024-25Completed
100%
VASUNDHRAKaushambhi  
410 🔗 345 109Road improvement work by patch near H.No. 11/9A, 11/104 and 11/6 in Ward-83, Rajendra Nagar Sector-11. 6.01 18/09/2024 6.01 19 Sep 202414 Oct 2024 09 Oct 2024 R.G. Builtach Engg. Ltd. Vinod KumarJunior Engineer NIGAM NIDHI 2024-25Completed
100%
MOHAN NAGAR Shyam Park X  
411 🔗 346 106Road improvement work by patch from plot no. 870 to 823 in Ward-78, Shalimar Garden Ex-1. 9.40 18/09/2024 9.40 27 Sep 202414 Oct 2024 09 Oct 2024 Maheshn Cand Contr. Vinod KumarJunior Engineer NIGAM NIDHI 2024-25Completed
100%
MOHAN NAGAR Shalimar Garden X 1st  
412 🔗 347 105Road improvement work by patch work at various locations in Ward-70, Janakpuri and Vrindavan Garden. 9.64 18/09/2024 9.64 19 Sep 202414 Oct 2024 09 Oct 2024 Maheshn Cand Contr. Vinod KumarJunior Engineer NIGAM NIDHI 2024-25Completed
100%
MOHAN NAGAR Janakpuri  
413 🔗 348 107Road improvement work by patch work from Shanti Mandar Kutir to Harihar Mandar's house in Ward - 28. 9.11 18/09/2024 9.11 19 Sep 202414 Oct 2024 09 Oct 2024 Maheshn Cand Contr. Vinod KumarJunior Engineer NIGAM NIDHI 2024-25Completed
100%
MOHAN NAGAR Rajeev Colony  
414 🔗 349 112Road improvement work by patch work in front of Swami Vivekananda School, Ward-83, Rajendra Nagar. 8.78 18/09/2024 8.78 19 Sep 202414 Oct 2024 10 Oct 2024 R.G. Builtach Engg. Ltd. Vinod KumarJunior Engineer NIGAM NIDHI 2024-25Completed
100%
MOHAN NAGAR Shyam Park X  
415 🔗 350 108Patch improvement work of main Jain temple road, Ward-70, Rajbagh. 8.14 18/09/2024 8.14 19 Sep 202414 Oct 2024 09 Oct 2024 Maheshn Cand Contr. Vinod KumarJunior Engineer NIGAM NIDHI 2024-25Completed
100%
MOHAN NAGAR Janakpuri  
416 🔗 351 104Road improvement work by patch near 10/4,10/6,10/9,10/7 and 10/20 in Ward-83, Rajendra Nagar. 7.15 18/09/2024 7.15 19 Sep 202414 Oct 2024 09 Oct 2024 R.G. Builtach Engg. Ltd. Vinod KumarJunior Engineer NIGAM NIDHI 2024-25Completed
100%
MOHAN NAGAR Shyam Park X  
417 🔗 352 110Road improvement work by patch on the road between Ward-83 and 86. 7.66 18/09/2024 7.66 19 Sep 202414 Oct 2024 09 Oct 2024 R.G. Builtach Engg. Ltd. Vinod KumarJunior Engineer NIGAM NIDHI 2024-25Completed
100%
MOHAN NAGAR Shyam Park X  
418 🔗 353 112Patch repair work near Mother Dairy, Chatore and H.No. 342 & 343 on Maurya Road in Mohan Nagar Zone. 9.52 18/09/2024 9.52 19 Sep 202414 Oct 2024 10 Oct 2024 R.G. Builtach Engg. Ltd. Vinod KumarJunior Engineer NIGAM NIDHI 2024-25Completed
100%
MOHAN NAGAR    
419 🔗 354 99Patch repair work of damaged road from Radha Krishna Wali Road and Padav culvert to community building in Ward no. 38 and 44. 9.02 07/09/2024 9.02 19 Sep 2024 09 Oct 2024  Sanjay Gangwar 8178016821 Junior Engineer NIGAM NIDHI 2024-25Completed
100%
MOHAN NAGARSanjay Colony  
420 🔗 355 98Patch repair work of damaged roads at various places in Ward-34 and 90 Shaheednagar. 9.95 17/09/2024 9.95 19 Sep 2024 09 Oct 2024  Sanjay Gangwar 8178016821 Junior Engineer NIGAM NIDHI 2024-25Completed
100%
MOHAN NAGARGagan Vihar  
421 🔗 356 103Patch repair work of damaged road from Sahibabad Railway Station Cut GT Road Light to Girls Hostel in Ward-60, Shyampur Main. 8.57 13/09/2024 8.57 19 Sep 202414 Oct 2024 09 Oct 2024 R.G. Builtach Engg. Ltd. Sanjay GangwarJunior Engineer NIGAM NIDHI 2024-25Completed
100%
MOHAN NAGAR Shyampark main  
422 🔗 357 114Repair work of damaged road by patch work from Seal Pack Company to Plot No. 80J of Rajendra Nagar Industrial Area, Ward-60, Shyampur Main. 9.98 13/09/2024 9.98 19 Sep 202414 Oct 2024 10 Oct 2024 R.G. Builtach Engg. Ltd. Sanjay GangwarJunior Engineer NIGAM NIDHI 2024-25Completed
100%
MOHAN NAGAR Shyampark main  
423 🔗 358 102Repair work by patching the damaged road in lane no. 04 of Rajendra Nagar India Area in Ward-60, Shyampur Main. 9.65 13/09/2024 9.65 19 Sep 202414 Oct 2024 09 Oct 2024 R.G. Builtach Engg. Ltd. Sanjay GangwarJunior Engineer NIGAM NIDHI 2024-25Completed
100%
MOHAN NAGAR Shyampark main  
424 🔗 359 101Patch repair work of the main damaged road of Rajendra Nagar Ind Area of ​​Ward-60, Shyampur Main. 9.87 13/09/2024 9.87 19 Sep 202414 Oct 2024 09 Oct 2024 R.G. Builtach Engg. Ltd. Sanjay GangwarJunior Engineer NIGAM NIDHI 2024-25Completed
100%
MOHAN NAGAR Shyampark main  
425 🔗 360 71Patch repair work at various places in Ward-52 of City Zone, Old Aryanagar Road and Model Town. 9.76 19/09/2024 9.76 27 Sep 202425 Oct 2024 10 Oct 2024 Prateek Enter. Preeti BansalJunior Engineer NIGAM NIDHI 2024-25Completed
100%
CITY ZONE Aryanagar Kotgaon  
426 🔗 361 76Punch repair work at various places in Ward-31, Sihani Main Road, the road in front of Shagun Farm House and Ward-50. 9.94 17/09/2024 9.94 19 Sep 202410 Oct 2024 10 Oct 2024 Arun Const.Co. Preeti BansalJunior Engineer NIGAM NIDHI 2024-25Completed
100%
CITY ZONE    
427 🔗 362 77Patch repair work at various places in Ward-19 under City Zone. 5.88 17/09/2024 5.88 19 Sep 202414 Oct 2024 10 Oct 2024 Arun Const.Co. Preeti BansalJunior Engineer NIGAM NIDHI 2024-25Completed
100%
CITY ZONE Patel Nagar, Mukandnagar  
428 🔗 363 86Patch repair work at various places in Ward-08 and 69 under City Zone. 9.97 17/09/2024 9.97 19 Sep 202410 Oct 2024 10 Oct 2024 Arun Const.Co. Preeti BansalJunior Engineer NIGAM NIDHI 2024-25Completed
100%
CITY ZONE    
429 🔗 364 75Patch repair work at various places in Ward-09 and 49 under City Zone. 9.82 17/09/2024 9.82 19 Sep 2024 10 Oct 2024 Modern Engg. Asso. NAGENDRA SHARMAJunior Engineer NIGAM NIDHI 2024-25Completed
100%
CITY ZONE    
Fund Name: HON.MAYOR
430 🔗 365 72Patch repair work at various places in Wards 12, 88 and 96 under City Zone. 9.94 17/09/2024 9.94 27 Sep 202415 Oct 2024 15 Oct 2024 Prateek Enter. NAGENDRA SHARMAJunior Engineer NIGAM NIDHI 2024-25Completed
100%
CITY ZONE    
431 🔗 366 79Work of drain and interlocking tiles on both sides from Arvind Medical Store to Viru Choudhary's house via Bittu Choudhary in Ward - 50 Shanti Nagar and work of drain till Mithlesh's house. 18.37 18/09/2024 18.37 19 Sep 2024 10 Oct 2024 A.S. Const. NAGENDRA SHARMAJunior Engineer HON.MAYORIn Progress
0.00%
CITY ZONE Saddiknagar, Noornagar  
432 🔗 367 85Work of construction of interlocking tiles on the road leading to the cremation ground located at Ward-50, Rajnagar Extension Road, Noor Nagar. 6.30 10/09/2024 6.30 19 Sep 202414 Oct 2024 10 Oct 2024 Juber Const SHIV KUMAR SAROJJunior Engineer HON.MAYORCompleted
100%
CITY ZONE Saddiknagar, Noornagar  
433 🔗 368 136Work of construction of interlocking tiles and drain from Nathu Singh's house to Birbal Sharma's house on Bhatt Road in Ward-13 Ghukna. 2.80 10/09/2024 2.80 07 Oct 202412 Dec 2024 12 Dec 2024 J.P. Shakti Const. Preeti BansalJunior Engineer HON.MAYORCompleted
100%
CITY ZONE Ghukna  
434 🔗 369 134Work of drain and interlocking tiles from Deendayal Sharma to Sonu Tyagi in Ward-11 Nandgram Brajnagri. 12.60 18/09/2024 12.60 07 Oct 202413 Dec 2024 13 Dec 2024 Zuber Const. Preeti BansalJunior Engineer HON.MAYORCompleted
100%
CITY ZONE Nandgram, Deendayal puri  
435 🔗 370 154Work of drain and interlocking tiles from Shashibala's house to Rajiv Tyagi's house and from Adesh Tyagi to Rajni Sharma's house in Ward-50 Saraswati Vihar. 11.77 18/09/2024 11.77 07 Oct 202420 Jan 2025 20 Jan 2025  NAGENDRA SHARMA 8882460223 Junior Engineer HON.MAYORCompleted
100%
CITY ZONESaddiknagar, Noornagar  
436 🔗 371 90Work of interlocking tiles on the damaged road in front of Gadhi village on Ward-16 Vardaan Road. 23.52 18/09/2024 23.52 19 Sep 2024 10 Oct 2024  Rajender Singh 8178016904 Junior Engineer HON.MAYORCompleted
100%
KAVI NAGARMorta  
437 🔗 372 87Work of drain and interlocking tiles from Shiv Properties to Amit Bhatnagar's house in Ward-46 New Friends Colony. 11.87 18/09/2024 11.87 19 Sep 2024 10 Oct 2024 Om Enterprises 9891019900Rajender Singh 8178016904 Junior Engineer HON.MAYORCompleted
100%
KAVI NAGARGuldhar Duhai  
438 🔗 373 85Work of drain and interlocking tiles from the house of Mahesh Tyagi to the house of Raje Sharma in Ward-16 Morta. 14.86 18/09/2024 14.86 19 Sep 2024 10 Oct 2024 Om Enterprises 9891019900Rajender Singh 8178016904 Junior Engineer HON.MAYORCompleted
100%
KAVI NAGARMorta  
439 🔗 374 99Road improvement work by Danes in Ward-47 Shastri Nagar C-Block from Raj Gas Agency to SC-231, SC-231 to SC-287, SC-263 street, SC-302 to SC-315 and SC-256 to SC-251. 29.59 18/09/2024 29.59 19 Sep 2024 10 Oct 2024 PRATEEK ENTERPRISES 9311881082Rajender Singh 8178016904 Junior Engineer HON.MAYORCompleted
100%
KAVI NAGARShastrinagar Mahendra Encalave  
440 🔗 375 98Ward-91 Kavi Nagar I Block K.I. Repair of drain from 01 to K.I.16 and tiling work on site track. 7.08 10/09/2024 7.08 19 Sep 202412 Dec 2024 10 Oct 2024  Rajender Singh 8178016904 Junior Engineer HON.MAYORCompleted
100%
KAVI NAGARKavi nagar  
441 🔗 376 92Work of drain and interlocking tiles from Manoj's house to Yograj's house in Ward-30 Radha Garden. 6.35 11/09/2024 6.35 19 Sep 202415 Oct 2024 10 Oct 2024 J S S CONSTRUCTION 9999280744Rajender Singh 8178016904 Junior Engineer HON.MAYORCompleted
100%
KAVI NAGARSadarpur, Govind puram  
442 🔗 377 93Road improvement work through drain and Dense from C-83/64 to C-83/77 in Ward-62 Govindpuram C-Block. 20.60 18/09/2024 20.60 19 Sep 202415 Oct 2024 10 Oct 2024  Rajender Singh 8178016904 Junior Engineer HON.MAYORCompleted
100%
KAVI NAGARGovindpuram Harsav  
443 🔗 378 94Road improvement work through drain and Dense in Ward-62 Govindpuram C-Block from C-83/82 to C-83/102, 83/102 to 83/98, 83/96 to 83/89, 83/89 to 83/82. 24.10 17/09/2024 24.10 19 Sep 2024 10 Oct 2024  Rajender Singh 8178016904 Junior Engineer HON.MAYORCompleted
100%
KAVI NAGARGovindpuram Harsav  
444 🔗 379 142Work of drain and interlocking tiles from B-15 to B-105 in Ward-47, Mahendra Enclave. 23.18 20/02/2024 23.18 19 Sep 202415 Oct 2024 15 Oct 2024 A S CONSTRUCTIONS (AAQFA8231R) 8630570065Rajender Singh 8178016904 Junior Engineer HON.MAYORCompleted
100%
KAVI NAGARShastrinagar Mahendra Encalave  
445 🔗 380 95Work of drain and interlocking tiles from Anil's house to Vision Singh's house in Ward-30, Surya Garden. 4.50 19/09/2024 4.50 19 Sep 202415 Oct 2024 10 Oct 2024 J S S CONSTRUCTION 9999280744Rajender Singh 8178016904 Junior Engineer HON.MAYORCompleted
100%
KAVI NAGARSadarpur, Govind puram  
446 🔗 381 96RCC drain construction work from MAS Steel/Gali No.-04 to Gali No.-15 in Ward-30, Balaji Enclave. 29.86 19/09/2024 29.86 19 Sep 2024 10 Oct 2024 MODERN ENGINEERING ASSOCIATES 9810426008Rajender Singh 8178016904 Junior Engineer HON.MAYORCompleted
100%
KAVI NAGARSadarpur, Govind puram  
447 🔗 382 91Work of RCC drain and interlocking tiles in Raghuveer Tour & Travels/Gali No.16 to Gali No.9 in Ward-30, Balaji Enclave. 29.84 19/09/2024 29.84 19 Sep 2024 10 Oct 2024 MODERN ENGINEERING ASSOCIATES 9810426008Rajender Singh 8178016904 Junior Engineer HON.MAYORCompleted
100%
KAVI NAGARSadarpur, Govind puram  
448 🔗 383 97Work of interlocking tiles from King Gym to B-153 via B-163 in Ward-47, Mahendra Enclave. 14.67 19/09/2024 14.67 19 Sep 202414 Oct 2024 10 Oct 2024 A S CONSTRUCTIONS (AAQFA8231R) 8630570065Rajender Singh 8178016904 Junior Engineer HON.MAYORCompleted
100%
KAVI NAGARShastrinagar Mahendra Encalave  
Fund Name: MEMBER KOTA
449 🔗 384 88Work of drain and interlocking tiles from Primary School to Baljagat School in Ward-16, Sikrod Village. 27.42 19/09/2024 27.42 19 Sep 202403 Jan 2025 10 Oct 2024 Om Enterprises 9891019900Rajender Singh 8178016904 Junior Engineer HON.MAYORCompleted
100%
KAVI NAGARMorta  
450 🔗 385 132Ward-01, Bhim Nagar Street No. 08, from Subhash Pal to Mohan Kumar, repair of drains and improvement of damaged road by C.C. road. 14.96 10/09/2024 14.96 19 Sep 2024 24 Dec 2024 PRADHAN CONTRACTOR 9625326078SHIV KUMAR SAROJ 8178016826 Junior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARBagu Kischayan Nagar  
451 🔗 386 54Road improvement work of interlocking tiles on the damaged road from Roshan's house to Vinay's shop in Ward-02, Siddharth Vihar, Street No. 08 AB. 11.84 10/09/2024 11.84 19 Sep 2024 10 Oct 2024 A S CONSTRUCTIONS (AAQFA8231R) 8630570065SHIV KUMAR SAROJ 8178016826 Junior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARRahul Vihar Siddharth Vihar  
452 🔗 387 63Road improvement work by interlocking tiles on the damaged road from Avtar to Ankur in Ward-02 Siddharth Vihar Street No. 07 AB. 12.44 10/09/2024 12.44 19 Sep 202426 Nov 2024 10 Oct 2024 Nirvan Infra SHIV KUMAR SAROJJunior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARRahul Vihar Siddharth Vihar  
453 🔗 388 62Construction work of damaged lane/road from Kuldeep's house to Himmat's house and Lakhbir wali lane and the lane parallel to Himmat and from Vicky Mohan's house to Lala Shop in Ward-02 Siddharth Vihar through interlocking tiles and drain. 14.95 10/09/2024 14.95 19 Sep 2024 10 Oct 2024 Nirvan Infra SHIV KUMAR SAROJJunior Engineer MEMBER KOTAIn Progress
0.00%
VIJAY NAGARRahul Vihar Siddharth Vihar  
454 🔗 389 otherConstruction work of damaged lane/road from Ritika Beauty Parlour house to Neetu's house and from Vinay's house to Neetu's house in Ward-02, Siddharth Vihar, Lane No. 02 with interlocking tiles and drain. 14.99 08/08/2024 14.99 07 Oct 2024  A.S. Const. SHIV KUMAR SAROJJunior Engineer MEMBER KOTA 
0%
VIJAY NAGARRahul Vihar Siddharth Vihar  
455 🔗 390 107Construction work of CC road and RCC drain from Kanchan Traders to Jaiveer Bhadana's house via Subhash Vakil on Ward-03, Thana Road. 19.21 10/09/2024 19.21 07 Oct 2024 10 Dec 2024 Zuber Const. SHIV KUMAR SAROJJunior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARPurana Vijay Nagar  
456 🔗 391 117Construction work of drain from Master Builder to Dharamveer's house in Ward 05 Gagan Vihar and construction work of interlocking tiles in the damaged street. 10.42 12/09/2024 10.42 19 Sep 2024 14 Oct 2024  Vinod Kumar 8650930015 Junior Engineer MEMBER KOTAIn Progress
80.00%
MOHAN NAGARGagan Vihar  
457 🔗 392 120Construction work of drain from Rakesh's house to Tillu's house in ward 05 Gagan Vihar and construction work of interlocking tiles in the damaged street. 22.36 12/09/2024 22.36 19 Sep 2024 14 Oct 2024 Asutosh Kumar Cont Vinod KumarJunior Engineer MEMBER KOTACompleted
100%
MOHAN NAGAR Gagan Vihar  
458 🔗 393 84Construction work of drain and interlocking tiles in Ward-06, D-Block and Handicapped Colony from D-269 to D-123 and in the street of D-193 and from Chandni to the house of Durgesh Devi. 14.92 10/09/2024 14.92 19 Sep 2024 10 Oct 2024  Preeti Bansal 8433403327 Junior Engineer MEMBER KOTACompleted
100%
CITY ZONEDeendayal Puri  
459 🔗 394 83Construction work of drain and interlocking tiles in Ward-06, D-Block from D-172 to D-181 and from D-223 to Ramraja and from Adesh Tyagi to Rakesh Tyagi. 13.87 10/09/2024 13.87 19 Sep 202410 Oct 2024 10 Oct 2024  SUNIL KUMAR MAURYA 8707646842 Junior Engineer MEMBER KOTACompleted
100%
CITY ZONEDeendayal Puri  
460 🔗 395 81Construction work of drain and interlocking tiles from Manoj to Ramphal and from Rishi to Prempal Singh and from Sanjay Kumar to Brijesh Singh and from Ashok wali gali and from Ramveer Tyagi to Zakir's house in Ward-06, Nandgram Deendayalpuri. 23.93 10/09/2024 23.93 19 Sep 2024 10 Oct 2024  SUNIL KUMAR MAURYA 8707646842 Junior Engineer MEMBER KOTACompleted
100%
CITY ZONEDeendayal Puri  
461 🔗 396 108Work of construction of drain and interlocking tiles in Dilip and subsidiary streets from Ankur Kashyap in Ward-07 Indraraj Colony. 12.52 10/09/2024 12.52 07 Oct 2024 10 Dec 2024 Zuber Const. SHIV KUMAR SAROJJunior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARBihariPura Sudamapuri  
462 🔗 397 160Construction work of CC road and drain from Jitendra to Parvati's house in Ambedkar Bhawan, Shanti to Ramu and Raj in Ward-08, Ramagarhi. 10.18 10/09/2024 10.18 26 Dec 202406 Feb 2025 06 Feb 2025  SUNIL KUMAR MAURYA 8707646842 Junior Engineer MEMBER KOTACompleted
100%
CITY ZONENehru Nagar 2  
463 🔗 398 78Construction work of C.C. road and drain in Shankar Manohar, Paneer Wali Gali and Haridatt Jatav Wali Gali in Ward-08, Pranagadhi. 11.41 10/09/2024 11.41 19 Sep 2024 10 Oct 2024  NAGENDRA SHARMA 8882460223 Junior Engineer MEMBER KOTACompleted
100%
CITY ZONENehru Nagar 2  
464 🔗 399 80Construction of C.C. road and drain from fire station to Jaipal ration and Khemchand's mill in ward-08, Maliwada 13.58 10/09/2024 13.58 19 Sep 202410 Oct 2024 10 Oct 2024  NAGENDRA SHARMA 8882460223 Junior Engineer MEMBER KOTACompleted
100%
CITY ZONENehru Nagar 2  
465 🔗 400 163Construction of C.C. road and drain in Ward-09, Shibbanpura from Omkar's house to Hariom's house via Virendra's house. 14.37 10/09/2024 14.37 09 Oct 202420 Jan 2025 20 Jan 2025 VINOD KUMAR CONTRACTOR 9278081661SUNIL KUMAR MAURYA 8707646842 Junior Engineer MEMBER KOTAIn Progress
80.00%
CITY ZONESibbanpura Patel marg  
466 🔗 401 153Work of construction of interlocking tiles and drain in Ward-09, Shibbhanpura, from the house of Jasvir Singh via the house of Amar Singh to the house of Rajesh Kashyap. 13.20 10/09/2024 13.20 07 Oct 202420 Jan 2025 20 Jan 2025 Pramood Kumar Singhal Preeti BansalJunior Engineer MEMBER KOTACompleted
100%
CITY ZONE Sibbanpura Patel marg  
467 🔗 402 82Work of construction of drain and interlocking tiles in the service line behind the house of H.No. 173 Shri Anand Tyagi, Rajkumar Jain and H.No. 143 Smt. Poonam Tyagi in Ward-09, New Aryanagar. 12.00 10/09/2024 12.00 19 Sep 202410 Oct 2024 10 Oct 2024 MODERN CONSTRUCTION CO SUNIL KUMAR MAURYA 8707646842 Junior Engineer MEMBER KOTACompleted
100%
CITY ZONESibbanpura Patel marg  
468 🔗 403 123Road improvement work by drain and C.C. in the damaged lane from C-93 to Vaishno Devi temple in ward 10. 26.07 12/09/2024 26.07 19 Sep 202415 Oct 2024 14 Oct 2024 Ujjwal Const. Vinod KumarJunior Engineer MEMBER KOTACompleted
100%
MOHAN NAGAR DLF Colony  
469 🔗 404 116Improvement work of damaged street from parking to B1/65 in ward 10 DLF by providing drain and interlocking tiles. 21.72 12/09/2024 21.72 19 Sep 202412 Nov 2024 14 Oct 2024 Tej Const Vinod KumarJunior Engineer MEMBER KOTACompleted
100%
MOHAN NAGAR DLF Colony  
470 🔗 405 156Ward-11, Nandgram, Krishna Kunj: Z.R.S. Makeover to Verma, Choudhary Sahab's lane through Kapil Tyagi and Hemant Verma lane, Mithlesh's house through Atul's house to Krishna Kunj main road and work of drain and interlocking tiles. 11.07 10/09/2024 11.07 26 Nov 202421 Jan 2025 21 Jan 2025 Zuber Const. Preeti BansalJunior Engineer MEMBER KOTACompleted
100%
CITY ZONE Nandgram, Deendayal puri  
471 🔗 406 146Work of drain and interlocking tiles from Madan Singh to Shiv Mandir park and from Pramod Pandit to Yadav ji's house in Ward-11, Nandagram E-Block. 22.54 10/09/2024 22.54 26 Nov 202407 Jan 2025 07 Jan 2025 S.D. Contr. Preeti BansalJunior Engineer MEMBER KOTACompleted
100%
CITY ZONE Nandgram, Deendayal puri  
472 🔗 407 137Construction work of RCC drain from the corner of Buddha Park in Ward-12, Balupura, passing through Hon'ble Councilor's Office and Raju Provision Store to Friends Chemist Ramteeram Road. 14.93 10/09/2024 14.93 26 Nov 202430 Dec 2024 30 Dec 2024 Zuber Const. NAGENDRA SHARMAJunior Engineer MEMBER KOTAIn Progress
0.00%
CITY ZONE Kalkagadi, Jatavbada  
473 🔗 408 139Construction work of drain and C.C. road from Shiva's shop to Deepak's house in Jatwada Kanjimal, from Mukesh's house to Udaychand's house, from Satish's house to Srinivas's house, from Jeet's house to Prashant's house via Raman's house, and adjacent to Sushil's house in Kallupura. 13.78 10/09/2024 13.78 26 Nov 202430 Dec 2024 30 Dec 2024 Zuber Const. NAGENDRA SHARMAJunior Engineer MEMBER KOTACompleted
100%
CITY ZONE Kalkagadi, Jatavbada  
474 🔗 409 109Ward-13, Ghukna: Construction work of drain and interlocking tiles from B.N. Thakur to Ajaypal's house via Mahendra Tyagi and Vijay Tyagi's lane and from Kamlesh to Ojha and from Naresh Chandra to Trivedi and from Harbirpal to Ilu Sharma's house and from Dinesh Sharma to Bhatta Road and Surend's lane. 15.78 10/09/2024 15.78 19 Sep 2024 14 Oct 2024 A H Const NAGENDRA SHARMAJunior Engineer MEMBER KOTACompleted
100%
CITY ZONE Ghukna  
475 🔗 410 107Construction work of drain and interlocking tiles in lane no. 8 in ward-13, Ghukna and Brahmapuri from Pankaj to Rajesh Tyagi's house and from Pappu's house to Omi's house, via Atar Singh's house to Mahendra Nai's house and Banwari Dhobi wali lane and from Jaiprakash to Roopchand and from Moolchand Tyagi to Harpal's house. 14.83 10/09/2024 14.83 19 Sep 202428 Nov 2024 14 Oct 2024 Shyama Const. Preeti BansalJunior Engineer MEMBER KOTACompleted
100%
CITY ZONE Ghukna  
476 🔗 411 149Construction work of drain and interlocking tiles in Khajur wali gali in ward-13, Ghukna, from Lokesh's house to Shashi Bhushan Tyagi's house and from Rakesh to Vinod and from Ramswaroop to Sunil Panchal and Jaiveer Nayak wali gali and from Umendra Convent School to Narendra's house. 17.73 10/09/2024 17.73 07 Oct 202415 Jan 2025 15 Jan 2025 A.V. Enter. Preeti BansalJunior Engineer MEMBER KOTACompleted
100%
CITY ZONE Ghukna  
477 🔗 412 61Repair work of damaged road from R-169 to R-109, R-126 to R-118, R-183 to R-200, R-156 to R-134, R-142 to R-135 to R-148 and R-143 in Railway Enclave R-Block in Ward-14 by Dense. 24.13 10/09/2024 24.13 19 Sep 2024 14 Oct 2024 SHANTANU CONSTRUCTION 9871119064SHIV KUMAR SAROJ 8178016826 Junior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARNew Vijay Nagar  
478 🔗 413 52Repair work of damaged road from R-38 to R-48, R-49 to R-55, R-71 to R-66, R-109 to R-96, R-109 to R-54 to R-50 in Railway Enclave R-Block in Ward-14 by Dense. 16.57 10/09/2024 16.57 19 Sep 202415 Oct 2024 14 Oct 2024 RG Buildtech Engg. Ltd. SHIV KUMAR SAROJJunior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARNew Vijay Nagar  
479 🔗 414 126In Ward-15, RCC drain construction work on both sides from Sector 12 Shiv Juice Center via Ambedkar Park to L Block. 25.29 10/09/2024 25.29 26 Nov 202413 Jan 2025 24 Dec 2024 Sidh Const SHIV KUMAR SAROJJunior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARCharan Singh Colony  
480 🔗 415 53Road repair work by Dense from Sector 12 Jai Auto Mobile to L Block L-26 in Ward-15. 29.96 10/09/2024 29.96 19 Sep 202415 Oct 2024 14 Oct 2024 RG Buildtech Engg. Ltd. SHIV KUMAR SAROJJunior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARCharan Singh Colony  
481 🔗 416 86Work of laying interlocking tiles and thermoplastic paint, cat eye on side track from Sector 12 Jai Auto Mobile to L Block L-26 in Ward-15. 14.97 10/09/2024 14.97 19 Sep 2024 14 Oct 2024 Chandra Mohan Singh Raguwanshi SHIV KUMAR SAROJJunior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARCharan Singh Colony  
482 🔗 417 86Work of drain and interlocking tiles from Rajpal's house to Chandrapal's house in Ward 16, Sikrod village. 26.63 10/09/2024 26.63 19 Sep 2024 10 Oct 2024 Om Enterprises 9891019900Rajender Singh 8178016904 Junior Engineer MEMBER KOTANot Started
0.00%
KAVI NAGARMorta  
483 🔗 418  Work of drain and interlocking tiles from Pawan Dagar's house to Manveer Fauji's house in Ward 16, Sikrod village. 26.72 08/08/2024 26.72 07 Oct 2024   Rajender Singh 8178016904 Junior Engineer MEMBER KOTANot Started
0.00%
KAVI NAGARMorta  
484 🔗 419 116In Ward-17, Sevanagar, from Kuldeep's house to T.K. Dubey via Sandeep, Rajkumar, Harish's houses and from Saroj's house to Madan's house and from Shakuntala to Verma's house and from N.B.T. School to Mittal Hardware, drain and C.C. work. 21.18 10/09/2024 21.18 19 Sep 202415 Oct 2024 14 Oct 2024 Pramood Kumar Singhal Preeti BansalJunior Engineer MEMBER KOTACompleted
100%
CITY ZONE Sewa Nagar, Hindan Vihar  
485 🔗 420 105Work of drain and C.C. from Naresh Photographer to Shivendra Kaushik's house via Madan Tyagi and Anil Sharma's house in Ward-17, Seva Nagar. 12.80 10/09/2024 12.80 19 Sep 2024 14 Oct 2024 Shree Balaji Ent. NAGENDRA SHARMAJunior Engineer MEMBER KOTAIn Progress
70.00%
CITY ZONE Sewa Nagar, Hindan Vihar  
486 🔗 421 89Work of drain and interlocking tiles from Virendra Chaudhary's house to Jairam's house in Ward 18, Rajapur. 18.40 10/09/2024 18.40 19 Sep 2024 10 Oct 2024 SARTHAK CONSTRUCTION 8630570065Rajender Singh 8178016904 Junior Engineer MEMBER KOTACompleted
100%
KAVI NAGARRajapur ShastriNagar  
487 🔗 422 105Work of drain and interlocking tiles in Ward 18, Bagwali Colony, from A-105 to A-223, street A-116, street A-195, from A-225 to Tejpal's house. 14.20 10/09/2024 14.20 19 Sep 202412 Dec 2024 14 Oct 2024 SARTHAK CONSTRUCTION 8630570065Rajender Singh 8178016904 Junior Engineer MEMBER KOTACompleted
100%
KAVI NAGARRajapur ShastriNagar  
488 🔗 423 152Construction work of interlocking tiles and drain in Ward-19, Patel Nagar Bounjha from the house of Rakesh Sharma via Pammi to Mokam Singh and from Kamal to Krishna and from Vijay Sharma to Ramchand Upadhyay. 16.48 10/09/2024 16.48 07 Oct 202420 Jan 2025 20 Jan 2025 Pramood Kumar Singhal Preeti BansalJunior Engineer MEMBER KOTACompleted
100%
CITY ZONE Patel Nagar, Mukandnagar  
489 🔗 424 1Work of construction of interlocking tiles and drain in Ward-19, Balmiki Basti from Sinha Property to H.No. K-56 to Maa Kirana Store, from Shekhar to H.No. K-20, from Mukesh to Sunil Parcha, from Vansh to Guptaji, from Radhelal to Pappu Choudhary and till Rajendra Maurya Wali Gali. 13.69 10/09/2024 13.69 28 Nov 202411 Apr 2025 11 Apr 2025  NAGENDRA SHARMA 8882460223 Junior Engineer MEMBER KOTACompleted
100%
CITY ZONEPatel Nagar, Mukandnagar  
490 🔗 425 122Construction work of drain and interlocking tiles in the damaged street from the house of Subis Chandela to the house of Prem Singh in ward 20 Bhaupura. 10.51 12/09/2024 10.51 19 Sep 202412 Dec 2024 14 Oct 2024 Ujjwal Const. Vinod KumarJunior Engineer MEMBER KOTACompleted
100%
MOHAN NAGAR Bhaupura  
491 🔗 426 133Construction work of drain and interlocking tiles in the damaged street from Manveer's house to Rajiv's house (street no. 05) in ward 20 Bhaupura. 13.73 12/09/2024 13.73 19 Sep 202414 Oct 2024 14 Oct 2024  Vinod Kumar 8650930015 Junior Engineer MEMBER KOTACompleted
100%
MOHAN NAGARBhaupura  
492 🔗 427 132Construction work of drain and interlocking tiles in the damaged street from Indrapal Netaji's house to Janaki's house in Ward 20 Rajiv Colony. 17.75 12/09/2024 17.75 19 Sep 2024 14 Oct 2024  Vinod Kumar 8650930015 Junior Engineer MEMBER KOTACompleted
100%
MOHAN NAGARBhaupura  
493 🔗 428 138Construction work of RCC drain and road through CC in KV block in ward 21 from KB-14 to KB-23 via KB-01. 13.80 10/09/2024 13.80 07 Oct 202424 Jan 2025 24 Jan 2025 Mahalaxmi Infra. Sanjay GangwarJunior Engineer MEMBER KOTACompleted
100%
VASUNDHRA Bhoowa Pura  
494 🔗 429 177Construction work of C.C. road and drain from the house of Gajendra Fauji near FCI godown in Ward-22, Rahul Vihar via the house of Vijaypal Choudhary to the house of Dhamendra Kumar Suryavanshi. 11.77 12/09/2024 11.77 07 Oct 202429 Mar 2025 29 Mar 2025  NAGENDRA SHARMA 8882460223 Junior Engineer MEMBER KOTACompleted
100%
CITY ZONEDaulat Pura  
495 🔗 430 2Construction work of C.C. road and drain from Naveen Garments to Mama Barf Wala's house in Telmill Wali Gali in Ward-22, Daulatpura. 12.41 26/11/2024 12.41 26 Nov 202426 Apr 2025 26 Apr 2025  NAGENDRA SHARMA 8882460223 Junior Engineer MEMBER KOTACompleted
100%
CITY ZONEDaulat Pura  
496 🔗 431 148Construction work of CC road and drain in Ward-22 Sangam Vihar from house no. 33 to Bhajanlal's house, from Rajpal to Pramod's house, from Vedprakash to Ashok Kumar's house and from house no. 52A to K.K. Shukla's house. 13.35 12/09/2024 13.35 26 Nov 202407 Jan 2025 07 Jan 2025 S.D. Contr. Preeti BansalJunior Engineer MEMBER KOTACompleted
100%
CITY ZONE Daulat Pura  
497 🔗 432 141Construction of CC road from Yogesh flour mill to Sadak culvert on Ward-23, Kailashnagar main road. 25.14 10/09/2024 25.14 26 Nov 2024 24 Dec 2024 UNIVERSAL VENTURES 9811071719SHIV KUMAR SAROJ 8178016826 Junior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARKailash Nagar  
498 🔗 433 otherWork of drain and interlocking tiles from Ambedkar Bhawan to Sanjay Singh's house and from Surendra's house to Ratan's house and from Surendra's house to Subhash's house in Ward 24, Mehrauli Village. 15.87 10/09/2024 15.87 07 Oct 2024 12 Dec 2024 prem construction 9818655177Rajender Singh 8178016904 Junior Engineer MEMBER KOTACompleted
100%
KAVI NAGARMahrouli  
499 🔗 434 otherWork of drain and interlocking tiles in Ward 24, Mehrauli Village, from Vinod Pandit's house to Mukesh's house, from Roopchand's house to Ajit's house, Magantram's street, from Nanak's house to Pyarelal's house, from Rampal's house to Ram Singh's house. 12.40 10/09/2024 12.40 07 Oct 2024 12 Dec 2024 prem construction 9818655177Rajender Singh 8178016904 Junior Engineer MEMBER KOTACompleted
100%
KAVI NAGARMahrouli  
500 🔗 435 119Work of interlocking tiles on the side track of the road in front of Goyal Gas Agency, Ward - 25. 14.84 10/09/2024 14.84 07 Oct 2024 17 Dec 2024 A S CONSTRUCTIONS (AAQFA8231R) 8630570065SHIV KUMAR SAROJ 8178016826 Junior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARAmbedkar Nagar  
501 🔗 436 119In ward no. 26, Madhopura, from government ration shop to Shani temple, from grocery store to Shri Ram temple, from Shri Ram temple to Gulab Singh, from Shri Ram temple to Ganesh Dutt, from Babulal to Shankar, from Deepak to ice cream factory, from well temple to Chamunda temple, damaged road is repaired by C.C. Road and drain repair work. 17.43 10/09/2024 17.43 19 Sep 2024 24 Dec 2024 A.H Const. SHIV KUMAR SAROJJunior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARMadhopur Sundri  
502 🔗 437 124In ward no. 26, Madhopura, from Inder Gurjar to Choudhary Popan Singh to Bhagman Lal, Dola to Rajkumar, Satish to Rajkumar, Neetu to Arun, damaged road is repaired by C.C. Road and drain repair work. 10.57 10/09/2024 10.57 19 Sep 202415 Jan 2025 24 Dec 2024 Jaiveer Singh Contr. SHIV KUMAR SAROJJunior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARMadhopur Sundri  
503 🔗 438 121In ward no. 26, Madhopura, from Krishna General Store to Jagdish, from Dharampal to Panchayat Bhawan, from Shani Mandir to Jagdish, Kavita Advocate Wali Gali, from Tejpal to Urmila Sadan, from Mukesh to Shani Mandir Railway Line, the damaged road is repaired by C.C. Road and drain repair work. 10.32 10/09/2024 10.32 19 Sep 202426 Dec 2024 24 Dec 2024 A.H Const. SHIV KUMAR SAROJJunior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARMadhopur Sundri  
504 🔗 439 116Road improvement work by interlocking tiles on the damaged road from Soni Mahal to Happy, Vinod to Pappu, Pappu to Rajbala, Jamuna to Ganga Ram, Rajkumar to Hoshiyaar Singh in Ward-27, Shanti Nagar. 14.14 10/09/2024 14.14 07 Oct 2024 10 Dec 2024 J.P. Shakti Const. SHIV KUMAR SAROJJunior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARDundaheda  
505 🔗 440 91Road improvement work by interlocking tiles on the damaged road from Dixit to Mukesh, Deepchand to Vinod, Neetu to Shailesh, Rohit (Tota) to Satveer, Dr. Major to Ram Kuvar in Ward-27, Shanti Nagar. 10.97 03/09/2024 10.97 07 Oct 202413 Dec 2024 10 Dec 2024 Cotack Builders SHIV KUMAR SAROJJunior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARDundaheda  
506 🔗 441 114Road improvement work by interlocking tiles on the damaged road from Keshav Chaudhary to Chanchal Tyagi, Robin Tyagi to Keshav Tyagi, Lilu Tyagi to Nishant, Shriram Cable to Rinku Pal in Ward-27, Sain Vihar. 11.27 10/09/2024 11.27 07 Oct 2024 10 Dec 2024 J.P. Shakti Const. SHIV KUMAR SAROJJunior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARDundaheda  
507 🔗 442 111Road improvement work by interlocking tiles on the damaged road from Satyapal to Omkar, Shokendra to Pramod Sharma, Pintu to Sheshnath, Babita to Harendra Chaudhary in Ward-27, Shanti Nagar slum. 13.17 10/09/2024 13.17 07 Oct 2024 10 Dec 2024 J.P. Shakti Const. SHIV KUMAR SAROJJunior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARDundaheda  
508 🔗 443 129Construction work of damaged drain from water plant to Qasim's house in Nilmani Colony, Ward No. 28, Rajiv Colony and construction work of interlocking tiles in the damaged street. 16.66 12/09/2024 16.66 19 Sep 202414 Oct 2024 14 Oct 2024 A.S. Const. Vinod KumarJunior Engineer MEMBER KOTACompleted
100%
MOHAN NAGAR Rajeev Colony  
509 🔗 444 123Construction work of drain from Meena Bhais Wale to Mahadev's house in Nilmani Colony of Ward 28 Rajiv Colony and laying of interlocking tiles in the damaged street. 11.61 10/09/2024 11.61 19 Sep 202414 Oct 2024 14 Oct 2024 A.S. Const. Vinod KumarJunior Engineer MEMBER KOTACompleted
100%
MOHAN NAGAR Rajeev Colony  
510 🔗 445 118Construction work of drain and interlocking tiles in the damaged street from Ashok Mistry's house to Ramesh and Kamlesh's house to Nagendra Chauhan's house in Neelmani Colony, Ward 28, Rajiv Colony. 15.73 12/09/2024 15.73 19 Sep 2024 14 Oct 2024  Vinod Kumar 8650930015 Junior Engineer MEMBER KOTACompleted
100%
MOHAN NAGARRajeev Colony  
511 🔗 446 119Construction work of drain and damaged street through C.C. from Seva Ram's house to Kisan Pal's house in ward no. 29, Bhaupura Kuti. 18.96 10/09/2024 18.96 19 Sep 202409 Dec 2024 14 Oct 2024 Anuj kumar Contr. Vinod KumarJunior Engineer MEMBER KOTACompleted
100%
MOHAN NAGAR Kuti  
512 🔗 447 121Construction work of drain and damaged street through C.C. from Dr. Bengali's house to Ramesh Chand's house in Ward No. 29, Bhaupura Kuti. 14.68 10/09/2024 14.68 19 Sep 202412 Nov 2024 14 Oct 2024 Ujjwal Const. Vinod KumarJunior Engineer MEMBER KOTACompleted
100%
MOHAN NAGAR Kuti  
513 🔗 448 124Construction work of drain and damaged street through C.C. from Kisan Pal's house to Dr. Bengali's house in Ward No. 29, Bhaupura Kuti. 16.36 10/09/2024 16.36 19 Sep 202415 Oct 2024 14 Oct 2024 Ujjwal Const. Vinod KumarJunior Engineer MEMBER KOTACompleted
100%
MOHAN NAGAR Kuti  
514 🔗 449 162Work of drain and interlocking tiles from Meenu's house in Ward 30, Sadarpur village, via Vimala Tiwari Academy School to Shiv Temple. 14.89 10/09/2024 14.89 07 Oct 202428 Jan 2025 28 Jan 2025 A.K.G Construction 9654220230Rajender Singh 8178016904 Junior Engineer MEMBER KOTACompleted
100%
KAVI NAGARSadarpur, Govind puram  
515 🔗 450 161Work of drain and interlocking tiles in Titu wali gali, Dalchand wali gali, from Daulatram's house to Gangaram's house in ward 30, Sadarpur village. 11.32 10/09/2024 11.32 07 Oct 2024 28 Jan 2025 J S S CONSTRUCTION 9999280744Rajender Singh 8178016904 Junior Engineer MEMBER KOTACompleted
100%
KAVI NAGARSadarpur, Govind puram  
516 🔗 451 108Construction work of drain and interlocking tiles in Ward-31, Sihani from Lakhram to Pappu and from Subhash Tyagi to Nandu Tyagi Mode and from Gaurav Tyagi to Naveen Tyagi's house. 17.79 10/09/2024 17.79 19 Sep 2024 14 Oct 2024 Anuj kumar Contr. NAGENDRA SHARMAJunior Engineer MEMBER KOTACompleted
100%
CITY ZONE Nandgram Sihani  
517 🔗 452 100Construction work of drain and interlocking tiles in Ward-31, Subhash Nagar, from Mahendra to Sauran and from Maya to Kunwarpal and from Bishan Pandit via Vinod Kumar Shah to Munesh Panditji and Akash wali gali and Pankaj to Sanjay wali gali and Pradeep Kumar Tyagi wali gali and Bunty Cyber ​​Cafe wali gali and from Babitpal to Munesh wali gali. 22.77 21/07/2024 22.77 19 Sep 2024 14 Oct 2024  SUNIL KUMAR MAURYA 8707646842 Junior Engineer MEMBER KOTANot Started
0.00%
CITY ZONENandgram Sihani  
518 🔗 453 104Construction work of drain and interlocking tiles from Ramkumar Yadav to Sheerpal, Naresh to Sitaram Pandit, Mahavir to Manoj, Pramod to Sundar, Indrapal to Rajpal and Jaisingh to Chotu's house in Ward-32, Harvanshnagar and Bhatta Road. 29.77 10/09/2024 29.77 19 Sep 202407 Mar 2025 14 Oct 2024 Chowdhary Associates Preeti BansalJunior Engineer MEMBER KOTACompleted
100%
CITY ZONE Krishna Nagar  
519 🔗 454 106Construction work of drain and interlocking tiles in Ward-32, Harvanshnagar from Rajpal to Shridevi and Bhagwandas wali gali and Harikrishna wali gali and from Sundar to Suresh and from Navneet to Gauri Shankar temple. 14.10 10/09/2024 14.10 19 Sep 202428 Nov 2024 14 Oct 2024 Shyama Const. Preeti BansalJunior Engineer MEMBER KOTACompleted
100%
CITY ZONE Krishna Nagar  
520 🔗 455 161Construction work of CC road and drain from in front of SK Tour & Travel to GT Road in Ward-33, Jagniganj. 13.45 12/09/2024 13.45 07 Oct 202410 Feb 2025 10 Feb 2025 Vinod kumar Contr. NAGENDRA SHARMAJunior Engineer MEMBER KOTAIn Progress
75.00%
CITY ZONE Saray Najar Ali  
521 🔗 456 161Construction work of CC road and drain from Rajkumar to GT Road via Anil in Ward-33, Jagniganj. 13.51 12/09/2024 13.51 07 Oct 202410 Feb 2025 10 Feb 2025 Vinod kumar Contr. NAGENDRA SHARMAJunior Engineer MEMBER KOTAIn Progress
90.00%
CITY ZONE Saray Najar Ali  
522 🔗 457 180Repair work of drain and C.C. in damaged lane from GT Road to G 696 in Ward 34 Shahid Nagar Pratham. 15.05 10/09/2024 15.05 07 Oct 202409 Dec 2024 09 Dec 2024 Bijender Singh Sanjay GangwarJunior Engineer MEMBER KOTACompleted
100%
MOHAN NAGAR Shaheed Nagar First  
523 🔗 458 179Repair work of drain and C.C. in the damaged lane from Sahnawaj's house to Dr. Sarfaraz's house in Ward 34 Shaheednagar Pratham. 10.31 10/09/2024 10.31 07 Oct 202425 Nov 2024 25 Nov 2024 Bijender Singh Sanjay GangwarJunior Engineer MEMBER KOTACompleted
100%
MOHAN NAGAR Shaheed Nagar First  
524 🔗 459 178Repair work of drain and C.C. in the damaged lane from Khalil's house to Vittu Shuttering's house in Ward 34 Shahid Nagar Pratham. 13.72 10/09/2024 13.72 07 Oct 202425 Nov 2024 25 Nov 2024 Bijender Singh Sanjay GangwarJunior Engineer MEMBER KOTACompleted
100%
MOHAN NAGAR Shaheed Nagar First  
525 🔗 460 181Construction work of drain and C.C. road in the street from Kamil's house to the bakery in ward 34 Shahidnagar Pratham. 12.32 10/02/2024 12.32 07 Oct 202409 Dec 2024 09 Dec 2024 Bijender Singh Sanjay GangwarJunior Engineer MEMBER KOTACompleted
100%
MOHAN NAGAR Shaheed Nagar First  
526 🔗 461 101Construction work of damaged lane/road through CC and drain from Bijendra Yadav's house to Savita Raghav's house in Ward-35 Buddhist Vihar Akbarpur Bahrampur. 12.56 10/09/2024 12.56 07 Oct 202411 Feb 2025 10 Dec 2024 Marden Const.Co. SHIV KUMAR SAROJJunior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARAkhbarpur Behrampur  
527 🔗 462 100Construction work of damaged lane/road through C.C. and drain in Ward-35 Buddhist Vihar Akbarpur Bahrampur from Bijendra Yadav's house to Ajay Yadav's house, from Vinod Prajapati's house (temple) to Kapil Pandit's house, from Babli Chaudhary's house (Tridev temple) to Amit Master's house. 14.96 10/09/2024 14.96 07 Oct 2024 10 Dec 2024 Marden Const.Co. SHIV KUMAR SAROJJunior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARAkhbarpur Behrampur  
528 🔗 463 142Construction work of damaged lane/road through CC and drain from the house of Suraj Balmiki to the house of Kanhaiya Halwai in Ward-35 Buddhist Vihar Akbarpur Bahrampur. 14.96 10/09/2024 14.96 26 Nov 2024 24 Dec 2024 R C CONTRACTOR 9205733094SHIV KUMAR SAROJ 8178016826 Junior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARAkhbarpur Behrampur  
529 🔗 464 115Construction work of RCC drain from Sector 16 Market to Mother Dairy in Ward 36 Sector 16 Vasundhara. 14.93 10/09/2024 14.93 07 Oct 202416 Dec 2024 16 Dec 2024 S.G. Enter. Sanjay GangwarJunior Engineer MEMBER KOTACompleted
100%
VASUNDHRA Prahalad Gari  
530 🔗 465 127Construction work of drain, interlocking tiles and C.C. from Babli Chauhan's house to Salim Bhai's property in Ward 37, Shalimar Garden. 13.10 12/09/2024 13.10 19 Sep 2024 14 Oct 2024  Vinod Kumar 8650930015 Junior Engineer MEMBER KOTACompleted
100%
MOHAN NAGARShalimar Garden Main  
531 🔗 466 130Construction work of drain and interlocking tiles from Babli B 150 to B 181 in Ward 37, Shalimar Garden. 13.28 12/09/2024 13.28 19 Sep 202414 Oct 2024 14 Oct 2024  Vinod Kumar 8650930015 Junior Engineer MEMBER KOTACompleted
100%
MOHAN NAGARShalimar Garden Main  
532 🔗 467 126Work of drain and interlocking tiles in the damaged street from Rohila's house to Pappu's house and from Narendra's house to Panchal's house in Ramnagar, Ward 38, Arthala. 11.30 10/09/2024 11.30 19 Sep 2024 14 Oct 2024 A.S. Const. Vinod KumarJunior Engineer MEMBER KOTACompleted
100%
MOHAN NAGAR Atharla  
533 🔗 468 125Work of drain and interlocking tiles in the damaged street in Ramnagar, Ward 38, Arthala, from Rajendra Bharti's house to Vinod Kashyap's house and from Rajendra to Dr. Sharif and from Chauhan's house to Devendra's house. 11.76 10/09/2024 11.76 19 Sep 2024 14 Oct 2024  Sanjay Gangwar 8178016821 Junior Engineer MEMBER KOTACompleted
100%
MOHAN NAGARAtharla  
534 🔗 469 143Work of drain and interlocking tiles in the damaged street from Bharpai's house to Bhagmal's house and from Bhagmal to Vijay, Ramu and Dinesh's street in Ramnagar, Ward 38, Arthala. 12.10 10/09/2024 12.10 19 Sep 2024 14 Oct 2024  Sanjay Gangwar 8178016821 Junior Engineer MEMBER KOTACompleted
100%
MOHAN NAGARAtharla  
535 🔗 470 131Work of drain and interlocking tiles in the damaged street from Shambhu Dayal's house to Yadav's house in Ramnagar of ward 38, Arthala and in Mohit's, Kanti Devi's, Kamal Sharma's and Sanjay's streets. 11.29 10/09/2024 11.29 19 Sep 2024 14 Oct 2024  Sanjay Gangwar 8178016821 Junior Engineer MEMBER KOTACompleted
100%
MOHAN NAGARAtharla  
536 🔗 471 166Road improvement work by Dense on the road in front of house no. H/45, 48, 187 and house no. H/190 from Amba Store in Ward-39, Nehrunagar Third H Block. 12.81 12/09/2024 12.81 07 Oct 2024 20 Feb 2025 Prateek Enter. NAGENDRA SHARMAJunior Engineer MEMBER KOTACompleted
100%
CITY ZONE Narsirpur  
537 🔗 472 149Construction work of RCC drain and interlocking tiles from Shyam Singh's house to Rudra Kumar's house (Dhara Wali Gali) in Ward-40 Sahibabad village. 13.94 10/09/2024 13.94 21 Oct 202424 Feb 2025 24 Feb 2025  Sanjay Gangwar 8178016821 Junior Engineer MEMBER KOTACompleted
100%
VASUNDHRASahibabad  
538 🔗 473 154Construction work of RCC drain and interlocking tiles from Dhara Bhawan to V.N. Yadav's house (Dhara Wali Gali) in Ward-40 Sahibabad village. 11.44 10/09/2024 11.44 21 Oct 202405 Mar 2025 05 Mar 2025  Sanjay Gangwar 8178016821 Junior Engineer MEMBER KOTACompleted
100%
VASUNDHRASahibabad  
539 🔗 474 61Construction work of RCC drain and interlocking tiles from Vishal Hardware to Amar Dental Care in lane no. 2 in ward-41 Jhandapur. 11.86 10/09/2024 11.86 19 Sep 202416 Dec 2024 14 Oct 2024  Sanjay Gangwar 8178016821 Junior Engineer MEMBER KOTACompleted
100%
VASUNDHRAMaharajpur  
540 🔗 475 62Construction work of RCC drain and interlocking tiles in lane no. 2 in ward-41 Jhandapur from Bansal General Store to Ambedkar Park and from Hanuman Mandir to Gyani Chak. 13.26 10/09/2024 13.26 19 Sep 202429 Jan 2025 14 Oct 2024  Sanjay Gangwar 8178016821 Junior Engineer MEMBER KOTACompleted
100%
VASUNDHRAMaharajpur  
541 🔗 476  Construction work of C.C. road from public toilet to Akash Tyagi Mobile Care in Ward-41 Maharajpur. 12.75 21/07/2024 12.75 19 Sep 2024   Sanjay Gangwar 8178016821 Junior Engineer MEMBER KOTACompleted
100%
VASUNDHRAMaharajpur  
542 🔗 477 69Construction work of C.C. road from S.S. Network to Pal Stationery & Sports and up to house no. 62 in Ward-41 Maharajpur. 11.01 10/09/2024 11.01 19 Sep 2024 14 Oct 2024  Sanjay Gangwar 8178016821 Junior Engineer MEMBER KOTACompleted
100%
VASUNDHRAMaharajpur  
543 🔗 478 109Work of drain and interlocking tiles from Ramu Chowk to Mahesh Yadav's house in Ward 42, Bamheta village. 14.05 10/09/2024 14.05 19 Sep 202402 Dec 2024 14 Oct 2024 KESHRAM CONSTRUCTIONS 9910458482Rajender Singh 8178016904 Junior Engineer MEMBER KOTACompleted
100%
KAVI NAGARShahpur Bamheta  
544 🔗 479 112Work of drain and interlocking tiles from the house of Brahmadutt Yadav to the house of Anil Journalist in Ward 42, Bamheta village. 16.21 10/09/2024 16.21 19 Sep 202428 Nov 2024 14 Oct 2024 KESHRAM CONSTRUCTIONS 9910458482Rajender Singh 8178016904 Junior Engineer MEMBER KOTACompleted
100%
KAVI NAGARShahpur Bamheta  
545 🔗 480 113Work of drain and interlocking tiles from Baniya Ke Bagh/Rajesh's shop to Devendra's house in Ward 42, Bamheta village. 24.92 10/09/2024 24.92 19 Sep 202402 Dec 2024 14 Oct 2024 KESHRAM CONSTRUCTIONS 9910458482Rajender Singh 8178016904 Junior Engineer MEMBER KOTACompleted
100%
KAVI NAGARShahpur Bamheta  
546 🔗 481 153Construction work of RCC drain and CC road from Gaurav General Store to house no. 1282 and from house no. 1282 to Dharamveer's house, from Dharamveer to Umarpal, from Umarpal to Kilni's house and from R.K. Memorial School to house no. 1108 in Ward-43, Kadkad village. 10.71 10/09/2024 10.71 07 Oct 202428 Apr 2025 05 Mar 2025  Sanjay Gangwar 8178016821 Junior Engineer MEMBER KOTACompleted
100%
VASUNDHRAKadkad Modal  
547 🔗 482 140Construction work of RCC drain and CC road from Bhisam to Prempal and from Prempal to house no. 1067 and from 1067 to Balwant's house and from house no. 1051 to 1046 in ward-43, Kadkad village. 14.89 10/09/2024 14.89 07 Oct 202429 Jan 2025 29 Jan 2025  Sanjay Gangwar 8178016821 Junior Engineer MEMBER KOTACompleted
100%
VASUNDHRAKadkad Modal  
548 🔗 483 155Construction work of RCC drain and CC road from house no. 732 to 748 from Umrao Singh's house to house no. 772 in ward-43, Kadkad village. 14.16 10/09/2024 14.16 07 Oct 202405 Mar 2024 05 Mar 2025  Sanjay Gangwar 8178016821 Junior Engineer MEMBER KOTACompleted
100%
VASUNDHRAKadkad Modal  
549 🔗 484  Work of drain and interlocking tiles in the damaged street from Vijay Dhobi's house to Shailendra's house in Chitrakoot Colony, Sanjay Colony, Ward 44. 14.66 10/08/2024 14.66 09 Oct 2024   Sanjay Gangwar 8178016821 Junior Engineer MEMBER KOTACompleted
100%
MOHAN NAGARSanjay Colony  
550 🔗 485 135Work of drain and interlocking tiles in the damaged street from Dhaniram's house to Monu's house in Chitrakoot Colony, Ward 44, Sanjay Colony. 11.08 10/09/2024 11.08 19 Sep 2024 14 Oct 2024  Sanjay Gangwar 8178016821 Junior Engineer MEMBER KOTACompleted
100%
MOHAN NAGARSanjay Colony  
551 🔗 486 200Repair work of drain and C.C. in the damaged lane from Sonu's house to Habib and to the house of Hind Public School in ward 44 Sanjay Colony. 10.25 10/09/2024 10.25 21 Oct 202415 Mar 2025 15 Mar 2025 JSS Const. Sanjay GangwarJunior Engineer MEMBER KOTACompleted
100%
MOHAN NAGAR Sanjay Colony  
552 🔗 487 201Repair work of drain and C.C. in the damaged lane from Raja's house to S.P. Bhati and from Krishna Kumar Gupta's house to Anwari's house in Ward 44 Sanjay Colony. 11.15 10/09/2024 11.15 21 Oct 2024 24 Mar 2025  Sanjay Gangwar 8178016821 Junior Engineer MEMBER KOTACompleted
100%
MOHAN NAGARSanjay Colony  
553 🔗 488 134Construction work of interlocking tiles in the drain and damaged street from Rajwala Sharma's house to Kamala's house in Krishna Gaushala in Ward 45, Karhaida. 12.26 12/09/2024 12.26 19 Sep 2024 14 Oct 2024  Vinod Kumar 8650930015 Junior Engineer MEMBER KOTACompleted
100%
MOHAN NAGARKarheda  
554 🔗 489 142Construction work of interlocking tiles in the drain and damaged street from Kamala's house to Sone Lal's house in Krishna Gaushala in Ward 45, Karhaida. 10.20 12/09/2024 10.20 19 Sep 2024 14 Oct 2024  Vinod Kumar 8650930015 Junior Engineer MEMBER KOTAIn Progress
0.00%
MOHAN NAGARKarheda  
555 🔗 490 165Construction work by interlocking tiles in the drain and damaged street from Brijpal Singh's house to Vinod's house in Ward 45, Karhaida. 19.25 12/09/2024 19.25 19 Sep 202415 Oct 2024 15 Oct 2024  Vinod Kumar 8650930015 Junior Engineer MEMBER KOTACompleted
100%
MOHAN NAGARKarheda  
556 🔗 491 103Work of drain and interlocking tiles in Ward 46, Garden Enclave from Rituraj's house to Mukesh's house, from Sonu Chaudhary's house to Omvati's house, from Manmohan flour mill to Ashok's house, from Mukesh's house to Santosh's house, from Santosh's house to Subhash's house. 29.05 10/09/2024 29.05 19 Sep 2024 14 Oct 2024 MODERN CONSTRUCTION CO Rajender Singh 8178016904 Junior Engineer MEMBER KOTACompleted
100%
KAVI NAGARGuldhar Duhai  
557 🔗 492 110Road improvement work by DANS from SC-317 to SC-334 and SC-24 to SC-12 in Ward 47, Shastri Nagar C-Block. 10.89 10/09/2024 10.89 19 Sep 2024 14 Oct 2024 PRATEEK ENTERPRISES 9311881082Rajender Singh 8178016904 Junior Engineer MEMBER KOTACompleted
100%
KAVI NAGARShastrinagar Mahendra Encalave  
558 🔗 493 108Road improvement work by Danes in Ward 47, Shastri Nagar F-Block from SF-20 to SF-120, SF-120 to 116, in front of market, from SF-76 to SF-143, SF-153 to SF-166, SE-99A, 99B, 99C. 21.61 10/09/2024 21.61 19 Sep 202415 Oct 2024 14 Oct 2024 R G BUILDTECH ENGINEERS LTD 9810616350Rajender Singh 8178016904 Junior Engineer MEMBER KOTACompleted
100%
KAVI NAGARShastrinagar Mahendra Encalave  
559 🔗 494 87Road repair work through C.C. on the damaged road from Ali Mohammad to Dasna Wale Doctor in Ward-48, Sector-12, Mirzapur. 12.36 10/09/2024 12.36 19 Sep 202427 Dec 2024 14 Oct 2024 Mahima Const. Rajender SinghJunior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARMirjapur  
560 🔗 495 99Construction work of interlocking tiles and drain from Gurudwara to C/90 near Electricity House in C Block, Nandgram, from Neeraj Medical to C/72 and from F/380 to F/372 in F Block. 12.15 10/09/2024 12.15 19 Sep 2024 14 Oct 2024 Asutosh Kumar Cont Preeti BansalJunior Engineer MEMBER KOTAIn Progress
90.00%
CITY ZONE Nandgram Mariyam Nagar  
561 🔗 496 92Construction work of interlocking tiles and drain from Rishi Kirana Store C/812 near Shiva Temple in Ward-49 Nandgram C Block. 21.75 10/09/2024 21.75 19 Sep 202428 Nov 2024 14 Oct 2024 Rishu Const Preeti BansalJunior Engineer MEMBER KOTACompleted
100%
CITY ZONE Nandgram Mariyam Nagar  
562 🔗 497 128Work of drain and C.C. road from Rakesh Tyagi to Ravindra Tyagi and from Subodh Tyagi to Vinod and Neeraj Tyagi and from Amarnath Tyagi to Sushil Tyagi and Surendra Tyagi to Neeraj Tyagi in Ward-50, Sadik Nagar. 10.38 10/09/2024 10.38 19 Sep 202418 Mar 2025 14 Oct 2024 Balaji Const.Co. Preeti BansalJunior Engineer MEMBER KOTACompleted
100%
CITY ZONE Saddiknagar, Noornagar  
563 🔗 498 91In Ward-50, Sadik Nagar, from Satish Chandra's house to Sachin's house and from Deepchand's house to Mahesh Sharma's house via R.K. Sharma, drain and C.C. road work. 10.09 10/09/2024 10.09 19 Sep 2024 14 Oct 2024  Preeti Bansal 8433403327 Junior Engineer MEMBER KOTACompleted
100%
CITY ZONESaddiknagar, Noornagar  
564 🔗 499 86Construction work of drain and C.C. road from Tejveer Tyagi's house to Keshav Tyagi via Anil Tyagi's house in Ward-50, Saddik Nagar and from Bijendra Kumar Tyagi to Tikaram Prajapati. 16.88 10/09/2024 16.88 19 Sep 2024 14 Oct 2024 Juber Const Preeti BansalJunior Engineer MEMBER KOTACompleted
100%
CITY ZONE Saddiknagar, Noornagar  
565 🔗 500 84Road improvement work by Danes in the internal lanes of Gate No. 09 in Ward-51, G Block. 29.90 10/09/2024 29.90 19 Sep 2024 14 Oct 2024 PRATEEK ENTERPRISES 9311881082SHIV KUMAR SAROJ 8178016826 Junior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARPratap Vihar Sec-11  
566 🔗 501 85Road improvement work by Danes in the internal lanes of Gate No. 10 in Ward-51, G Block. 29.99 10/09/2024 29.99 19 Sep 2024 14 Oct 2024 SHANTANU CONSTRUCTION 9871119064SHIV KUMAR SAROJ 8178016826 Junior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARPratap Vihar Sec-11  
567 🔗 502 168Work of construction of CC road and drain repair from house no. B/237 to B/347 in Ward-52, Panchvati B Block. 12.02 12/09/2024 12.02 19 Sep 202425 Feb 2025 25 Feb 2025 Shree Radhya Const. NAGENDRA SHARMAJunior Engineer MEMBER KOTACompleted
100%
CITY ZONE Aryanagar Kotgaon  
568 🔗 503 102Work of drain and interlocking tiles from Bake Lal's house to Ravi Pal's house in Ward 53, Raispur. 10.34 10/09/2024 10.34 19 Sep 202413 Dec 2024 14 Oct 2024 Vinod kumar Contr. Rajender SinghJunior Engineer MEMBER KOTACompleted
100%
KAVI NAGAR Raishpur  
569 🔗 504 121Construction work of CC road from house no. 801 to house no. 773/3 and from house no. 773/3 to the corner of our park in Sadbhavna Society, ward-54. 13.39 10/09/2024 13.39 07 Oct 202416 Dec 2024 16 Dec 2024  Sanjay Gangwar 8178016821 Junior Engineer MEMBER KOTACompleted
100%
VASUNDHRAVashundhra-1  
570 🔗 505 124Construction work of C.C. road from house no. 820 to Shahbeen clinic in Sadbhavna society in ward-54 and on society park road. 13.02 10/09/2024 13.02 07 Oct 202416 Dec 2024 16 Feb 2024  Sanjay Gangwar 8178016821 Junior Engineer MEMBER KOTACompleted
100%
VASUNDHRAVashundhra-1  
571 🔗 506 67Repair work of damaged road from house 0-5/798 to Children's Park in Ward-54 Vasundhara Sector-05 by Dense. 14.97 10/09/2024 14.97 19 Sep 202422 Nov 2024 14 Oct 2024  Sanjay Gangwar 8178016821 Junior Engineer MEMBER KOTACompleted
100%
VASUNDHRAVashundhra-1  
572 🔗 507 88Construction work of interlinking tiles road in house no. 393 to 435, 467 to corner of park and from 392 (Prince Property) to 535 (Krishna Park) in ward-55, D block. 19.74 10/09/2024 19.74 19 Sep 2024 14 Oct 2024 SG ENTERPRISES SHIV KUMAR SAROJ 8178016826 Junior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARVijay Nagar sec11 block-A  
573 🔗 508 100Road improvement work by DANS in Ward 56, Chiranjiv Vihar Sector-05 from 05/29 to 05/49. 10.47 10/09/2024 10.47 19 Sep 2024 14 Oct 2024  Rajender Singh 8178016904 Junior Engineer MEMBER KOTACompleted
100%
KAVI NAGARChiranjeev Vihar  
574 🔗 509 114Road improvement work by Dans from AE-59 to AE-64, AE-65 to AE-74, AE-49 to AE-31 in Ward 56, Avantika I. 14.93 10/09/2024 14.93 19 Sep 202430 Dec 2024 14 Oct 2024  Rajender Singh 8178016904 Junior Engineer MEMBER KOTACompleted
100%
KAVI NAGARChiranjeev Vihar  
575 🔗 510 116Road improvement work by DANS from CC-05 to CC-01/16 and CC-01/06 to CC-01/11 and CB-27 to CC-01/20 in Ward 56, Avantika Pratham. 19.33 10/09/2024 19.33 19 Sep 2024 15 Oct 2024  Rajender Singh 8178016904 Junior Engineer MEMBER KOTACompleted
100%
KAVI NAGARChiranjeev Vihar  
576 🔗 511 83Improvement work through drain and interlocking tiles from Subodh Tyagi to Likheram Tyagi and from Narendra Tyagi to water tank and from Subhash Tyagi to Rajkishore and from Rajkishore to Brajkishore in ward-57 Makanpur. 13.68 10/09/2024 13.68 19 Sep 202406 Nov 2024 15 Oct 2024  Sanjay Gangwar 8178016821 Junior Engineer MEMBER KOTACompleted
100%
VASUNDHRAMakan pur  
577 🔗 512 64In ward-57 Makanpur, from Devendra Tyagi to Surendra Tyagi, from Vinod Tyagi to Mangu Tyagi and from Devendra Tyagi to Rame and till Bijendra Tyagi, road improvement work through drain and C.C. 14.47 10/09/2024 14.47 19 Sep 202406 Nov 2024 14 Oct 2024 Shri Balaji Enterprises 9773906224Sanjay Gangwar 8178016821 Junior Engineer MEMBER KOTACompleted
100%
VASUNDHRAMakan pur  
578 🔗 513 100Road improvement work through drain and CC from Devendra Gupta to Satyapal Tyagi and from Devendra to Jaiveer in ward-57 Makanpur. 13.04 10/09/2024 13.04 19 Sep 202411 Nov 2024 15 Oct 2024 Shri Balaji Enterprises 9773906224Sanjay Gangwar 8178016821 Junior Engineer MEMBER KOTACompleted
100%
VASUNDHRAMakan pur  
579 🔗 514 136In ward 58 Mawai, the damaged road from Devdutt Sharma to Kuldeep Sharma, Amarnath to Sunita Panchal, Babulal to Raj Bahadur and Shri Chhote Lal to Mangeram Tyagi was repaired using C.C. 11.91 10/09/2024 11.91 26 Nov 2024 24 Dec 2024 Pardhan Const. SHIV KUMAR SAROJJunior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARShivpuri  
580 🔗 515 127Road repair work through C.C. on damaged road from H.No. A-22 to A-543, A-543 to Sarvesh, A-587 to A-591, A-557 to A-583 in Ward-58, Mawai. 11.79 10/09/2024 11.79 26 Nov 202403 Jan 2025 24 Dec 2024 Nirban Infra SHIV KUMAR SAROJJunior Engineer MEMBER KOTACompleted
100%
VIJAY NAGARShivpuri  
581 🔗 516 87Ward - 59, Old City Chandrapuri, near Shalimar Paints, Rajkumar and Rajbir, near Choudhary Chai Wala, Navyug Market, near State Bank and near stationery shop, work of drain repair and interlocking tiles on side track at various places. 14.56 12/09/2024 14.56 19 Sep 2024 14 Oct 2024 Madan Const Preeti BansalJunior Engineer MEMBER KOTACompleted
100%
CITY ZONE Chandrapuri  
582 🔗 517 95Ward-59, Purana Shahar Gate Wali Gali, from Sumit's house to Anant Sharma's house via Lavkush's house and in Pandit ji's lane, C.C. road and drain construction work. 10.80 12/09/2024 10.80 19 Sep 2024 14 Oct 2024  Preeti Bansal 8433403327 Junior Engineer MEMBER KOTACompleted
100%
CITY ZONEChandrapuri  
583 🔗 518 126Ward-59, Old City, Old Munsfi Bazaar, from Balaji Packing to Jaimata Trading, Amarpali Saree Center, Hindon Tailors via Guruji Enterprises and near the mosque, work of drain and CC road and interlocking tiles. 12.65 12/09/2024 12.65 19 Sep 2024 14 Oct 2024 Navdha Const Preeti BansalJunior Engineer MEMBER KOTACompleted
100%
CITY ZONE Chandrapuri  
584 🔗 519 90Ward-59, Old City, near the clock tower in the old Munsfi market, from Bhavani Kambal to Rajendra Box Wala and in the lanes of Balaji, Pinky and Jai Bhagwan and Jai Banke Bihari, construction work of drain and C.C. road. 12.88 12/09/2024 12.88 19 Sep 2024 14 Oct 2024 Madan Const Preeti BansalJunior Engineer MEMBER KOTAIn Progress
10.00%
CITY ZONE Chandrapuri  
585 🔗 520 123Repair work of damaged road from A 158 to 170 and 132 to 144 in ward 61 sector 10 by Dense. 14.68 10/09/2024 14.68 07 Oct 202416 Dec 2024 16 Dec 2024 R G BUILDTECH ENGINEERS LTD 9810616350Sanjay Gangwar 8178016821 Junior Engineer MEMBER KOTACompleted
100%
VASUNDHRAVasundhra-2  
Fund Name: NIGAM NIDHI 2024-25
586 🔗 521 116Repair work of damaged road from A 44 to 220 in Ward 61 Sec 10 by Dense. 14.96 10/09/2024 14.96 07 Oct 202416 Dec 2024 16 Dec 2024 R G BUILDTECH ENGINEERS LTD 9810616350Sanjay Gangwar 8178016821 Junior Engineer MEMBER KOTACompleted
100%
VASUNDHRAVasundhra-2  
587 🔗 707 174Construction work of interlocking tiles road and drain near Shani temple in Ramanujam Yadav market on Ramteeram Road, Ward-88. 1.72 07/12/2024 1.72 26 Dec 202418 Mar 2025 18 Mar 2025 A.P Const. NAGENDRA SHARMAJunior Engineer NIGAM NIDHI 2024-25Completed
100%
CITY ZONE Gandhi Nagar TurabNagar  
588 🔗 708 170Thermoplastic paint and cat eye work in city zone from Chaudhari mode to Daulatpura flyover, from Rakesh Marg to Shani Mandir, Dudheshwarnath Mandir and at various intersections on Patel Marg. 7.71 07/12/2024 7.71 31 Jan 202501 Mar 2025 01 Mar 2025 A.K.&Asso. Preeti BansalJunior Engineer NIGAM NIDHI 2024-25In Progress
0.00%
CITY ZONE    
589 🔗 709 173Thermoplastic paint and cat eye work at various intersections in City Zone from Thakurdwara to Meerut Tiraha, Nandgram Mode to Sihani Chungi, Sihani Police Chowki to Kalkagarhi via Aryanagar Square and Rajnagar Express. 8.98 07/12/2024 8.98 31 Jan 202517 Mar 2025 17 Mar 2025 Trinetra Infra Preeti BansalJunior Engineer NIGAM NIDHI 2024-25In Progress
0.00%
CITY ZONE    
Fund Name: MEMBER KOTA
590 🔗 710 194Work of raw site track interlocking tiles in front of Buddha Park and in front of the houses in front of 6/1 and 6/136 in Ward-86, Rajendra Nagar Sector-05. 8.16 09/09/2024 8.16 31 Jan 202520 Feb 2025 20 Feb 2025 Solanki Const. Sanjay GangwarJunior Engineer NIGAM NIDHI 2024-25Completed
100%
MOHAN NAGAR Rajendra Nagar Sec5  
591 🔗 557 156Road improvement work by CC from D 92 to D 113 in D Block of Ward 75, Lajpat Nagar and improvement work of RCC drain and CC road from D 184 to D 21. 29.85 12/09/2024 29.85 19 Sep 2024 15 Oct 2024  Vinod Kumar 8650930015 Junior Engineer MEMBER KOTACompleted
100%
MOHAN NAGARLajpat Nagar 1  
592 🔗 561 88Road repair work by laying interlocking tiles on the road behind Jain temple, the road between the temple and the park, and the road from the rear corner of Jain temple to Chaaya Public School and the road leading to the water tank in Ward 77 Sec 3, Vaishali. 13.48 10/09/2024 13.48 19 Sep 202415 Oct 2024 15 Oct 2024  POOJA SINGH 8178016909 Junior Engineer MEMBER KOTACompleted
100%
VASUNDHRAVaishali Sec 2  
593 🔗 562 98Road repair work by interlocking tiles of H.No. 339 to 357 and subsidiary road, park road and road from 236 to 288 in Ward 77 Sector 3, Vaishali. 13.67 10/09/2024 13.67 19 Sep 202415 Oct 2024 15 Oct 2024 V K CONTRACTOR 7982481495POOJA SINGH 8178016909 Junior Engineer MEMBER KOTACompleted
100%
VASUNDHRAVaishali Sec 2  
594 🔗 563 80Road repair work by laying interlocking tiles on the road from H.No. 177 to 235 and from Jitendra Singh Co. to New Hospital Road and from 69 to 91 in Ward 77 Sec 3 Vaishali. 13.46 10/09/2024 13.46 19 Sep 202415 Oct 2024 15 Oct 2024  POOJA SINGH 8178016909 Junior Engineer MEMBER KOTACompleted
100%
VASUNDHRAVaishali Sec 2  
595 🔗 564 183Construction work of damaged street by C.C. from plot no. 298 to plot no. 575 in ward 78, Shalimar Garden Ex-2. 25.07 12/09/2024 25.07 09 Nov 202412 Dec 2024 12 Dec 2024 Maheshn Cand Contr. Vinod KumarJunior Engineer MEMBER KOTACompleted
100%
MOHAN NAGAR Shalimar Garden X 1st  
596 🔗 565 otherConstruction work of damaged street from Ward 78 Shalimar Garden Plot No. 575 to Sachin Public School by C.C. 24.93 12/09/2024 24.93 19 Sep 202415 Oct 2024 15 Oct 2024  Vinod Kumar 8650930015 Junior Engineer MEMBER KOTACompleted
100%
MOHAN NAGARGagan Vihar  
597 🔗 566 122Repair work of damaged road from gate no. 1 to gate no. 2 in Anukampa Green Society in ward 79 Abhay Khand 2 and from H.No. 321 to 322 and H.No. 7 in Gyan Khand 1 by Dense. 18.19 10/09/2024 18.19 19 Sep 202416 Dec 2024 16 Dec 2024 R G BUILDTECH ENGINEERS LTD 9810616350POOJA SINGH 8178016909 Junior Engineer MEMBER KOTACompleted
100%
VASUNDHRAAbhay Khand  
598 🔗 567 104In Ward 79 Nyay Khand, from H.No. 8 to H.No. 25, H.No. 1039 to H.No. 508 and H.No. 513 to 540 and other subsidiary streets, construction of drains and road improvement work through CC. 25.68 10/09/2024 25.68 19 Sep 202415 Oct 2024 15 Oct 2024 R.R. Const. POOJA SINGHJunior Engineer MEMBER KOTACompleted
100%
VASUNDHRA Abhay Khand  
599 🔗 568 146Street improvement work by laying drain and interlocking tiles in the damaged street from Nagar Dairy to A/32 in Ward 80, Rajendra Nagar. 29.75 12/09/2024 29.75 19 Sep 202415 Oct 2024 15 Oct 2024 Ujjwal Const. Vinod KumarJunior Engineer MEMBER KOTACompleted
100%
MOHAN NAGAR Rajendra Nagar Sec2  
600 🔗 569 162Improvement work of damaged drain and street by interlocking tiles from A/205 to A/168 in ward 80 Rajendra Nagar. 20.26 12/09/2024 20.26 19 Sep 202415 Oct 2024 15 Oct 2024  Vinod Kumar 8650930015 Junior Engineer MEMBER KOTACompleted
100%
MOHAN NAGARRajendra Nagar Sec2  
601 🔗 570 126Repair work of damaged road from H.No. 570 to H.No. 720 along with green belt and adjacent to Mother Dairy booth no. 890 in ward 81 Niti Khand by DANS. 22.93 10/09/2024 22.93 19 Sep 202416 Dec 2024 16 Dec 2024 R G BUILDTECH ENGINEERS LTD 9810616350POOJA SINGH 8178016909 Junior Engineer MEMBER KOTACompleted
100%
VASUNDHRAShakti Khand  
602 🔗 571 71Repair work of damaged road from H.No. 354 to Aman Plaza and from Guptaji Sweets Corner to Park in Ward 81, Shakti Khand 4 by Dense. 27.70 10/09/2024 27.70 19 Sep 202415 Oct 2024 15 Oct 2024 PRATEEK ENTERPRISES 9311881082POOJA SINGH 8178016909 Junior Engineer MEMBER KOTACompleted
100%
VASUNDHRAShakti Khand  
603 🔗 572 151Construction work of drain and damaged street by C.C. from Tavdeep's house to Movie Palace Road in Ward 82, Jawahar Park. 10.15 12/09/2024 10.15 19 Sep 202415 Oct 2024 15 Oct 2024 Solanki Const. Vinod KumarJunior Engineer MEMBER KOTACompleted
100%
MOHAN NAGAR Jawahar Park  
604 🔗 573 177Construction work of drain and damaged street through C.C. from Billu's house to Bhatna Gad School in Ward 82, Jawahar Park. 14.23 12/09/2024 14.23 07 Oct 202425 Nov 2024 25 Nov 2024 Bijender Singh Vinod KumarJunior Engineer MEMBER KOTACompleted
100%
MOHAN NAGAR Jawahar Park  
Fund Name: NIGAM NIDHI 2024-25
605 🔗 574 179Construction work of drain and C.C. in the damaged street in Rasan wali gali in ward 82, Jawahar Park. 15.73 12/09/2024 15.73 19 Sep 202418 Nov 2024 18 Nov 2024 Bijender Singh Vinod KumarJunior Engineer MEMBER KOTACompleted
100%
MOHAN NAGAR Jawahar Park  
606 🔗 683 155Road improvement through drain and C.C. in Ward-03 Vijayanagar Sector-09, from K-119A to K-135 and in the street of Maa Bhagwati General Store. 9.67 26/07/2024 9.67 26 Dec 202430 Jan 2025 30 Jan 2025 Ariti Const.Co. SHIV KUMAR SAROJJunior Engineer NIGAM NIDHI 2024-25Completed
100%
VIJAY NAGARPurana Vijay Nagar  
607 🔗 684 156Repair work of damaged road from Parveen to Kishan in Ward-14 Sector-12 Sarvodayanagar by C.C. 8.21 03/09/2024 8.21 26 Dec 202430 Jan 2025 30 Jan 2025 Ariti Const.Co. SHIV KUMAR SAROJJunior Engineer NIGAM NIDHI 2024-25Completed
100%
VIJAY NAGARNew Vijay Nagar  
608 🔗 685 157Repair of damaged road from Sher Khan to Prabhas Sachiv to Naresh in Ward-58, Mawai Gali No.-06 by C.C. 9.79 03/09/2024 9.79 26 Dec 202430 Jan 2025 30 Jan 2025 VANSH CONSTRUCTIONS 9953776458SHIV KUMAR SAROJ 8178016826 Junior Engineer NIGAM NIDHI 2024-25Completed
100%
VIJAY NAGARShivpuri  
609 🔗 686 158Road improvement by interlocking tiles from Ward-55 D-Block H.No. 487 (Pravati) to corner of triangular park. 9.96 05/09/2024 9.96 26 Dec 202430 Jan 2025 30 Jan 2025 R.D. Enter. SHIV KUMAR SAROJJunior Engineer NIGAM NIDHI 2024-25Completed
100%
VIJAY NAGARVijay Nagar sec11 block-A  
610 🔗 687 156Ward-62 Govindpuram C-Lock C-278 via Primary School to C-274, road improvement through drain and Dense. 28.70 14/10/2024 28.70 26 Nov 202430 Dec 2025 30 Dec 2025  Rajender Singh 8178016904 Junior Engineer NIGAM NIDHI 2024-25Completed
100%
KAVI NAGARGovindpuram Harsav  
611 🔗 688 1Repair and painting work of Shri Pradeep Kumar's quarter in Ward-71 Sanjaynagar F-Block Tanki Compound. 1.21 05/12/2024 1.21 10 Feb 202508 Apr 2025 08 Apr 2025  Rajender Singh 8178016904 Junior Engineer NIGAM NIDHI 2024-25In Progress
70.00%
KAVI NAGARSanjay Nagar 2  
612 🔗 689 3Repair and painting work of Mr. Suresh Kumar's quarter in Ward-71 Sanjaynagar F-Block Tanki Compound. 1.13 05/12/2024 1.13 10 Feb 202508 Apr 2025 08 Apr 2025  Rajender Singh 8178016904 Junior Engineer NIGAM NIDHI 2024-25In Progress
70.00%
KAVI NAGARSanjay Nagar 2  
Fund Name: MEMBER KOTA
613 🔗 690 4Repair and painting work of Mr. Javed's quarter in Ward-91 Kavinagar Tanki Compound. 1.28 05/12/2024 1.28 31 Jan 202508 Apr 2025 08 Apr 2025  Rajender Singh 8178016904 Junior Engineer NIGAM NIDHI 2024-25In Progress
60.00%
KAVI NAGARKavi nagar  
Fund Name: NIGAM NIDHI 2024-25
614 🔗 575 154Dens door road improvement work of the damaged road from A-82 to 16 and A-74 in Ward 83 Shyampur X. 17.64 12/09/2024 17.64 19 Sep 202415 Oct 2024 15 Oct 2024 Prateek Enter. Vinod KumarJunior Engineer MEMBER KOTACompleted
100%
MOHAN NAGAR Shyam Park X  
615 🔗 691 2Repair and painting work of Mr. Sanjay Verma's quarter in Ward-91 Kavi Nagar Tanki Compound. 1.26 05/12/2024 1.26 31 Jan 202508 Apr 2025 08 Apr 2025  Rajender Singh 8178016904 Junior Engineer NIGAM NIDHI 2024-25In Progress
60.00%
KAVI NAGARKavi nagar  
616 🔗 692 25Construction work of side track from HIG C-12 to HIG C-34 in Ward 67, Sanjay Nagar. 6.82 21/10/2024 6.82 26 Dec 202426 Dec 2024 26 Dec 2024  Rajender Singh 8178016904 Junior Engineer NIGAM NIDHI 2024-25Completed
100%
KAVI NAGARKamla Nehru Nagar Sanjay Nagar 1  
617 🔗 693 157Road repair work through C.C. on the damaged road from Sher Khan to Prabhas, Sachin to Naresh in Ward 58, Mawai Street No. 06. 6.79 03/09/2024 6.79 26 Dec 202404 Feb 2025 04 Feb 2025 Vansh Const. SHIV KUMAR SAROJJunior Engineer NIGAM NIDHI 2024-25Completed
100%
VIJAY NAGARShivpuri  
618 🔗 694 otherRoad and drain repair work through C.C. on the damaged road from H.No. 173/1 to Choudhary Dham Singh, Pramod Kumar Sharma to Rajesh Master ji in Ward No. 26, Gaupuri. 8.47 02/12/2024 8.47 31 Jan 2025  A.H Const. SHIV KUMAR SAROJJunior Engineer NIGAM NIDHI 2024-25Completed
100%
VIJAY NAGARMadhopur Sundri  
619 🔗 695 5Work of drain and tiles from Rampal's house to Bhola Pandit's house in Ward-16, Sikrod village. 9.67 05/12/2024 9.67 31 Jan 202526 Apr 2025 26 Apr 2025 Chowdhary Associates Rajender SinghJunior Engineer NIGAM NIDHI 2024-25In Progress
0.00%
KAVI NAGAR Morta  
620 🔗 696 32Tiles work near health centre/water tank in Ward-16, Sikrod village. 4.29 05/12/2024 4.29 31 Jan 202526 Dec 2024 26 Dec 2024 CHAUDHARY ASSOCIATES 8860538129Rajender Singh 8178016904 Junior Engineer NIGAM NIDHI 2024-25Completed
100%
KAVI NAGARMorta  
621 🔗 697  Construction work of interlinking tiles road from house no. 487 (Pravati) to the corner of triangular park in ward-55, D block. 9.86 02/12/2024 9.86 31 Jan 2025  R.D.Enterprises 9555550801SHIV KUMAR SAROJ 8178016826 Junior Engineer NIGAM NIDHI 2024-25Completed
100%
VIJAY NAGARVijay Nagar sec11 block-A  
Fund Name: MEMBER KOTA
622 🔗 698 170Work of construction of culvert at Swadeshi Polytex Ltd. cut in Ward-65, Kavi Nagar Industrial Area. 5.66 24/10/2024 5.66 31 Jan 202526 Dec 2024 26 Dec 2024 A.K. Contr. & Builders Rajender SinghJunior Engineer NIGAM NIDHI 2024-25Completed
100%
KAVI NAGAR Vivekanand Nagar Jeevan Vihar  
623 🔗 576 144Dens door road improvement work of the damaged road from Anand Medical Store to Ambe Hospital Road in Ward 83 Shyampur X. 20.75 12/09/2024 20.75 19 Sep 202415 Oct 2024 15 Oct 2024 Prateek Enter. Vinod KumarJunior Engineer MEMBER KOTACompleted
100%
MOHAN NAGAR Shyam Park X  
624 🔗 577 otherIn Ward 84, Raj Nagar RDC, RDC-167 to RDC-173, RDC-166 to RDC-156, RDC-173 to RDC-156, RDC-22 to RDC-12, RDC-23 to RDC-29, RDC-36 to RDC-30, RDC-42 to RDC-55, RDC-66 to RDC-56, RDC-67 to RDC-77, RDC-85 to RDC-91, RDC-144 to RDC-138, Road improvement work by DANS from RDC-92 to RDC-114, RDC-131 to RDC-137. 22.18 10/09/2024 22.18 07 Oct 202416 Nov 2024 16 Nov 2024  Rajender Singh 8178016904 Junior Engineer MEMBER KOTACompleted
100%
KAVI NAGARRajNagar  
625 🔗 578 118Road improvement work of internal roads of Ward 84, Rajnagar Sector-10 by Dans. 20.04 10/09/2024 20.04 19 Sep 202415 Oct 2024 15 Oct 2024  Rajender Singh 8178016904 Junior Engineer MEMBER KOTACompleted
100%
KAVI NAGARRajNagar  
626 🔗 579 173Construction work of drain and interlocking in the damaged street from house no. 44 to house no. 63 and from Shiv Mandir to Chhabra Tyre in ward 85, Lajpat Nagar II, street no. 2. 27.46 12/09/2024 27.46 19 Sep 202415 Oct 2024 15 Oct 2024 Mohit Choudhary Vinod KumarJunior Engineer MEMBER KOTACompleted
100%
MOHAN NAGAR Lajpat Nagar 2  
627 🔗 580 172In ward 85 Lajpat Nagar, in F Block from F.131 to F.116 and F.131 to F.132 and F.61 to F.72, F.142 to S.155, F.142 to F.155 and F.122 to F.111, F.192 to F.196 and F.66 to F.21, in front of F.92 and other places, construction work by interlocking. 13.54 12/09/2024 13.54 19 Sep 202415 Oct 2024 15 Oct 2024 Mohit Choudhary Vinod KumarJunior Engineer MEMBER KOTACompleted
100%
MOHAN NAGAR Lajpat Nagar 2  
628 🔗 581 161Dens door road improvement work of the damaged road from SPS Apartment to Plot No. 09 in Ward 86, Rajendra Nagar Sector 05. 16.88 12/09/2024 16.88 19 Sep 202415 Oct 2024 15 Oct 2024  Vinod Kumar 8650930015 Junior Engineer MEMBER KOTACompleted
100%
MOHAN NAGARRajendra Nagar Sec5  
629 🔗 582 168Construction of drain work by RCC from SPS Apartment to Agarwal's house in Ward 86, Rajendra Nagar. 24.94 12/09/2024 24.94 19 Sep 202415 Oct 2024 15 Oct 2024 Univershal Vanchar Vinod KumarJunior Engineer MEMBER KOTACompleted
100%
MOHAN NAGAR Rajendra Nagar Sec5  
630 🔗 583 66In Ward-87 Nyay Khand 03, improvement work by interlocking tiles in house no. 596 to 592, house no. 501 to 512 via 480 and house no. 525G to 520 and house no. 459 to 457 and house no. 472 to 469, house no. 253 to 248 and house no. 237 via 230 to 232, house no. 821 to 800 and house no. 768 to 761 and house no. 445 to 461. 22.58 10/09/2024 22.58 19 Sep 202414 Oct 2024 14 Oct 2024 R.R. Const. POOJA SINGHJunior Engineer MEMBER KOTACompleted
100%
VASUNDHRA Gyankhand Indrapuram  
Fund Name: NIGAM NIDHI 2024-25
631 🔗 584 120Repair of damaged road from house no. 868 to Sneh General Store, house no. 860 to 872 and from Shiv Dairy to Vivekanand School in Ward-87, Nyay Khand 03, Indirapuram by Dense and work of interlocking tiles on side patri. 21.51 10/09/2024 21.51 19 Sep 202416 Dec 2024 16 Dec 2024 R G BUILDTECH ENGINEERS LTD 9810616350POOJA SINGH 8178016909 Junior Engineer MEMBER KOTACompleted
100%
VASUNDHRAGyankhand Indrapuram  
632 🔗 699  Repair and painting work of Smt. Kanta Devi's quarter in Ward 84, Rajnagar Sector-04 Tanki Compound. 2.38 02/12/2024 2.38 31 Jan 2025   Rajender Singh 8178016904 Junior Engineer NIGAM NIDHI 2024-25Not Started
0.00%
KAVI NAGARRajNagar  
633 🔗 700  Repair work of shelter homes built in wards 75, 37 and 70 in Mohannagar. 5.08 02/12/2024 5.08 31 Jan 2025   Vinod Kumar 8650930015 Junior Engineer NIGAM NIDHI 2024-25Completed
100%
MOHAN NAGARGagan Vihar Work done By quoutation
634 🔗 701 195Construction work of RCC wall around the garbage transfer station in Ward-44, Sanjay Colony and work of installing metro sheet from Purvanchal side. 19.86 14/10/2024 19.86 31 Jan 202520 Feb 2025 20 Feb 2025 Solanki Const. Sanjay GangwarJunior Engineer NIGAM NIDHI 2024-25Completed
100%
MOHAN NAGAR Sanjay Colony  
635 🔗 702 202Repair work of damaged rooms for storing belongings of service centre and garden staff in Ward-75, Lajpat Nagar. 5.24 22/10/2025 5.24 10 Feb 202515 Apr 2025 15 Apr 2025  Vinod Kumar 8650930015 Junior Engineer NIGAM NIDHI 2024-25In Progress
60.00%
MOHAN NAGARLajpat Nagar 1  
636 🔗 703 203Work of construction of store room in health garage at Ward-83, Shyampur Ex. 0.50 30/11/2024 0.50 10 Feb 202515 Apr 2025 15 Apr 2025  Vinod Kumar 8650930015 Junior Engineer NIGAM NIDHI 2024-25In Progress
0.00%
MOHAN NAGARShyam Park X  
637